Six Sigma Metrics Practice
Unlimited Six Sigma practice for the ASQ Green Belt and Black Belt exams: DPU and DPMO, first pass and rolled throughput yield, sigma level, Cp and Cpk, and control chart rules. Check my answer names the slip, such as leaving out the opportunities per unit or adding step yields instead of multiplying them.
Each sigma question says whether the 1.5 shift applies. Normal curve areas are computed, so a z table may differ in the last digit.
Exam practice
These metrics are CSSGB topics II.E.1, III.F.3 and III.F.4, and control charts are topic VI.A. Start with the free real exam questions, then get the full pack.
Six Sigma FAQ
Formulas used in the drill
- DPU = defects ÷ units.
- DPO = defects ÷ (units × opportunities per unit). DPMO = DPO × 1,000,000.
- Percent defective = defective units ÷ units × 100.
- FPY = (units in − scrapped − reworked) ÷ units in.
- RTY = FPY of step 1 × FPY of step 2 × every later step.
- Long-term Z = the z with the defect rate in the upper tail of the normal curve. With the 1.5 shift: sigma level = Z + 1.5.
- Cp = (USL − LSL) ÷ 6s. Cpk = the smaller of (USL − mean) ÷ 3s and (mean − LSL) ÷ 3s.
- PPM out of spec = (tail above USL + tail below LSL) × 1,000,000.
What is the difference between DPU and DPMO?
DPU is defects ÷ units. DPMO is defects ÷ (units × opportunities per unit) × 1,000,000, so it also counts how many ways each unit can go wrong. Both count every defect: a unit with three defects adds three, even though it is only one defective unit. The NIST e-Handbook draws the same line: a defective item has at least one defect.
Do I add the 1.5 sigma shift?
Only when the question asks for the short-term sigma level. ASQ gives the goal of a 6 sigma process as 3.4 defects per million opportunities. The normal curve has 3.4 per million beyond 4.5 standard deviations, so that 6 sigma figure includes a shift of 1.5. The 1.5 shift is the common Six Sigma convention, not a measured value; long-term Z has no shift. The CSSGB Body of Knowledge asks you to identify and calculate the sigma shift between short-term and long-term data.
Why does my DPMO come out half the table value?
You split the defects over two tails of the normal curve. A sigma level puts the whole defect rate in one tail: the z with that rate above it. A two-sided lookup halves the DPMO and pushes the sigma level up.
How do you calculate rolled throughput yield?
Multiply the first pass yield of every step: 98% × 95% × 99% = 92.17%. ASQ defines first pass yield as units entering − defective units, over units entering, so a reworked unit does not count as right first time. Averaging the yields, adding up the losses or dividing final output by input all give too high a number.
What is the difference between Cp and Cpk?
Cp = (USL − LSL) ÷ 6σ compares the spec width with the process width and ignores where the mean sits. Cpk = the smaller of (USL − mean) ÷ 3σ and (mean − LSL) ÷ 3σ, so it uses the nearer spec limit. In the NIST example (USL 20, LSL 8, mean 16, s 2), Cp is 1.0 but Cpk is only 0.67, because the mean sits 2 above the middle of the spec.
Which control chart rules does the drill use?
The Western Electric rules as the NIST e-Handbook lists them: any point beyond 3σ; 2 of the last 3 points beyond 2σ on the same side; 4 of the last 5 beyond 1σ on the same side; 8 points in a row on one side of the center line; 6 in a row trending up or down; 14 in a row alternating up and down. NIST notes that adding them to the 3σ limits raises false alarms from about 1 in 371 points to about 1 in 92.
Sources
- ASQ, Certified Six Sigma Green Belt Body of Knowledge (2022, PDF): II.E.1 process performance (DPU, RTY, DPMO, sigma levels, capability indices), III.F.3 Cp, Cpk, Pp and Ppk, III.F.4 short-term vs long-term capability and sigma shift, VI.A control charts.
- ASQ, Certified Six Sigma Black Belt Body of Knowledge (2022, PDF): V.F.1, V.F.2, V.F.6 and V.F.7 (capability, process sigma, DPMO, DPU, first pass yield, RTY), VIII.A.5 control chart analysis.
- ASQ, What Is Six Sigma?: a 6 sigma process means 3.4 defects per million opportunities.
- ASQ, Quality Glossary: first pass yield.
- NIST/SEMATECH e-Handbook of Statistical Methods, 6.1.6 What is Process Capability? (Cp, Cpk, Cpu, Cpl, the k method and its worked example).
- NIST/SEMATECH e-Handbook, 6.3.2 What are Variables Control Charts? (the Western Electric rules) and 6.3.3.1 Counts Control Charts (defects and defective units).
- The drill's own approach, where no official formula is published: DPU, DPO and DPMO follow from their names; RTY multiplies the step yields because a unit has to pass every step; the 1.5 shift is the common Six Sigma convention and every question says whether it applies. Normal curve areas are computed, not copied from a table.
- Checked 20 November 2026: the drill reproduces the NIST capability example exactly (Cp 1.0, k 0.3333, Cpk 0.6667, Cpu 0.6667, Cpl 1.3333) and ASQ's 3.4 DPMO at 6 sigma.
Checked 20 November 2026 against the ASQ CSSGB and CSSBB Bodies of Knowledge and the NIST/SEMATECH e-Handbook of Statistical Methods.
- DrillControl chart and reliability practiceWork out X-bar, R, p and c chart limits from the NIST factors and series, parallel and r out of n reliability.
- DrillISTQB test technique practiceEquivalence partitions, boundary values, decision tables, state transitions and code coverage.
- CalculatorEarned value and PERT calculatorSV, CV, SPI, CPI, EAC, ETC, VAC and TCPI from four numbers, plus PERT three-point estimates.