Earned Value Calculator: BAC, EAC and TCPI, plus PERT

This earned value calculator works out the estimate at completion (EAC), the to-complete performance index (TCPI) and every other earned value measure from four numbers. Enter the budget at completion (BAC), planned value (PV), earned value (EV) and actual cost (AC) to get SV, CV, SPI, CPI, EAC, ETC, VAC and TCPI, with what each one means. Below it is a PERT calculator for three-point estimates. Everything runs in your browser, and the formulas are the ones PMI publishes.

Earned value formulas

Measure Formula Reading it
Schedule variance (SV) EV - PV Positive: ahead. Negative: behind
Cost variance (CV) EV - AC Positive: under budget. Negative: over
Schedule performance index (SPI) EV / PV 1.0 = on pace
Cost performance index (CPI) EV / AC Below 1.0: each dollar buys less than a dollar of work
Estimate at completion (EAC) BAC / CPI Final cost if current cost efficiency continues
Estimate to complete (ETC) EAC - AC Cost of the remaining work (PMI defines EAC = AC + ETC)
Variance at completion (VAC) BAC - EAC Expected over or under at the finish
To-complete performance index (TCPI) (BAC - EV) / (BAC - AC) Efficiency needed from now on to hit the budget

A worked example

This is PMI's own example. You are four months into a $100,000 project (BAC). You planned to have finished $40,000 of work by now (PV), you have actually finished work worth $36,000 (EV), and you have spent $45,000 (AC).

  • SV = 36,000 - 40,000 = -4,000: a little behind plan.
  • CV = 36,000 - 45,000 = -9,000: you have spent more than the work is worth.
  • SPI = 36,000 / 40,000 = 0.90, and CPI = 36,000 / 45,000 = 0.80.
  • EAC = 100,000 / 0.80 = 125,000, so VAC = -25,000, and the remaining work will cost about 80,000 (ETC).
  • TCPI = 64,000 / 55,000 = 1.16: you would need to work 16% more efficiently than planned from now on to finish on budget.

Those are the default values in the calculator above, so you can check each step.

PERT and three-point estimates

PERT takes three duration estimates for an activity: optimistic (O), most likely (M) and pessimistic (P). PMI's Practice Standard for Scheduling gives the PERT duration as (O + 4M + P) / 6, which weights the most likely value four times. A plain average of the three, (O + M + P) / 3, is the triangular estimate. With O = 4, M = 6 and P = 14 days, PERT gives 7 days and the simple average gives 8.

Practise and learn

Keep the PMP formulas cheat sheet next to you, then test yourself with the free PMP practice test or the free CAPM practice test. Not sure which one to take? Read PMP vs CAPM. Want each formula explained in plain English first? PMCLEAR's free PMP lessons walk through earned value, EAC and the rest of the exam.

Earned value calculator FAQ

What is budget at completion (BAC)?
BAC is the total approved budget for the project: in PMI's words, what the whole job is budgeted to cost. You enter it, and the calculator works out EAC, VAC and TCPI from it.

What is a good CPI?
1.0 means you get exactly a dollar of planned work for each dollar spent. Above 1.0 is under budget and below 1.0 is over budget.

What is the difference between EAC and ETC?
EAC is the forecast total cost of the whole project. ETC is only the cost still to come. PMI defines EAC as AC plus ETC, so ETC = EAC - AC.

What does a TCPI above 1 mean?
You need to be more cost efficient from now on than you were planning to be, to finish within the budget. The further above 1, the harder that is.

Why is the PERT estimate weighted?
PERT gives the most likely duration four times the weight of the optimistic and pessimistic ones, so one extreme guess moves the estimate less than in a simple average.

Formulas last checked 20 November 2026 against PMI's "Earned Value Management: Reading the Numbers" on pmi.org and PMI's Practice Standard for Scheduling (second edition). The worked example is PMI's.