Critical Path Practice: Forward Pass, Backward Pass and Float

Free critical path practice for PMP, CAPM, PMI-SP and CompTIA Project+ students. Each generated network asks for one thing: the project duration, the critical path, or the early start, early finish, late start, late finish, total float or free float of one activity. Check my answer names the slip, such as the smallest predecessor EF taken instead of the highest, or one day off from the other way of counting days.

Check your answer to see the working.

Day 0 problems follow a conference paper in PMI's Learning Library, not the PMBOK Guide. Day 1 problems follow the US GAO Schedule Assessment Guide. Follow the method your course uses.

GAO gives no free float formula. The day 1 one here is derived from its rule that a successor starts the day after its predecessor finishes.

Finish to start links only, with no lags. Working on cost too? Try the earned value calculator.

Practise the exams

Start with the free real exam questions for your exam, then get the full pack.

PMI PMP
741 real exam questionsUS$39
Free: 169 questionsGet the full pack
PMI CAPM
517 real exam questionsUS$39
Free: 129 questionsGet the full pack
PMI-SP
320 real exam questionsUS$39
Free: 103 questionsGet the full pack
CompTIA Project+ PK0-005
625 real exam questionsUS$39
Free: 156 questionsGet the full pack

Critical path and float FAQ

The formulas in short
  • Day 0 forward pass: ES = highest predecessor EF, EF = ES + duration.
  • Day 0 backward pass: LF = lowest successor LS, LS = LF minus duration.
  • Day 1 forward pass: ES = highest predecessor EF + 1, EF = ES + duration minus 1.
  • Day 1 backward pass: LF = lowest successor LS minus 1, LS = LF minus duration + 1.
  • Total float: LS minus ES, or LF minus EF.
  • Free float, day 0: lowest successor ES minus EF. Day 1 (derived): lowest successor ES minus EF minus 1.
  • Critical path: the activities with total float 0. Their durations add up to the project duration.
How do you find the critical path?

Run the forward pass to get each early start (ES) and early finish (EF), then the backward pass to get each late finish (LF) and late start (LS), then work out the float. The PMI Learning Library paper says critical activities are those that do not possess any float, and that their durations add up to the project duration. It is the longest path through the network.

Does the first activity start on day 0 or day 1?

Both are in use, so check which one your course or question uses. The PMI Learning Library paper places a zero in the early start of the first activity, and EF = ES + duration. The US GAO Schedule Assessment Guide counts whole days from day 1: EF = ES + duration minus 1, and a successor starts on its predecessor's early finish plus 1 day. Every question in this drill states its method.

What changes between the day 0 and day 1 methods?

Only the start dates. ES and LS are 1 higher under day 1. EF and LF are the same numbers, and so are the project duration, the total float, the free float and the critical path.

What are the forward pass formulas?

Day 0 (PMI paper): ES = highest EF of the immediate predecessors, and EF = ES + duration. Day 1 (GAO): ES = latest predecessor EF plus 1 day, and EF = ES + duration minus 1. The project duration is the EF of the last activity.

What are the backward pass formulas?

Start by dropping the EF of the last activity down to its LF. Day 0 (PMI paper): LF = lowest LS of the immediate successors, and LS = LF minus duration. Day 1 (GAO): LF = earliest successor LS minus 1 day, and LS = LF minus duration + 1.

What is the difference between total float and free float?

Total float is how long an activity can be delayed without delaying the project completion date. Free float is how long it can be delayed without delaying any succeeding activity. An activity can have total float and no free float.

How do you calculate total float and free float?

Total float = LS minus ES, which is the same as LF minus EF (both sources). Free float = lowest ES of the successors minus EF in the PMI paper. GAO gives no free float formula, so for day 1 the drill derives one from GAO's rule that a successor starts the day after its predecessor finishes: lowest successor ES minus EF minus 1.

Can free float be larger than total float?

No. The PMI paper lists it as a check on your arithmetic: free float can never be larger than total float, and negative numbers should not appear for any calculated value.

Why is my answer one day off?

You have probably mixed the two methods: a plus 1 or minus 1 from the day 1 method in a day 0 problem, or the other way round. Take every date from one method. The drill names this slip when it sees it.

Is the PMI source the PMBOK Guide?

No. It is a conference paper in PMI's Learning Library: Kramer and Jenkins, Understanding the basics of CPM calculations, PMI Global Congress 2006. The PMBOK Guide is not quoted here.

What does the drill leave out?

Lags, leads, start to start and finish to finish links, date constraints, negative float, calendars and resources. Every network has one first activity, one last activity and exactly one critical path.

Sources
  • Project Management Institute, Learning Library: Understanding the basics of CPM calculations, a conference paper by S. W. Kramer and J. L. Jenkins (PMI Global Congress 2006), not the PMBOK Guide. Used for the day 0 method: a zero in the early start of the first activity, ES = highest predecessor EF, EF = ES + duration, LF = lowest successor LS, LS = LF minus duration, total float, free float, and critical activities as those with no float.
  • US Government Accountability Office, Schedule Assessment Guide (GAO-16-89G), Appendix IV: The Forward and Backward Pass and its Total Float page. Used for the day 1 method: EF = ES + duration minus 1, a successor starts on the predecessor's early finish plus 1 day, LS = LF minus duration + 1, LF = successor LS minus 1 day, and TF = LS minus ES or LF minus EF.
  • US Government Accountability Office, Schedule Assessment Guide, Definitions of Total Float and Free Float: free float is the part of total float available before the delay affects the immediate successor, and an activity with zero total float is critical.
  • Checked 21 November 2026. The tool's own approach: every network is invented; the day 1 free float formula is derived from the GAO rule above, because GAO prints no free float formula; the free float of the last activity is shown as 0 and never asked. The drill reproduces the worked example in GAO Appendix IV, and an independent re-solver that tries every path agreed with it on 24,000 generated problems.

Checked 21 November 2026 against the PMI Learning Library paper and the US GAO Schedule Assessment Guide.