Five of the 60 questions in this pack
Commercial negotiations on prices cover a range of aspects including pricing arrangements. A buyer may negotiate for a 'fixed price agreement'. Why is a fixed price agreement advantageous to the buyer?
- A. The buyer will benefit from the savings that the supplier makes from the efficient cost management of the contract
- B. The buyer will not need to monitor the supplier's costs relating to the contract
- C. Suppliers always seek price agreements that include cost sharing incentives
- D. Suppliers calculate prices using fixed costs which the buyer must counteract by pushing for a fixed price agreement
Show answer and explanation
Correct answer: B. The buyer will not need to monitor the supplier's costs relating to the contract
Under a fixed price agreement the buyer pays the agreed price whatever the supplier's costs turn out to be. The buyer therefore has no need to monitor the supplier's costs on the contract.
Why the other options are wrong
- A. Under a fixed price the supplier keeps any savings from efficient cost management, so the buyer does not benefit from them.
- C. Suppliers do not always want cost sharing incentives, and this says nothing about why a fixed price helps the buyer.
- D. This describes how suppliers build their prices, not an advantage of a fixed price to the buyer.
When considering a new supply source for a product, a procurement professional will review the suppliers' quotations before a supplier negotiation. Which of the following is a direct cost associated with the product within a potential supplier's quotation?
- A. Rent for the supplier's premises
- B. Insurance for production machinery
- C. Metal used in the product
- D. Wages for the supplier's sales department
Show answer and explanation
Correct answer: C. Metal used in the product
A direct cost can be traced to the product itself. The metal used in the product is a direct material cost.
Why the other options are wrong
- A. Rent for premises is an overhead shared across all production, so it is an indirect cost.
- B. Insurance for machinery is an overhead, not a cost traced to one product.
- D. Wages for the sales department are an overhead, not part of making the product.
Which of the following is a challenge when calculating absorption costing?
- A. Attributing a fair amount of overhead to each unit of production
- B. Attributing fair cost drivers and cost pools to each unit of production
- C. Understanding the profit element as a percentage of cost
- D. Understanding the profit element as a percentage of selling price
Show answer and explanation
Correct answer: A. Attributing a fair amount of overhead to each unit of production
Absorption costing shares overheads across the units produced. The difficulty is deciding what fair amount of overhead each unit should carry.
Why the other options are wrong
- B. Cost drivers and cost pools belong to activity-based costing, not absorption costing.
- C. Working out profit as a percentage of cost is a mark-up calculation done after costing, not a challenge of absorption costing.
- D. Working out profit as a percentage of selling price is a margin calculation done after costing, not a challenge of absorption costing.
John is discussing undertaking a post-negotiation review with Simone and states that 'a meeting with all stakeholders must be undertaken as it is the most effective way of getting feedback'. Is this statement correct?
- A. Yes, as it allows all stakeholders to be present physically
- B. Yes, it allows stakeholders to blame procurement for any failings
- C. No, there may be a more effective way to undertake the review
- D. No, John may only record what he believes is correct
Show answer and explanation
Correct answer: C. No, there may be a more effective way to undertake the review
A meeting with every stakeholder is not necessarily the most effective way to get feedback, so the statement is not correct. Other methods, such as questionnaires, may give more honest and useful feedback.
Why the other options are wrong
- A. Having everyone physically present does not make a meeting the most effective review method.
- B. A review is meant to learn lessons, not to give stakeholders a chance to blame procurement.
- D. A review should gather evidence from stakeholders, not just record what one person believes.
During a negotiation, Jose Gomez, the salesperson for a strategic supplier, states that his sales director will not approve discounts against initial purchases. However, Jose offers a 5% discount against the aftercare package, which will provide the same monetary saving. Sally Pampas requires both the product and the aftercare package and has an objective to achieve a 5% discount off the purchase price. To achieve a win-win (integrative) negotiation, Sally should __________.
- A. decline the offer and walk away from the negotiation
- B. accept the offer of a 5% discount against the aftercare package
- C. ask Jose to apply a 15% discount against the purchase price
- D. ask Jose to apply the 5% discount against the purchase price
Show answer and explanation
Correct answer: B. accept the offer of a 5% discount against the aftercare package
Jose cannot discount the purchase, but a 5% discount on the aftercare package gives Sally the same monetary saving. Accepting it meets her objective and keeps the deal, which is a win-win outcome.
Why the other options are wrong
- A. Walking away throws away an offer that already meets Sally's objective.
- C. Asking for 15% on the purchase price pushes for more than Jose can give and ignores his stated limit.
- D. Jose has already said discounts on the initial purchase will not be approved, so asking again stalls the negotiation.
Try CIPS L4M5 Commercial Negotiation free first
60 questions in the full pack- Free sample: 5 questions 5 real questions, every answer explained, in one PDF. Download PDF
- Full pack, $39.00 USD paid once All 60 questions, every answer explained, plus a questions-only PDF. Updates for life.Get the full pack
L4M5 exam questions with answers: all 60 for the CIPS Commercial Negotiation module.
This pack is the complete set, covering every part of the L4M5 Commercial Negotiation syllabus. Download the free sample to see the question style first.
- 60 exam practice questions: mapped to the L4M5 Commercial Negotiation syllabus
- Complete answers and explanations, including why every wrong option is wrong
- Questions-only PDF: for timed practice
- Email delivery: sent to your email within 24 hours
- Free monthly updates for life
You pay for this PDF once, with a refund if you fail anyway.
L4M5 exam questions: the short answers
What does L4M5 cover?
Approaches to negotiating commercial agreements with external parties, how to prepare for a negotiation and the techniques available, including costing and pricing.
Which qualification is L4M5 part of?
It is a core module of the CIPS Level 4 Diploma in Procurement and Supply.
What makes this exam hard
L4M5 tests how you prepare for and run a commercial negotiation. The sample questions here cover fixed price agreements, direct costs, absorption costing, reviewing a negotiation afterwards and choosing a win-win (integrative) outcome.
Many questions are short scenarios with named buyers and suppliers, so practise reading what the buyer is trying to achieve before looking at the options. Costing questions reward knowing the difference between direct costs and overheads.
Before you buy
Free questions
Real CIPS L4M5 Commercial Negotiation questions are free on the site, each with the answer explained.
What you get for $39.00 USD
- All 60 questions, each with the correct answer and why the other options are wrong
- 2 PDFs: the full pack, plus a questions-only copy for timed practice
- Delivered to your email within 24 hours
- Updated once a month, with free updates for life, emailed to the address you used at checkout
- Paid once
What do I get?
Every pack comes as 2 PDFs: one with every answer explained, and a questions-only copy for timed practice. This pack is delivered to your email within 24 hours, and every pack includes free updates for life.
How often are the questions updated?
Question sets are updated once a month. The date of the latest update is shown on every exam page.
Will I receive updates after purchasing?
Yes. All PDF purchases include lifetime updates. Updated versions are emailed automatically to the email address used during checkout.
What if an answer looks wrong?
We correct mistakes as we find them, and the monthly update sends those fixes to you. No question bank this size is ever completely flawless, so if something still looks off to you, check it against the vendor's own documentation and send it to support@dailydebian.com. We reply to every message, and the fix ships in the next update, free, for life.
Are your materials enough to pass the exam?
Most candidates use them as their main practice source. If you study with them and still fail, we refund you in full.
What happens if I fail my exam?
You get your money back. Email support@dailydebian.com within 14 days of receiving your results, with your order number and a copy of your official score report showing the fail. Requests are reviewed within 5 to 7 business days and approved refunds go back to the original payment method. Full terms are in the refund policy.
Do you have discount codes?
Yes, when you buy more than one exam pack. For 2 packs, use code BUY2 for 15% off. For 3 or more packs, use code BUY3 for 20% off. Enter the code in the discount box at checkout.
What payment methods do you accept?
Visa, Mastercard, American Express, UnionPay, Apple Pay, Google Pay, Shop Pay and PayPal. All prices are shown in your local currency at checkout.
Do you offer shipping?
No. All products are digital downloads. There is no physical shipping.
I did not receive my order after payment.
Contact support@dailydebian.com with your order number and payment confirmation details.