Question 1
What are common examples used to communicate risk probability and impact?
- A. Risk checklist, risk assessment, regression analysis, and assumption and constraint analysis
- B. Monitor Risks process, multi-dimensional risk assessment, control chart, and Monte Carlo simulation
- C. Probability distributions, sensitivity analysis, modeling and simulation, and probability and impact matrix
- D. Monitor Risks process, assumption and constraint analysis, modeling and simulation, and risk register
Show answer and explanation ▾
Correct answer: C
Probability distributions, sensitivity analysis, modeling and simulation, and the probability and impact matrix are the common tools for showing how likely a risk is and how large its effect could be.
Why the other options are wrong:
- A. A risk checklist and assumption analysis help to identify risks but do not communicate probability and impact.
- B. Monitor Risks is a process and a control chart tracks stability, so this is not a set of communication examples.
- D. The risk register records risks, but Monitor Risks and assumption analysis are not the common communication tools.
Question 2
When using the risk register to manage the cost risk analysis, which of the following models the way correlation arises, and avoids the need to estimate the correlation coefficients?
- A. Risk Monte Carlo analysis
- B. Risk driver method
- C. Risk scatter diagram
- D. Risk RACI matrix
Show answer and explanation ▾
Correct answer: A
A Monte Carlo analysis built on the risks in the risk register runs the cost model many times, so cost elements affected by the same risk move together in each iteration. The correlation between them arises from the model itself and does not have to be entered as coefficients.
Why the other options are wrong:
- B. The risk driver method is not the simulation technique this question describes for running the cost model.
- C. A scatter diagram plots two variables against each other to show a relationship; it does not model cost risk.
- D. A RACI matrix assigns roles and responsibilities and has nothing to do with correlation.
Question 3
Which of the following characteristics would a risk tolerant person or group demonstrate?
- A. Adaptable and resourceful; not afraid to take action; thrill seeking
- B. Discomfort with uncertainty; low tolerance for ambiguity; seeks security and resolution in the face of risk
- C. Risk taking is a price worth paying for future payoffs; seeks strategies and tactics that have high future payoffs; thinks abstractly and creatively envisioning possibilities, and not afraid of change or unknowns
- D. Reasonable comfort with most uncertainty; accepts risk as a normal feature of projects and business, and takes uncertainty in stride with no apparent or significant influence on their behavior
Show answer and explanation ▾
Correct answer: D
A risk tolerant person or group is reasonably comfortable with most uncertainty and accepts risk as a normal part of projects and business. The uncertainty has no apparent or significant influence on how they behave.
Why the other options are wrong:
- A. Being adaptable, resourceful and thrill seeking describes a risk seeking attitude.
- B. Discomfort with uncertainty and a low tolerance for ambiguity describe a risk averse attitude.
- C. Trading short-term risk for high future payoffs and thinking abstractly describe a risk neutral attitude.
Question 4
The risk manager organizes a stakeholder meeting to obtain agreement on project risk response strategies. At the conclusion of this meeting, the risk response strategies should be which of the following?
- A. Scheduled, budgeted, and easy for project stakeholders to understand
- B. Cost-effective, validated by Monte Carlo analysis, and assigned
- C. Iterative, scaled to the project, and addressing threats and opportunities
- D. Timely, cost-effective, agreed-upon, and accepted
Show answer and explanation ▾
Correct answer: D
After the meeting the response strategies should be timely, cost-effective, agreed on by stakeholders and accepted. Agreement is the purpose of the meeting.
Why the other options are wrong:
- A. Being scheduled and budgeted matters, but agreement and acceptance are what the meeting is meant to produce.
- B. Monte Carlo validation is not required for every response strategy.
- C. Being iterative and scaled to the project does not cover timely, agreed and accepted.
Question 5
A new resource is added to the project team from a matrix organization.
How should the project's risk manager familiarize the new team member with the project's risk management process?
- A. The functional manager is responsible for providing the training.
- B. Provide project specific risk training and mentor through the risk process.
- C. Send the new team member the risk management plan to read.
- D. Provide the new team member with a copy of the risk register and latest status report.
Show answer and explanation ▾
Correct answer: C
The risk management plan documents how risk management is structured and performed on the project, including the methodology, roles, timing, categories and definitions. Reading it gives a new team member the project's risk process in the form the team has agreed to follow.
Why the other options are wrong:
- A. The functional manager manages the resource's line work and does not own the project's risk process.
- B. Training and mentoring take more effort and are not the documented description of the process.
- D. The risk register and status report show current risks and progress, not how the risk process works.
Question 6
The stakeholder is unwilling to make decisions that would result in negative consequences to the project.
Which of the following describes the stakeholder's attitude regarding project risks?
- A. Risk averse
- B. Risk neutral
- C. Risk accepting
- D. Not enough information available to describe the stakeholder's risk attitude
Show answer and explanation ▾
Correct answer: A
A risk averse stakeholder is uncomfortable with uncertainty and avoids decisions that could lead to negative consequences. Unwillingness to accept any downside for the project is the defining sign of this attitude.
Why the other options are wrong:
- B. A risk neutral stakeholder weighs short-term risk against long-term payoff instead of avoiding negative outcomes.
- C. A risk accepting stakeholder would be willing to live with possible negative consequences.
- D. The described behavior is enough to identify the attitude.
Question 7
A project manager is developing the risk management process and schedules a risk planning workshop at the start of the project. Upon receiving the invitation, a senior stakeholder emails the project manager stating that a risk management plan is not needed since this is a small project, and lack of a plan will reduce costs.
Which of the following should the project manager do?
- A. Advise the stakeholder that risk management is a valuable undertaking and must be applied to all projects to some degree.
- B. Cancel the workshop, as the stakeholder is senior and risk management is an optional process, especially on smaller projects.
- C. Continue with the workshop, but remove the stakeholder from the list of attendees.
- D. Review the scope in an attempt to save money in other areas of the project to provide funding for the risk management activities.
Show answer and explanation ▾
Correct answer: A
Risk management adds value on every project because every project carries uncertainty. The effort is scaled to the size, complexity and importance of the project, so a small project gets a lighter process, not none.
Why the other options are wrong:
- B. Risk management is not optional, and seniority does not remove the need for it.
- C. Excluding the stakeholder leaves the objection unresolved and loses the stakeholder's input.
- D. Cutting scope elsewhere does not address the stakeholder's belief that risk planning is unnecessary.
Question 8
What is a project issue within a project environment?
- A. A negative effect on a project objective arising from occurrence of a threat
- B. A certain event which has a positive or negative impact in the project
- C. A risk which has a significant impact on the project
- D. An uncertain event which may impact the project
Show answer and explanation ▾
Correct answer: A
A risk is an uncertain event that may or may not happen. Once a threat actually occurs and has a negative effect on a project objective, it is no longer a risk and is managed as an issue.
Why the other options are wrong:
- B. An issue is a negative condition that has occurred, not an event with a positive impact.
- C. A risk with a significant impact is still uncertain and remains a risk until it occurs.
- D. An uncertain event that may affect the project is the definition of a risk.
Question 9
What is the purpose of mitigating negative risks as a part of the risk response process?
- A. To transfer the probability of a risk happening to a third party, and to reduce the severity of the impact
- B. To reduce the probability of a risk happening, and/or reduce the severity of the impact
- C. To accept the probability of a risk happening to reduce the severity of the impact
- D. To increase the probability of a risk happening, but reduce the severity of the impact
Show answer and explanation ▾
Correct answer: B
Mitigation is early action that reduces the probability that a threat occurs, the severity of its impact, or both, bringing the risk within acceptable threshold limits.
Why the other options are wrong:
- A. Shifting a risk to a third party is the transfer strategy.
- C. Taking the risk as it is describes the accept strategy.
- D. Mitigation never aims to increase the probability of a threat.
Question 10
In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to the project cancellation.
How should the probability and impact be characterized for this risk?
- A. Low probability/low impact
- B. High probability/low impact
- C. Low probability/high impact
- D. High probability high impact
Show answer and explanation ▾
Correct answer: D
The customs delay is described as likely to occur, which is a high probability. The consequence could be cancellation of the project, which is the most severe impact possible, so the risk is high probability and high impact.
Why the other options are wrong:
- A. A likely event that could cancel the project is neither low probability nor low impact.
- B. Possible project cancellation is a high impact, not a low one.
- C. The delay is described as likely, so the probability is high.
Question 11
A risk is identified and documented by the risk manager, but it is unclear how this risk can be proactively managed. In this situation, what type of reserve should be allocated for the risk?
- A. Contingency
- B. Management
- C. Budget
- D. Residual
Show answer and explanation ▾
Correct answer: A
Contingency reserve is the time or money set aside for identified risks, including those that are accepted because no proactive response is practical. The risk here is identified and documented, so it is a known risk covered by contingency.
Why the other options are wrong:
- B. Management reserve covers unforeseen work and unidentified risks, and this risk has been identified.
- C. Budget reserve is not a defined reserve type for individual risks.
- D. Residual describes the risk that remains after a response, not a type of reserve.
Question 12
Which of the following is an effective channel for risk mitigation assistance, project risk visibility and risk escalation support?
- A. Project steering committee
- B. Project management office (PMO)
- C. Change control board (CCB)
- D. Board of directors
Show answer and explanation ▾
Correct answer: B
The project management office supports projects across the organization with methods, expertise and reporting. That makes it an effective channel for help with mitigation, visibility of project risks and support when a risk has to be escalated.
Why the other options are wrong:
- A. A steering committee gives direction and decisions on one project and is not a working support channel.
- C. The change control board reviews and decides on change requests.
- D. The board of directors governs the organization and does not support individual project risks day to day.
Question 13
The risk manager wants to determine what is to be measured, how it is to be measured, and what project outcomes are to be measured. In which of the following processes should this be established?
- A. Initiating Process
- B. Executing Process
- C. Planning Process
- D. Monitoring and Controlling Process
Show answer and explanation ▾
Correct answer: C
What will be measured, how it will be measured and which outcomes will be tracked are defined during planning and recorded in the risk management plan. Later processes use those definitions; they do not create them.
Why the other options are wrong:
- A. Initiating authorizes the project and does not define the measurement approach.
- B. Executing carries out the plan that already holds these definitions.
- D. Monitoring and controlling applies the measures that were set in planning.
Question 14
Which of the following are examples of relevant data gathering tools?
- A. Risk response plan and interviews
- B. Questionnaires and historical data
- C. Work breakdown structure and historical data
- D. Work breakdown structure and interviews
Show answer and explanation ▾
Correct answer: B
Questionnaires collect information from many people in a structured way, and historical data brings in what happened on earlier projects. Both are data gathering tools that feed risk identification and analysis.
Why the other options are wrong:
- A. A risk response plan is an output of response planning, not a data gathering tool.
- C. The work breakdown structure is a scope document, not a data gathering tool.
- D. The work breakdown structure is a scope document, not a data gathering tool.
Question 15
The risk manager is conducting stakeholder analysis.
Which technique should be used to help identify and manage expectations?
- A. SWOT analysis
- B. Influence diagram
- C. Power/Interest Grid
- D. Interactive method
Show answer and explanation ▾
Correct answer: C
A power/interest grid groups stakeholders by their level of authority and their level of concern about the project. The grouping shows who must be managed closely, kept satisfied, kept informed or monitored, which is the basis for managing expectations.
Why the other options are wrong:
- A. SWOT analysis examines strengths, weaknesses, opportunities and threats, not stakeholders.
- B. An influence diagram shows causal relationships among variables in a decision.
- D. Interactive method is not a stakeholder analysis technique.
Question 16
What steps would be used during the qualitative risk analysis process to provide input to the risk register?
- A. Select risks characteristics, collect and analyze data, prioritize risks, categorize risks causes, document results
- B. Interviews, expert opinions, sponsor inputs, risk manager review, prioritize risks, and document results
- C. Interviews, expert opinions, risk manager review, prioritize risks, and document results
- D. Select risks characteristics, collect and analyze data, prioritize risks, discuss action plans for major risks, document results
Show answer and explanation ▾
Correct answer: A
Qualitative risk analysis selects the risk characteristics to assess, collects and analyzes data on them, prioritizes the risks, groups them by cause and documents the results. Those results update the risk register.
Why the other options are wrong:
- B. This lists information sources and reviewers, not the steps of the analysis.
- C. This lists information sources and reviewers, not the steps of the analysis.
- D. Discussing action plans belongs to risk response planning, not qualitative analysis.
Question 17
A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures.
The current executive sponsor believes the project is in good shape based on feedback from the last project manager and reports this to senior executive management. The executive sponsor believes there were no major risks threatening the time, budget, or quality of the project. In the first week of risk analysis, the project manager concludes the project timeline is unrealistic and is three months behind schedule. The organization's risk appetite is low.
What is the first step that should be taken?
- A. Review the project schedule and recommend fast tracking the schedule and/or crashing the critical path.
- B. Discuss the project schedule with the executive sponsor and agree on a strategy for updating the risk management plan and risk response plans.
- C. Update existing risk response plans and include more resources to get the project back on track.
- D. Immediately call a steering committee meeting, report the project status, and suggest project scope reductions to save time.
Show answer and explanation ▾
Correct answer: B
The sponsor holds a view of the project that the analysis has shown to be wrong, so the first step is to share the findings with the sponsor. Agreeing together on how to update the risk management plan and response plans fits the organization's low risk appetite.
Why the other options are wrong:
- A. Compressing the schedule before the sponsor agrees on the situation adds risk and skips the needed discussion.
- C. Adding resources and changing response plans without sponsor agreement acts ahead of approval.
- D. Going to the steering committee first bypasses the sponsor who engaged the project manager.
Question 18
During what process should a project manager assign a risk owner?
- A. Plan Risk Responses
- B. Plan Risk Management
- C. Monitor Risks
- D. Identify Risks
Show answer and explanation ▾
Correct answer: D
During Identify Risks each risk is recorded in the risk register together with a potential risk owner. Naming the owner as soon as the risk is identified makes sure someone is responsible for it through analysis and response planning.
Why the other options are wrong:
- A. By Plan Risk Responses the owner is already in place and helps develop the response.
- B. Plan Risk Management defines roles and the approach but does not deal with individual risks.
- C. Monitor Risks tracks risks that already have owners.
Question 19
A risk manager wants to determine which risks are going to have the highest impact on a project.
Which of the following techniques should the risk manager use?
- A. Assumptions analysis
- B. Sensitivity analysis
- C. Root cause analysis
- D. Prioritization matrices
Show answer and explanation ▾
Correct answer: B
Sensitivity analysis shows which individual risks or other sources of uncertainty have the most potential impact on project outcomes. The results are often shown as a tornado diagram ranked from the largest effect to the smallest.
Why the other options are wrong:
- A. Assumptions analysis tests whether project assumptions are valid.
- C. Root cause analysis finds the underlying causes of a risk or problem.
- D. Prioritization matrices rank options against weighted criteria and do not measure impact on outcomes.
Question 20
Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks.
How could the situation be improved for the future?
- A. Cross train others to reduce the SME workload.
- B. Introduce scope reductions to limit the reliance on SMEs.
- C. Replace the SME with resources, who are responsible for receiving output from the SME on their deliverables.
- D. Extend the project schedule timeline to accommodate availability of the SME.
Show answer and explanation ▾
Correct answer: A
Cross training spreads the expert's knowledge to other people, so the work no longer depends on one person's availability. That removes the cause of the delays for future work.
Why the other options are wrong:
- B. Reducing scope gives up deliverables instead of fixing the resource constraint.
- C. People who only receive the expert's output cannot replace the expert's knowledge.
- D. Extending the schedule accepts the delay and leaves the dependency in place.
Question 21
In what way can the risk manager determine when poor risk planning techniques are influencing the scope, schedule, quality, and/or budget of the project?
- A. Evaluate the results of the Monte Carlo analysis
- B. Document and periodically update project risk information
- C. Monitor project metrics and performance information
- D. Update the risk management plan
Show answer and explanation ▾
Correct answer: C
Project metrics and work performance information show how scope, schedule, quality and cost are actually performing against the plan. Variances and trends in that data reveal when weak risk planning is affecting the project.
Why the other options are wrong:
- A. Monte Carlo results model possible outcomes and do not show actual performance.
- B. Updating risk information records the risks but does not reveal their effect on performance.
- D. Updating the plan is an action taken after the problem is detected.
Question 22
The company board is concerned about potential legal action from a high-risk project
What technique can be used to justify risk response decisions taken on this project?
- A. Interviews
- B. Nominal group technique
- C. Brainstorming
- D. Decision tree analysis
Show answer and explanation ▾
Correct answer: D
Decision tree analysis lays out each alternative with its costs, probabilities and outcomes and calculates the expected monetary value of each path. That gives a documented, numerical basis for the response chosen.
Why the other options are wrong:
- A. Interviews gather opinions and information and do not justify a decision numerically.
- B. Nominal group technique ranks ideas by structured voting within a group.
- C. Brainstorming generates ideas and does not evaluate alternatives.
Question 23
The project manager generates a monthly risk report for key stakeholders which documents high and medium risk items only.
Where would the project manager find the list of recipients for the report?
- A. Communications management plan
- B. Risk management plan
- C. Risk register
- D. Project charter
Show answer and explanation ▾
Correct answer: A
The communications management plan records who receives each piece of project information, in what format and how often. The distribution list for a recurring risk report is found there.
Why the other options are wrong:
- B. The risk management plan defines reporting formats for risk but the recipients of project reports are held in the communications management plan.
- C. The risk register holds the risks and their details, not report recipients.
- D. The project charter authorizes the project at a high level and has no distribution lists.
Question 24
A CEO wants to reduce costs in the time spent for risk management activities.
What step did the risk manager fail to perform?
- A. Assigning the CEO as a risk owner
- B. Preventing all issues from occurring
- C. Properly communicating the risk management activities and their outcomes
- D. Explaining the purpose of the management reserve
Show answer and explanation ▾
Correct answer: C
An executive who wants to cut risk management time has not seen what the activities deliver. Communicating the activities and their outcomes shows the value of risk management and maintains support for it.
Why the other options are wrong:
- A. Making the CEO a risk owner does not show the value of the risk process.
- B. No risk process can prevent every issue from occurring.
- D. Management reserve is one budget element and does not explain the value of risk activities.
Question 25
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve.
From which of the following sources should the funds be drawn to cover the risk mitigation?
- A. Organization management reserve
- B. Unplanned risk reserve
- C. Contingency reserve
- D. Management reserve
Show answer and explanation ▾
Correct answer: C
The risk was on the risk register, so it is an identified risk. Responses to identified risks are funded from the contingency reserve, which is part of the cost baseline, while management reserve is held for unidentified risks.
Why the other options are wrong:
- A. An organization management reserve is not the funding source for an identified project risk.
- B. Unplanned risk reserve is not a defined project reserve.
- D. Management reserve is for unforeseen work and unidentified risks, and this risk was identified.
Question 26
Which tool can the project risk manager utilize to help identify and assess project risks?
- A. Risk audit
- B. Risk surveys
- C. Risk manager interviews
- D. Risk sensitivity surveys
Show answer and explanation ▾
Correct answer: B
Risk surveys collect views from stakeholders and team members on what could affect the project and how serious each item is. The responses help both to identify risks and to assess them.
Why the other options are wrong:
- A. A risk audit examines the effectiveness of responses and of the risk process.
- C. Interviewing the risk manager is not a tool for gathering risks from the project's stakeholders.
- D. Risk sensitivity surveys are not a recognized risk identification tool.
Question 27
The project manager is unable to obtain a global consensus of competing subject matter experts and stakeholders on the project scope. This has caused a one-month delay.
What should the project manager do next to reduce further delay?
- A. Initiate a scope change request.
- B. Schedule a project kick-off meeting.
- C. Schedule a stakeholder meeting.
- D. Engage the project sponsor/portfolio manager.
Show answer and explanation ▾
Correct answer: C
The delay comes from disagreement among experts and stakeholders about scope. A stakeholder meeting brings the parties together to work through the differences and reach agreement, which is the direct way to stop further delay.
Why the other options are wrong:
- A. A scope change request cannot be raised while the scope itself has not been agreed.
- B. A kick-off meeting launches agreed work and does not resolve a scope disagreement.
- D. Escalating to the sponsor comes after the project manager has tried to resolve the conflict directly.
Question 28
A risk is identified early in the project. After six months, it is determined that the risk does not apply to this particular project.
How should the risk be handled by the risk manager?
- A. Ignore the risk and concentrate only on the pertinent risks.
- B. Remove the risk from the risk register and inform the project manager that it is no longer valid.
- C. Close the risk during the next risk board meeting and keep it in the risk register.
- D. Conduct a risk analysis to determine how an inappropriate risk was formally accepted.
Show answer and explanation ▾
Correct answer: C
A risk that no longer applies is formally closed through the agreed review process and its record stays in the risk register. The register then keeps the history for audits and for lessons learned on later projects.
Why the other options are wrong:
- A. Ignoring the risk leaves an open entry that no longer reflects the project.
- B. Removing the entry deletes the history that later reviews and projects rely on.
- D. Identifying a risk that later proves irrelevant is normal and does not call for an investigation.
Question 29
Who is ultimately responsible for monitoring a risk that is about to exceed its risk threshold?
- A. Any project stakeholder
- B. Project management office
- C. Senior manager
- D. Risk action owner
Show answer and explanation ▾
Correct answer: D
Each risk has a named person responsible for watching it and acting on it. When a risk approaches its threshold, that assigned owner is responsible for monitoring it and making sure the agreed actions are carried out.
Why the other options are wrong:
- A. Stakeholders may report concerns but are not accountable for monitoring a specific risk.
- B. The project management office supports the process and does not own individual risks.
- C. A senior manager may receive escalations but does not monitor individual risks.
Question 30
The sponsor hires a program manager as a consultant to evaluate a change program currently underway. The leading program manager tells the consultant that the program, currently in the execution phase, is in good standing, and detailed plans are available for review. The consultant reviews the project documentation and talks to the stakeholders, finding the opposite to be true. The project must be in recovery mode to get it back on track, and it is still in the planning phase.
There is low morale among the team members, the meetings are poorly managed, the detailed schedule has gaps, the risk register has not been updated for months, communications and detailed resource plans do not exist, and contract negotiations with a key vendor are behind schedule for critical deliverables.
What is the first course of action the program manager should take based on the current state?
- A. Cancel or put the project on hold, and hire a new program manager.
- B. Assess the risk management plan and adjust it accordingly to accommodate the gaps.
- C. Continue the project and create the project documentation that is missing.
- D. Meet with the project sponsor to report current findings, review current risk management plan and develop a corrective course of action.
Show answer and explanation ▾
Correct answer: D
The sponsor engaged the consultant to evaluate the program, and the findings contradict what has been reported. The first action is to report the findings to the sponsor, review the current risk management plan and agree on a corrective course of action.
Why the other options are wrong:
- A. Cancelling the work or replacing the manager is the sponsor's decision and needs the findings first.
- B. Adjusting the plan before the sponsor knows the real status skips the reporting step.
- C. Continuing while filling in documents does not address the true state of the program.
Question 31
Which of the following is the primary project artifact used to capture risks, strategies, ownership patterns, and other vital information about an organization's project risk baseline?
- A. Risk action plan with owners
- B. Risk register
- C. Mitigation plan
- D. Risk management plan
Show answer and explanation ▾
Correct answer: B
The risk register is the project document that records each identified risk with its description, analysis results, response strategy, owner and status. It is the main record of the project's risks.
Why the other options are wrong:
- A. An action plan with owners covers response actions only.
- C. A mitigation plan covers the response to particular threats, not the full record of risks.
- D. The risk management plan describes how risk management is performed and does not list individual risks.
Question 32
The project manager receives an updated project schedule from a sub team detailing the deliverables, dates, and durations for a critical milestone on the development and testing for off-shore activities. This report is received one hour before a meeting with the chief executive officer (CEO) to present an updated master schedule of the critical path. The CEO has been promised a discussion on the project schedule several times. However, based on the recent update from the off-shore team, the project manager realizes this new schedule is not realistic. There are new risks associated with it and it is not well thought out. Some key stakeholders want to present this revised plan to the CEO. This meeting has been postponed twice already.
Which action should the project manager take before meeting with the CEO?
- A. Talk to the stakeholders before the meeting to discuss the options and ask their opinion.
- B. Present the revised master schedule to the CEO with the caveat that it is being updated as new information is received, and these are the current dates at this point.
- C. Request the meeting be re-scheduled before presenting the master schedule to the CEO, stating that new major risks were identified and need to be assessed thoroughly.
- D. Present the revised schedule to the CEO and only answer questions about validity, if asked.
Show answer and explanation ▾
Correct answer: C
The project manager knows the new schedule is unrealistic and carries risks that have not been assessed. Asking to reschedule, and saying why, avoids presenting information known to be unreliable and gives time to assess the new risks properly.
Why the other options are wrong:
- A. Asking stakeholders for opinions an hour beforehand does not make the schedule reliable.
- B. Presenting dates the project manager believes are unrealistic misleads the CEO, even with a caveat.
- D. Presenting the schedule and staying silent about its validity withholds known problems.
Question 33
During a weekly project review meeting, a stakeholder identifies some new risks.
When creating risk responses for these newly identified risks, what should the project team do to discover trends and more efficiently manage the responses?
- A. Classify the risk impacts based on their severity.
- B. List workaround solutions.
- C. Identify the risk owners.
- D. Determine the root causes.
Show answer and explanation ▾
Correct answer: A
Classifying the new risks by the severity of their impact groups them in a consistent way. The grouping makes patterns visible and lets the team focus response effort where the consequences are greatest.
Why the other options are wrong:
- B. Workarounds are unplanned responses to events that have already happened.
- C. Naming owners assigns responsibility but does not reveal trends.
- D. Root cause work is not the grouping step this question asks for.
Question 34
Due to lack of specific knowledge within a technical domain, the project manager decides an expert from outside the organization should be invited into the project to identify and analyze risks. The project manager understands that the risk management process has many benefits, but it will also have clear costs.
Which of the following should the project manager do?
- A. Identify internal resources with proper knowledge, and keep costs down.
- B. Hire experts as needed.
- C. Hire a specialized risk analysis consulting company.
- D. Determine that the benefits outweigh the costs where risk is involved.
Show answer and explanation ▾
Correct answer: D
Risk management effort should be worth what it costs. Before bringing in an outside expert, the project manager confirms that the benefit of identifying and analyzing the technical risks outweighs the cost of doing so.
Why the other options are wrong:
- A. The stem states that the specific knowledge is lacking inside the organization.
- B. Hiring without weighing cost against benefit ignores the costs the project manager has recognized.
- C. Engaging a consulting company without weighing cost against benefit ignores the costs the project manager has recognized.
Question 35
A project team is conducting initial risk planning.
What other risk-related task should the project manager perform?
- A. Identifying the risk threshold
- B. Determining the risk register headings
- C. Scoring the risks utilizing the risk matrix
- D. Prioritizing the risks in the risk register
Show answer and explanation ▾
Correct answer: A
Risk planning sets the stakeholders' risk appetite and the measurable thresholds that express it. Those thresholds are recorded in the risk management plan and guide later analysis and response decisions.
Why the other options are wrong:
- B. Choosing register headings is a formatting detail, not a core planning task.
- C. Scoring risks happens in qualitative analysis, after risks are identified.
- D. Prioritizing risks happens in qualitative analysis, after risks are identified.
Question 36
A company is executing a high-visibility project to develop mobile phone technology. The project sponsor is concerned that an overall high risk rating may undermine support for the project within the company. The sponsor has instructed the project manager to manipulate the data used for Monte Carlo simulation to artificially reduce the risk rating.
What should the project manager do?
- A. Schedule a face-to-face meeting with the project sponsor.
- B. Modify the data.
- C. Ignore the request.
- D. Email the project sponsor explaining why the data should not be modified.
Show answer and explanation ▾
Correct answer: A
Manipulating analysis data conflicts with the honesty required by the PMI Code of Ethics and Professional Conduct. Meeting the sponsor face to face lets the project manager address the concern directly, explain why the data must stay accurate and look for legitimate ways to handle it.
Why the other options are wrong:
- B. Changing the data to lower the rating is dishonest reporting.
- C. Ignoring the request leaves the sponsor's concern and the conflict unresolved.
- D. Email is a weak channel for a sensitive disagreement that calls for a direct conversation.
Question 37
The project manager schedules a third workshop to facilitate the qualitative risk analysis. One team member complains that they should not have iterative meetings, but rather, should complete this at the beginning of the project.
Which of the following should the project manager do?
- A. Continue with the workshop, but discipline the team member for undermining the authority of the project manager.
- B. Agree with the team member, as qualitative analysis should only be performed during the initial stages of a project.
- C. Proceed with the meeting, but remove the team member from the invitees' list.
- D. Explain that it is good practice to perform qualitative analysis throughout the life of the project.
Show answer and explanation ▾
Correct answer: D
Risk management is iterative. Qualitative analysis is repeated through the project because new risks appear and the probability and impact of existing risks change.
Why the other options are wrong:
- A. Disciplining a team member for raising a question damages openness in the team.
- B. Qualitative analysis is not limited to the initial stages of a project.
- C. Excluding the team member removes input and leaves the misunderstanding in place.
Question 38
Which of the following situational factors has a significant effect on risk attitude?
- A. The risk heuristics evaluation available to the project team during planning and execution
- B. The perception of probability or frequency of occurrence and the perception of impact magnitude
- C. The number of project team members with close relationships to the chief executive officer (CEO)
- D. The number of external stakeholders and the potential for indirect consequences
Show answer and explanation ▾
Correct answer: B
Risk attitude is a response to uncertainty that is driven by perception. How likely or frequent a risk seems and how large its impact seems strongly shape the attitude a person or group adopts.
Why the other options are wrong:
- A. A heuristics evaluation being available to the team is not a main driver of risk attitude.
- C. Personal relationships with the CEO do not determine risk attitude.
- D. The count of external stakeholders is not what shapes how a risk is perceived.
Question 39
What are the supporting elements for effective risk management?
- A. Trained core people, matrix organization, simple scalable process, and tools and techniques
- B. Competent people, collaborative organization, rigorous process, and tools and techniques
- C. Competent people, supportive organization, simple scalable process, and tools and techniques
- D. Competent people, functional organization, policy, and tools and techniques
Show answer and explanation ▾
Correct answer: C
Effective risk management depends on competent people, an organization that supports the practice, a simple process that scales to the project, and suitable tools and techniques.
Why the other options are wrong:
- A. A matrix organization is a structure type, not a supporting element of risk management.
- B. The process should be simple and scalable, not rigorous for its own sake.
- D. A functional organization and policy alone do not make risk management effective.
Question 40
Upon returning from vacation, the risk manager observes during the project status meeting that several activities being accomplished were not in the original plan.
What should the risk manager do first?
- A. Meet with the project team.
- B. Inform management of out-of-scope work.
- C. Review activities for new risks.
- D. Review the change control log.
Show answer and explanation ▾
Correct answer: D
Work that was not in the original plan may have been added through approved changes. Checking the change control log first shows whether the activities were authorized before any other action is taken.
Why the other options are wrong:
- A. Meeting the team comes after the facts about approved changes are known.
- B. Reporting out-of-scope work is premature until the log shows the work was not approved.
- C. Reviewing the activities for new risks follows once their approval status is confirmed.
Question 41
As part of identifying the risk appetite of project stakeholders, the project manager must first identify the stakeholders.
Which of the following inputs are used to identify project stakeholders?
- A. Project charter, management reserve, enterprise environmental factors, and organizational process assets
- B. Project management plan, human resource plan, enterprise environmental factors, and organizational process assets
- C. Project charter, bid documents, enterprise environmental factors, and organizational process assets
- D. Project charter, communications management plan, enterprise environmental factors, and organizational process assets
Show answer and explanation ▾
Correct answer: D
Stakeholders are identified using the project charter, components of the project management plan such as the communications management plan, enterprise environmental factors and organizational process assets.
Why the other options are wrong:
- A. Management reserve is a budget element, not an input for identifying stakeholders.
- B. The human resource plan is not an input for identifying stakeholders.
- C. This set leaves out the communications management plan.
Question 42
After applying several risk identification techniques, the risk manager is ready to document project risks in the risk register, including risk name, risk statement, probability of occurring, and potential impact. After this information is complete, who is best suited to serve as risk owners?
- A. Risk manager
- B. Project sponsors
- C. Project manager
- D. Project team members
Show answer and explanation ▾
Correct answer: D
A risk owner should be the person best placed to manage the risk, which usually means someone working in the affected area. Project team members hold that detailed knowledge and can monitor the risk and carry out its response.
Why the other options are wrong:
- A. The risk manager facilitates the process and does not own every risk.
- B. Sponsors provide support and funding and are too far from the work to own most risks.
- C. The project manager is accountable for the project overall and cannot own every individual risk.
Question 43
Which of the following should the risk manager consider as external environmental factors when creating the risk management plan?
- A. Government regulations, industry best practice templates, organizational standard processes, and competitor landscape
- B. Government regulations, industry standards, conditions of the marketplace, and competitor landscape
- C. Government regulations, risk categories, organizational standard processes, and competitor landscape
- D. Government regulations, human resource policies and procedures, organizational standard processes, and competitor landscape
Show answer and explanation ▾
Correct answer: B
External enterprise environmental factors are conditions outside the organization's control, such as government regulations, industry standards, marketplace conditions and the competitor landscape.
Why the other options are wrong:
- A. Templates and organizational standard processes are organizational process assets.
- C. Risk categories and organizational standard processes are internal to the organization.
- D. Human resource policies and organizational standard processes are internal to the organization.
Question 44
Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?
- A. Change management plan and lessons learned
- B. Stakeholder register and lessons learned
- C. Risk audit and lessons learned
- D. Risk audit and risk matrix
Show answer and explanation ▾
Correct answer: C
Risk audits examine how effective risk responses were, and lessons learned record what worked and what did not. Both are archived from past projects in the organizational process assets.
Why the other options are wrong:
- A. A change management plan describes how changes are handled, not how well responses worked.
- B. A stakeholder register lists stakeholders and says nothing about response effectiveness.
- D. A risk matrix rates probability and impact and does not record how responses performed.
Question 45
Which analysis method uses stratified sampling without replacement?
- A. Latin Hypercube
- B. Monte Carlo simulation
- C. Impact analysis
- D. Linear regression analysis
Show answer and explanation ▾
Correct answer: A
Latin Hypercube sampling divides each input distribution into equal-probability intervals and draws one sample from each interval without replacement. This stratified approach covers the whole distribution with fewer iterations.
Why the other options are wrong:
- B. Standard Monte Carlo simulation uses simple random sampling across the whole distribution.
- C. Impact analysis is not a sampling method.
- D. Linear regression fits a line to data and is not a sampling method.
Question 46
In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to project cancellation.
Why should a mitigation plan be developed for this risk?
- A. This is a financial risk.
- B. This task is on the critical path.
- C. A response plan should be developed for all risks.
- D. This is a high-priority risk.
Show answer and explanation ▾
Correct answer: D
The risk is likely to occur and could lead to project cancellation, so it has high probability and high impact. High-priority risks warrant proactive responses such as a mitigation plan.
Why the other options are wrong:
- A. The risk concerns customs delays, and its category is not the reason for a mitigation plan.
- B. The stem does not state that the task is on the critical path.
- C. Low-priority risks can be accepted or placed on a watch list without a mitigation plan.
Question 47
A race director is planning a marathon with US$80,000 in upfront costs that will be offset by race fees. The remainder of the funds will be donated to a national charity. State law mandates that all money paid by the participants must be refunded if the race is cancelled for any reason.
Which of the following is the best example of a risk mitigation response?
- A. Let the runners know the race will be cancelled only in the event of an emergency.
- B. Purchase an insurance policy covering up to US$85,000 in losses, at a cost of US$5,000, in the event the race is cancelled.
- C. Inform the charity that they will receive no funds should the race be cancelled.
- D. Charge the runners an additional amount to cover the US$80,000.
Show answer and explanation ▾
Correct answer: B
The insurance policy is the only option that actively reduces the financial loss the organizers would bear if the race is cancelled. For a cost of US$5,000 it covers the upfront costs that would otherwise be lost.
Why the other options are wrong:
- A. Telling runners when the race might be cancelled does not reduce the loss.
- C. Informing the charity communicates the consequence and does not reduce the loss.
- D. State law requires all money paid by participants to be refunded, so extra fees give no protection.
Question 48
The risk manager for a construction project graphically groups project risks by the subsets of economic risk, social risk, and technical risk.
Where has this information been captured?
- A. Risk breakdown structure
- B. Risk management plan
- C. Risk register
- D. Risk control plan
Show answer and explanation ▾
Correct answer: A
A risk breakdown structure is a hierarchical, graphical representation of risks grouped by category and subcategory. Economic, social and technical risk are examples of such categories.
Why the other options are wrong:
- B. The risk management plan describes the approach; the graphical grouping itself is the breakdown structure.
- C. The risk register lists individual risks and their details in tabular form.
- D. Risk control plan is not a standard risk management artifact.
Question 49
When considering human factors and risk attitudes relative to the risk process, which approach should be used to influence the risk management process for optimal effects at the individual and group levels?
- A. Agile
- B. Reactive
- C. Ongoing
- D. Proactive
Show answer and explanation ▾
Correct answer: D
Human factors and risk attitudes affect every step of the risk process. They need to be understood and managed proactively, so that attitudes are recognized and adjusted before they distort decisions by individuals and groups.
Why the other options are wrong:
- A. Agile is a delivery approach, not a way of managing risk attitudes.
- B. A reactive approach deals with attitudes only after they have already affected decisions.
- C. Ongoing describes frequency and does not state the approach needed.
Question 50
What identification technique is used to help reduce the ambiguity of a risk statement?
- A. Driver, risk, outcome
- B. Exploit, risk, accept
- C. Probability, risk, impact
- D. Cause, risk, effect
Show answer and explanation ▾
Correct answer: D
Structured risk statements, also called risk metalanguage, separate the cause, the uncertain event and its effect on objectives. Writing each risk in that three-part form removes confusion between causes, risks and effects.
Why the other options are wrong:
- A. Driver, risk, outcome is not the standard structure for a risk statement.
- B. Exploit and accept are response strategies, not parts of a risk statement.
- C. Probability and impact are assessed for a risk and do not describe it.
Question 51
During the initial risk planning process, the risk manager and project manager discuss ways to handle known risks.
Which project reserve should the project manager use to budget for known risks?
- A. Budget reserve
- B. Contingency reserve
- C. Change management reserve
- D. Risk reserve
Show answer and explanation ▾
Correct answer: B
Contingency reserve is the budget within the cost baseline that is allocated for identified, or known, risks. It funds accepted risks and planned contingent or mitigating responses.
Why the other options are wrong:
- A. Budget reserve is not a defined reserve type for known risks.
- C. Change management reserve is not a defined project reserve.
- D. Risk reserve is a loose term and is not the specific reserve for known risks.
Question 52
During the risk Monitor and Control Project Work process, the scope, schedule, and cost begin to increase.
What outputs should be updated and/or created?
- A. Project management plan, project documents, and human resource plan
- B. Change requests, project management plan, and project documents
- C. Change requests, cost plan, and project documents
- D. Enterprise environmental factors, change requests, and project management plan
Show answer and explanation ▾
Correct answer: B
The outputs of Monitor and Control Project Work include change requests, project management plan updates and project documents updates. Growth in scope, schedule and cost is handled by raising change requests and updating the plan and documents.
Why the other options are wrong:
- A. This set omits change requests, which are needed to act on the variances.
- C. The cost plan is one component, while the whole project management plan is updated.
- D. Enterprise environmental factors are an input, not an output to be updated.
Question 53
The project enters a testing phase to validate a project requirement. The testing is occurring in a common company testing area maintained by operations. The project team accepts the external customer's additional testing requirements, which may cause a slip in the schedule. A risk is identified, added to the risk register, and a response is developed.
What is the next step to be completed?
- A. Inform the external customer that the project manager has added the schedule risk to the register.
- B. Hire more resources to ensure the original schedule is maintained.
- C. Communicate and monitor the risk response with testing and operations.
- D. Resist the customer's scope increase to maintain the original testing requirements.
Show answer and explanation ▾
Correct answer: C
Once a risk is recorded and a response is developed, the response has to be communicated to the affected parties and then monitored. Testing and operations share the test area and are the groups that must know about and act on the response.
Why the other options are wrong:
- A. Telling the customer a risk was logged does not carry out or track the response.
- B. Hiring resources is a new response that was not the one developed.
- D. The team has already accepted the customer's additional requirements.
Question 54
A project team's risk facilitator identifies a number of risks and must prioritize them based on the organization's risk appetite levels.
Which technique should be used?
- A. PERT
- B. Stakeholder risk profile analysis
- C. Project scope statement analysis
- D. Monte Carlo technique
Show answer and explanation ▾
Correct answer: B
Stakeholder risk profile analysis grades and qualifies the risk appetite and tolerance of the project's stakeholders. Knowing those levels lets the facilitator rank risks in line with what the organization is willing to accept.
Why the other options are wrong:
- A. PERT is a three-point estimating technique for durations and costs.
- C. Analyzing the scope statement clarifies deliverables, not appetite for risk.
- D. Monte Carlo is a quantitative simulation and does not capture risk appetite.
Question 55
While preparing for a project review meeting with leadership, the project team analyzes and checks its scope activities and discovers missing requirements. The project risk manager decides to hire a subcontractor to fulfill these newly discovered requirements.
What risk strategy did the project risk manager use?
- A. Avoid
- B. Transfer
- C. Accept
- D. Mitigate
Show answer and explanation ▾
Correct answer: B
Hiring a subcontractor to deliver the newly found requirements shifts the work, and the risk of delivering it, to a third party under a contract. Shifting ownership of a risk to another party is the transfer strategy.
Why the other options are wrong:
- A. Avoidance would remove the requirements or the threat altogether.
- C. Acceptance means taking no action unless the risk occurs.
- D. Mitigation reduces probability or impact while the team keeps the risk.
Question 56
During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customer's electrical infrastructure. This event was originally identified as a risk during earlier stages of the project and the associated risk response indicated a plan to purchase a new power adapter.
Which project fund will be used to cover this cost?
- A. Management reserve
- B. Management budget
- C. Project budget
- D. Contingency reserve
Show answer and explanation ▾
Correct answer: D
The incompatibility was an identified risk with a planned response. The cost of carrying out a planned response to an identified risk is paid from the contingency reserve.
Why the other options are wrong:
- A. Management reserve is for unidentified risks and unforeseen work.
- B. Management budget is not a defined project fund for risk responses.
- C. Risk response costs are drawn from the reserve set aside for identified risks, not from general work budgets.
Question 57
Which of the following demonstrates that a company's risk management process is successful?
- A. Projects deemed too risky are given additional time.
- B. The number of identified risks has decreased.
- C. Profitability has increased due to the risk management process.
- D. Additional resources were added to complete the project faster.
Show answer and explanation ▾
Correct answer: C
Risk management succeeds when it helps the organization achieve its objectives. Higher profitability that results from the risk process is direct evidence that the process is delivering value.
Why the other options are wrong:
- A. Giving risky projects more time is a decision, not evidence that the process works.
- B. Fewer identified risks may simply mean weaker identification.
- D. Adding resources to finish faster is a schedule tactic and not a measure of risk management.
Question 58
A heavy industrial design firm has over USS3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project.
What is the most effective method to capture these opportunities?
- A. Integrate them into the RBS.
- B. Schedule a project team meeting.
- C. Formally notify the project manager.
- D. Establish a contingency reserve.
Show answer and explanation ▾
Correct answer: D
High-priority opportunities need resources before they can be pursued. Setting aside a contingency reserve provides the time and money to act on the opportunity responses when the conditions arise.
Why the other options are wrong:
- A. Placing opportunities in the risk breakdown structure only categorizes them.
- B. A team meeting discusses the opportunities but does not provide the means to pursue them.
- C. Notifying the project manager passes on information and does not capture the opportunity.
Question 59
How can the project manager rank competing stakeholder priorities for all the identified risks?
- A. Perform qualitative and quantitative risk analysis.
- B. Engage the project sponsor to decide.
- C. Refer to stakeholder analysis prioritization tree.
- D. Perform a review of organizational process assets.
Show answer and explanation ▾
Correct answer: A
Qualitative and quantitative risk analysis rate every identified risk on agreed scales and on its measured effect on objectives. That objective ranking replaces competing opinions with a common basis for priority.
Why the other options are wrong:
- B. Asking the sponsor to decide substitutes one opinion for analysis.
- C. A stakeholder analysis prioritization tree is not a recognized technique for ranking risks.
- D. Organizational process assets provide history and templates, not a ranking of current risks.
Question 60
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks.
Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?
- A. Scope reduction to reduce SME reliance
- B. Risk management plan and planned risks responses
- C. Risk identification process and participation
- D. Detailed review of the project schedule before approval
Show answer and explanation ▾
Correct answer: C
Limited availability of a critical expert is a resource risk that thorough risk identification with the right participants should have found. Reviewing how identification was run, and who took part, shows the project manager where the process fell short.
Why the other options are wrong:
- A. Reducing scope changes the deliverables and is not a coaching area for the risk process.
- B. Responses cannot be planned for a risk that was never identified.
- D. A schedule review checks dates and logic and does not address the missed risk.
Question 61
Which of the following characteristics would a risk-adverse person or group demonstrate?
- A. Reasonable comfort with most uncertainty; accepts risk as a normal feature of projects and business, and takes uncertainty in stride with no apparent or significant influence on their behavior.
- B. Risk taking is a price worth paying for future payoffs; seeks strategies and tactics that have high future payoffs; thinks abstractly and creatively envisioning possibilities, and is not afraid of change oi unknowns.
- C. Discomfort with uncertainty; low tolerance for ambiguity, and seeks security and resolution when facing risk.
- D. Adaptable and resourceful, and is not afraid to take action, or even thrill seeking.
Show answer and explanation ▾
Correct answer: C
A risk averse person or group feels uncomfortable with uncertainty, has a low tolerance for ambiguity and looks for security and resolution when facing risk.
Why the other options are wrong:
- A. Reasonable comfort with most uncertainty describes a risk tolerant attitude.
- B. Accepting risk for high future payoffs and thinking abstractly describe a risk neutral attitude.
- D. Being adaptable, resourceful and thrill seeking describes a risk seeking attitude.
Question 62
A project manager has a two-month project with three project team members. The project sponsor does not agree with the project manager that a risk planning process is necessary, since the project is very small.
Would it be appropriate for the project manager to implement some level of risk management?
- A. Yes, even small projects may require risk planning.
- B. No, small projects do not usually require risk planning.
- C. No, risk planning should be initiated with the sponsor's consent.
- D. Yes, the risk planning process implementation is ultimately the project manager's decision.
Show answer and explanation ▾
Correct answer: A
Every project carries uncertainty, so some level of risk management applies to all projects. The process is scaled to the project, and a small two-month project needs a simple plan, not no plan.
Why the other options are wrong:
- B. Small projects still face risks that need planning.
- C. The need for risk planning comes from the project's uncertainty, not from the sponsor's consent.
- D. The reason is the value of risk planning on any project, not the project manager's authority.
Question 63
Which of the following would a proactive risk manager do during the Monitoring and Controlling Process?
- A. Develop risk responses, create risk management plan, and stay alert for risk events.
- B. Update the lessons learned documents, develop risk responses, and create the risk management plan.
- C. Review identified risks, stay alert for risk events, and remind team members to keep the risk manager informed about risk triggers.
- D. Review lessons learned document to identify risks, quantify risks, and lower impact ratings.
Show answer and explanation ▾
Correct answer: C
During monitoring and controlling, a proactive risk manager reviews the identified risks, watches for risk events and makes sure team members report trigger conditions early. These actions keep the risk register current and let planned responses start on time.
Why the other options are wrong:
- A. Developing responses and creating the risk management plan are planning activities, not monitoring and controlling work.
- B. Creating the risk management plan and developing responses belong to planning, not to monitoring and controlling.
- D. Quantifying risks and lowering impact ratings are analysis activities, and ratings are not lowered as a routine monitoring step.
Question 64
A stakeholder is asked to approve additional funding to implement a risk response plan. However, the stakeholder is unsure of the amount that could be approved without escalation.
Where should the stakeholder look to determine the amount that can be approved?
- A. Project charter
- B. Risk management plan
- C. Risk register
- D. Organizational process assets
Show answer and explanation ▾
Correct answer: B
The risk management plan sets out roles, responsibilities, budgeting and the protocols for applying contingency and management reserves. It is where a stakeholder finds the approval limits and escalation rules for funding a risk response.
Why the other options are wrong:
- A. The project charter authorizes the project at a high level and does not define approval limits for risk response funding.
- C. The risk register lists the risks and their responses, not the authority levels for approving funds.
- D. Organizational process assets hold general policies and templates, not this project's agreed risk funding and escalation rules.
Question 65
A cost analyst team member asks the project manager for the latest risk data for inclusion with the cost estimates for the project.
Which tool should the cost analyst team member use to identify the probability of achieving specific cost targets?
- A. Monte Carlo analysis
- B. Decision tree analysis
- C. Analogous estimating
- D. Brainstorming
Show answer and explanation ▾
Correct answer: A
Monte Carlo analysis runs the cost model many times with values drawn from probability distributions. The resulting cumulative distribution shows the probability of meeting any chosen cost target.
Why the other options are wrong:
- B. Decision tree analysis compares alternative decisions by expected value, it does not give the probability of meeting a cost target.
- C. Analogous estimating bases an estimate on similar past projects and produces no probability of achieving a target.
- D. Brainstorming is a technique for gathering ideas and risks, not for calculating probabilities.
Question 66
The project manager is implementing a computer interface to facilitate communications between two ticketing systems for two major companies in the IT industry.
During the Plan Risk Response process, the project team agrees on the contingency plan that should mitigate the negative impact of the risk.
However, during the project execution, one of the subject matter experts identifies a residual risk that was not taken into consideration during the risk response planning session, but could potentially affect the project schedule baseline.
What should the risk manager do to handle this residual risk?
- A. Increase the management reserve.
- B. Analyze this risk and update the risk register.
- C. Accept the risk, since it is minor.
- D. Reject the risk, since the risk plan will take care of all the risks.
Show answer and explanation ▾
Correct answer: B
A newly recognized residual risk is treated like any other risk: it is analyzed for probability and impact and recorded in the risk register so that it can be monitored and given a response if needed.
Why the other options are wrong:
- A. Management reserve is for unknown unknowns and is not increased before the risk has been analyzed.
- C. The risk cannot be called minor and accepted before it has been analyzed.
- D. A risk that was missed in response planning is not covered by the existing plan and cannot simply be rejected.
Question 67
The risk management process can be defined as which of the following?
- A. Iterative through the planning phase
- B. Baselined at the beginning of execution
- C. Iterative throughout the entire project
- D. Updated in the execution phase
Show answer and explanation ▾
Correct answer: C
Risk management is iterative across the whole project life cycle. New risks appear and existing risks change as the project progresses, so identification, analysis, response planning and monitoring are repeated until the project closes.
Why the other options are wrong:
- A. The process does not stop being repeated when the planning phase ends.
- B. Risk management is not a baseline that is fixed at the start of execution.
- D. Updating is not limited to the execution phase, it happens throughout the project.
Question 68
A risk manager creates a survey for project stakeholders to obtain their opinions on high levels of risk. Key questions in the survey address acceptable levels of cost increases and schedule delays.
What is the risk manager trying to determine?
- A. Risk urgency
- B. Risk exposure
- C. Risk threshold
- D. Risk attitude
Show answer and explanation ▾
Correct answer: C
A risk threshold is the measurable level of variation around an objective that stakeholders will accept. Asking how much cost increase and schedule delay is acceptable defines those thresholds.
Why the other options are wrong:
- A. Risk urgency describes how soon a response is needed, not how much variation is acceptable.
- B. Risk exposure measures the combined probability and impact of risks, not the acceptable limits.
- D. Risk attitude is the general disposition toward uncertainty, not a measurable limit on cost or schedule variation.
Question 69
Which of the following will ultimately determine risk thresholds?
- A. The absolute value of the consequence
- B. The risk appetite of the key stakeholders
- C. The practice standard for risk management
- D. The project manager
Show answer and explanation ▾
Correct answer: B
Risk thresholds express stakeholder risk appetite in measurable terms. The degree of uncertainty the main stakeholders are willing to take on in pursuit of the objectives sets the limits above which a risk is not accepted.
Why the other options are wrong:
- A. The absolute size of a consequence does not set the limit, the same consequence is acceptable to one organization and not to another.
- C. A practice standard gives guidance on good practice and does not set a project's thresholds.
- D. The project manager documents and applies the thresholds but does not ultimately determine them.
Question 70
Which of the following represents levels of risk attitude?
- A. Conservative, moderate, and liberal
- B. Risk-averse, risk-neutral, risk-tolerant, risk-seeking
- C. Risk-mitigating, risk-avoiding, risk-transferring, risk-accepting
- D. High, medium, and low
Show answer and explanation ▾
Correct answer: B
Risk attitude runs along a spectrum from risk-averse, through risk-tolerant and risk-neutral, to risk-seeking. Each level describes how comfortable a person or group is with uncertainty.
Why the other options are wrong:
- A. Conservative, moderate and liberal are not the standard levels of risk attitude.
- C. Mitigating, avoiding, transferring and accepting are risk response strategies, not attitudes.
- D. High, medium and low are rating levels for probability or impact, not attitudes.
Question 71
Which of the following should multicultural groups be aware of on a project relative to risk?
- A. Problematic risk management practices
- B. Multicultural beta risk management software
- C. Differences regarding risk attitudes and emotional literacy
- D. "Parent-child" risk relationships
Show answer and explanation ▾
Correct answer: C
Risk attitudes and the way people recognize and express emotions about risk vary between cultures. A multicultural team must be aware of these differences, because they affect how risks are perceived, reported and handled.
Why the other options are wrong:
- A. Problematic practices are a general concern on any project and are not specific to multicultural groups.
- B. Multicultural beta risk management software is not a recognized risk management concept.
- D. Parent-child risk relationships describe how risks are structured, not a cultural factor.
Question 72
Project stakeholders identify, analyze, and plan the risk responses for a project. However, the contingency reserves are depleted before the project is completed.
What recommendation could be implemented to prevent this from recurring?
- A. Use the Monte Carlo simulation.
- B. Implement a reserve analysis process.
- C. Conduct more frequent reserve watch list status meetings.
- D. Increase the contingency reserve.
Show answer and explanation ▾
Correct answer: B
Reserve analysis compares the contingency reserve remaining with the amount of risk remaining at any point in the project. Performing it regularly shows early whether the reserve is still adequate, before it runs out.
Why the other options are wrong:
- A. Monte Carlo simulation helps size a reserve but does not track how the reserve is being consumed.
- C. Watch list meetings cover low priority risks and do not compare the remaining reserve with the remaining risk.
- D. Simply increasing the reserve does not provide a process to detect or prevent depletion.
Question 73
During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customer's electrical infrastructure. This event was not originally identified as a risk. To maintain the project schedule, the project manager decides to purchase a new power adapter.
What type of response best describes this course of action?
- A. Contingency plan
- B. Management plan
- C. Fall-back plan
- D. Workaround
Show answer and explanation ▾
Correct answer: D
A workaround is an unplanned response to a risk event that was not identified or was passively accepted. Buying an adapter after the unidentified incompatibility appears is a workaround.
Why the other options are wrong:
- A. A contingency plan is prepared in advance for an identified risk, and this event was never identified.
- B. A management plan describes how the project is run and is not a type of risk response.
- C. A fallback plan is prepared in advance for use when the primary response fails.
Question 74
After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget.
What is the forecasting methodology that should be utilized to calculate the impact?
- A. Estimate to complete (ETC)
- B. Budget at completion (BAC)
- C. Estimate risk completion (ERC)
- D. Estimate at completion (EAC)
Show answer and explanation ▾
Correct answer: D
Estimate at completion forecasts the total cost of the project from actual costs to date plus the expected cost of the remaining work. Recalculating it with the three risks included shows their effect on the budget.
Why the other options are wrong:
- A. Estimate to complete forecasts only the remaining work, not the total impact on the budget.
- B. Budget at completion is the original approved budget and is not a forecast.
- C. Estimate risk completion is not an earned value forecasting term.
Question 75
A risk has been identified in a multi-functional project. The project manager decides to take no action.
What type of response is this considered?
- A. Avoidance
- B. Exploitation
- C. Procrastination
- D. Acceptance
Show answer and explanation ▾
Correct answer: D
Acceptance acknowledges a risk and takes no action unless it occurs. Deciding to do nothing about an identified risk is passive acceptance.
Why the other options are wrong:
- A. Avoidance requires action to eliminate the threat, such as changing the project plan.
- B. Exploitation is a strategy for opportunities and requires action to make sure the opportunity happens.
- C. Procrastination is not a risk response strategy.
Question 76
Which of the following could be included in risk monitoring and controlling techniques?
- A. Status review meetings, trend analysis, earned value analysis, McGregor's analysis, defect repair, inspection
- B. Status review meetings, variance analysis, trend analysis, earned value analysis, inspection, control charts
- C. Status review meetings, control charts, Inspection, defect repair, Maslow's analysis, trend analysis
- D. Variance analysis, trend analysis, earned value analysis, Maslow's analysis, control charts, brainstorming
Show answer and explanation ▾
Correct answer: B
Status review meetings, variance analysis, trend analysis, earned value analysis, inspection and control charts all compare actual performance with the plan. They reveal deviations that signal emerging or changing risks.
Why the other options are wrong:
- A. McGregor's analysis concerns motivation theory and defect repair is a corrective action, neither is a risk monitoring technique.
- C. Maslow's analysis concerns motivation theory and defect repair is a corrective action, neither is a risk monitoring technique.
- D. Maslow's analysis concerns motivation theory, and brainstorming is an identification technique.
Question 77
The company is a risk seeking organization, and has experienced measurable success based on their current strategy for growth. A new project has that exceeds the risk levels documented in the risk management plan.
What would be the best course of action for the company to take with the project based on its current scope?
- A. Monitor ongoing risks closely for any major changes.
- B. Perform a Monte Carlo simulation to understand possible risk outcomes.
- C. Cancel the project, as the overall level of risk remains unacceptable.
- D. Conduct a stakeholder meeting to validate stakeholder risk appetite.
Show answer and explanation ▾
Correct answer: C
The risk management plan documents the level of risk the organization will accept. When a project's overall risk exceeds that documented level and its scope is unchanged, even a risk-seeking organization should not proceed with it.
Why the other options are wrong:
- A. Monitoring does nothing to bring the overall risk back within the documented limits.
- B. A simulation describes possible outcomes but does not change the fact that the risk level exceeds the documented limits.
- D. The acceptable risk levels are already documented in the risk management plan, so a meeting to validate them does not resolve the excess.
Question 78
What are the critical success factors for the Plan Risk Management process?
- A. Mitigate all risks, engage stakeholders, and follow organizational policies.
- B. Identify and address barriers, engage stakeholders, and follow organizational policies.
- C. Contingency reserves engage stakeholders and follow organizational policies.
- D. Identify and address barriers, engage stakeholders, and follow government regulations.
Show answer and explanation ▾
Correct answer: B
The critical success factors for Plan Risk Management are to identify and address barriers to successful risk management, to involve project stakeholders, and to comply with the organization's objectives, policies and practices.
Why the other options are wrong:
- A. Mitigating all risks is neither possible nor a goal of risk management planning.
- C. Contingency reserves are a result of later analysis and are not a success factor for planning.
- D. The success factor refers to the organization's own policies and practices, not to government regulations.
Question 79
What items should be included in a complex project's risk management plan?
- A. Risk management methodology, scope statement, and thresholds and corresponding definitions
- B. Risk management methodology, risk management organization, and thresholds and corresponding definitions
- C. Risk management organization, templates, and milestone plan
- D. Risk management organization, risk communication plan, and milestone plan
Show answer and explanation ▾
Correct answer: B
A risk management plan describes the methodology, the risk management organization with its roles and responsibilities, and the thresholds with their definitions of probability and impact. A complex project needs all three stated clearly.
Why the other options are wrong:
- A. The scope statement is a separate project document and is not part of the risk management plan.
- C. A milestone plan belongs to the schedule and is not a component of the risk management plan.
- D. A milestone plan belongs to the schedule, and communication is planned in the communications management plan.
Question 80
Which analysis method has a lower standard deviation?
- A. European Hypercube
- B. Monte Carlo simulation
- C. Hecht analysis
- D. Latin Hypercube
Show answer and explanation ▾
Correct answer: D
Latin Hypercube sampling is stratified: it divides each input distribution into equal probability intervals and samples from every interval. Results converge with fewer iterations and show less sampling variation than plain random sampling.
Why the other options are wrong:
- A. European Hypercube is not a recognized simulation sampling method.
- B. Standard Monte Carlo simulation uses purely random sampling, which gives more sampling variation for the same number of iterations.
- C. Hecht analysis is not a recognized simulation sampling method.
Question 81
While creating the appropriate risk strategy, the project manager discovers that the project team lacks the necessary expertise to define the risk management plan.
What additional resources should be utilized?
- A. Consultants, organizational process assets, subject matter experts, and stakeholder tolerance analysis
- B. Consultants, industry group, and subject matter experts
- C. Consultants, professional and technical associations, subject matter experts, and industry groups
- D. Consultants, professional and technical associations, and subject matter experts
Show answer and explanation ▾
Correct answer: B
When the team lacks risk planning expertise, the project manager brings in expert judgment from outside the team. Consultants, industry groups and subject matter experts supply the specialized knowledge needed to define the risk management plan.
Why the other options are wrong:
- A. Organizational process assets and stakeholder tolerance analysis are not additional sources of expertise.
- C. This list is not the set of expert resources that best fits the need described.
- D. This list leaves out industry groups, which are a recognized source of specialized risk knowledge.
Question 82
A project manager is creating a risk management plan, but participants in a group meeting are hesitant to express their concerns.
What will encourage participants to offer their opinions?
- A. Brainstorming
- B. Monte Carlo simulation
- C. Interviews
- D. Nominal group technique
Show answer and explanation ▾
Correct answer: D
In the nominal group technique each participant writes ideas down individually before they are shared and ranked. This gives every participant an equal voice and draws out views from people who hesitate to speak in open discussion.
Why the other options are wrong:
- A. Brainstorming relies on open group discussion, where hesitant participants tend to stay silent.
- B. Monte Carlo simulation is a quantitative analysis technique, not a way to gather opinions.
- C. Interviews are held outside the group meeting and do not make the group session itself more open.
Question 83
Which of the following is a key element of neuro-linguistic programming?
- A. Re-coding based on agile methodology
- B. Flex-scheduling
- C. Cross-training
- D. Building rapport with others
Show answer and explanation ▾
Correct answer: D
Neuro-linguistic programming is an approach to communication and personal influence. Building rapport with others is one of its core elements, and it helps a risk manager gain trust and honest input from stakeholders.
Why the other options are wrong:
- A. Re-coding based on agile methodology is not part of neuro-linguistic programming.
- B. Flex-scheduling is a working time arrangement, not a communication technique.
- C. Cross-training is a staff development practice, not part of neuro-linguistic programming.
Question 84
When monitoring the execution quality of risk-related plans and processes, which of the following would be a useful metric to track and record?
- A. The number of risks in the project risk register
- B. The degree of variation from the baseline
- C. The number of levels in the risk breakdown structure
- D. The degree of variation from the risk response strategy
Show answer and explanation ▾
Correct answer: B
The quality of execution is judged by comparing what actually happened with what was planned. The degree of variation from the baseline is therefore a useful metric to track and record.
Why the other options are wrong:
- A. The number of risks in the register shows volume, not how well plans and processes are being executed.
- C. The number of levels in the risk breakdown structure describes how risks are categorized, not execution quality.
- D. A response strategy is a chosen approach, not a baseline against which execution is measured.
Question 85
A project manager identifies a risk in a multifunctional project and decides to take no action.
What should the risk manager do if the risk occurs?
- A. Implement a workaround.
- B. Create a change request.
- C. Implement a contingency or fallback plan.
- D. Review the project management plan.
Show answer and explanation ▾
Correct answer: A
Taking no action is passive acceptance, so no contingency or fallback plan exists. When a passively accepted risk occurs, the team deals with it through a workaround, an unplanned response.
Why the other options are wrong:
- B. A change request may follow later, but the immediate way to deal with the event is a workaround.
- C. No contingency or fallback plan was prepared, because the decision was to take no action.
- D. Reviewing the project management plan does not deal with the risk event that has occurred.
Question 86
When analyzing the reward system in a company, there is evidence that "fire-fighter behavior" is the highest rewarded behavior. It suggests that people are dealing with major problems primarily in an emergency mode, and deploying quickly. Secondly, those who work efficiently are getting the most attention and recognition for their efforts.
What impact does this observation potentially have on the risk management process?
- A. Nothing, since the reward system does not have any impact on the risk management process.
- B. It means that this company's culture does not reward all people, and it gives little attention to proactive behavior such as risk management.
- C. It does not matter as each project has its own rewards system with no relationship to the company's rewards.
- D. This is a positive situation for risk management, since it encourages quick deployment of solutions and workarounds when necessary.
Show answer and explanation ▾
Correct answer: B
A reward system that favors fire fighting recognizes people for reacting to problems after they occur. Proactive work such as risk management, which prevents those problems, gets little attention, and that weakens the risk management process.
Why the other options are wrong:
- A. Reward systems shape behavior, so they directly affect how seriously risk management is taken.
- C. Projects operate within the company culture, and its reward system influences how project teams behave.
- D. Rewarding reactive workarounds discourages the proactive planning that risk management depends on.
Question 87
What would be the next step after determining the agreed-upon risk response for a specific risk?
- A. Add the risk response to the project management plan and document the predicted exposure.
- B. Evaluate the project related implications and update the risk response to the project management plan if needed.
- C. Document the predicted exposure.
- D. Communicate to stakeholders.
Show answer and explanation ▾
Correct answer: D
Once a response has been agreed for a risk, it is communicated to the stakeholders. The risk owner, the action owners and the affected parties must know what was decided so that the response can be carried out and supported.
Why the other options are wrong:
- A. Documenting the predicted exposure is part of planning the response, not the step that follows agreement.
- B. The project implications are evaluated while the response is being selected, before it is agreed.
- C. Predicted exposure is assessed during response planning, not after the response has been agreed.
Question 88
Which of the following techniques for planning risk response can provide a means of identifying symptoms for use as trigger conditions for contingency responses?
- A. Root cause analysis
- B. Quantitative risk analysis
- C. Ensuring that actions are available to address significant events before their occurrence
- D. Involving selected experts in the process
Show answer and explanation ▾
Correct answer: A
Root cause analysis traces a risk back to its underlying causes. Knowing the causes makes it possible to recognize the early symptoms that precede the risk, and those symptoms serve as trigger conditions for contingency responses.
Why the other options are wrong:
- B. Quantitative risk analysis estimates the numerical effect of risks on objectives and does not identify symptoms.
- C. Having actions available before events occur describes a goal of response planning, not a technique for finding triggers.
- D. Involving experts is a general success factor, not a technique that identifies symptoms.
Question 89
The engineering department offers the project manager some highly-skilled resources for the same cost as those currently on board.
What should the project manager do next to handle this situation?
- A. Create a change request to prevent a delay in getting the resources hired.
- B. Analyze the impact of replacing the resources and exploit the opportunity.
- C. Decline, to avoid changes in project team setup and stakeholder disruption.
- D. Accept the resources, to ensure project efficiency improvement is gained from the new resources.
Show answer and explanation ▾
Correct answer: B
Higher skilled resources at the same cost are an opportunity. The project manager first analyzes the impact of replacing the current resources, then exploits the opportunity so that its benefit is captured.
Why the other options are wrong:
- A. A change request comes after the impact has been analyzed, not before.
- C. Declining gives up a positive risk without assessing its benefit.
- D. Accepting the resources without analyzing the impact of the replacement skips a necessary step.
Question 90
What best describes the job of a risk owner?
- A. Responsible and accountable for managing risks
- B. Creating a detailed description of a risk
- C. Responsible and accountable for the risk management plan
- D. Actively involved in the identification of new risks
Show answer and explanation ▾
Correct answer: A
A risk owner is the person responsible and accountable for managing an assigned risk. The owner monitors the risk, makes sure the agreed response is implemented and reports on its status.
Why the other options are wrong:
- B. Describing a risk in detail is part of identification and does not define the owner's job.
- C. The risk management plan is the responsibility of the project manager, not of an individual risk owner.
- D. Identifying new risks is expected of all project participants and does not define the risk owner role.
Question 91
The risk manager examines the enterprise environmental factors to gain an understanding of the stakeholders' risk appetite. However, risk appetites are not determined.
What is the best method a risk manager should use to initially define the stakeholders' risk appetite?
- A. Review risk response strategies.
- B. Conduct SWOT analysis.
- C. What-If scenario.
- D. Meetings and interviews with key stakeholders.
Show answer and explanation ▾
Correct answer: D
When risk appetite is not documented, it has to be obtained from the stakeholders themselves. Meetings and interviews with the main stakeholders let the risk manager draw out and agree how much risk they are willing to take.
Why the other options are wrong:
- A. Risk response strategies are chosen after appetite is known and do not define it.
- B. SWOT analysis identifies strengths, weaknesses, opportunities and threats, not the appetite of stakeholders.
- C. What-if scenarios explore possible outcomes and do not establish stakeholder appetite.
Question 92
A six-month, USS1.2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project's reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly risk management reviews to evaluate performance. So far, the project has missed 50% of the planned risk mitigation milestones.
Based on this project data, what technique should the risk manager recommend to improve the risk management process?
- A. Increase the risk manager's position to a full-time position and acquire a dedicated project schedule lead.
- B. Adjust project risk thresholds to increase the number of residual risks on the project.
- C. Increase the frequency of risk status meetings and update the risk management plan.
- D. Perform a variance analysis and potentially allocate more reserves to improve risk mitigation.
Show answer and explanation ▾
Correct answer: C
Missing half of the mitigation milestones under monthly reviews shows that the reviews are too infrequent to keep responses on track. Holding risk status meetings more often and recording the new frequency in the risk management plan tightens control.
Why the other options are wrong:
- A. Adding staff is not a risk management technique and does not address the review cycle.
- B. Loosening thresholds would hide the problem instead of improving mitigation performance.
- D. Most reserves are unspent, so a shortage of reserves is not the cause of the missed milestones.
Question 93
Which of the following best describes the strength of the probability and impact matrix for qualitative risk analysis?
- A. It is well-suited to a decision tree analysis.
- B. It assists in handling other factors such as urgency and manageability that may partly determine the risk's ranking.
- C. It provides expert facilitators for the quantitative risk analysis.
- D. It reflects the organization's level of risk appetite.
Show answer and explanation ▾
Correct answer: B
The probability and impact matrix gives a simple, consistent basis for ranking individual risks in qualitative risk analysis. Its ratings can be considered together with other factors, such as urgency and manageability, that also influence a risk's priority.
Why the other options are wrong:
- A. The matrix is a qualitative ranking tool and is not designed to feed a decision tree analysis.
- C. The matrix is a tool and does not provide facilitators for quantitative risk analysis.
- D. This is not the strength the question describes.
Question 94
The risk manager and the project team conduct a risk brainstorming session for a new project. The risk manager wants to involve the entire project team in a group risk prioritization exercise for the identified risks. The project manager refuses the involvement of the entire project team due to resource concerns.
What should the risk manager do?
- A. Convince the project manager of the importance of the whole project team's involvement in the full risk process.
- B. Continue to involve the project team in the risk prioritization process and then discuss lessons learned with the project manager.
- C. Follow the project manager's instruction, as the project manager is the responsible party.
- D. Inform the sponsor about the project manager's decision and the disagreement between parties.
Show answer and explanation ▾
Correct answer: A
Risk management works best when the whole project team takes part, because prioritization depends on the knowledge and perspectives of the people doing the work. The risk manager should explain this value and persuade the project manager.
Why the other options are wrong:
- B. Going ahead against the project manager's decision undermines the project manager's authority.
- C. Complying without making the case leaves the quality of the risk prioritization weakened.
- D. Escalating to the sponsor is premature before trying to resolve the disagreement directly.
Question 95
A mobile operator wants to test a new network prototype before conducting full implementation on the entire network.
What type of risk response strategy did the mobile operator choose?
- A. Transfer
- B. Mitigate
- C. Avoid
- D. Accept
Show answer and explanation ▾
Correct answer: B
Testing a prototype before full implementation reduces the probability or impact of failure on the whole network. Acting early to reduce a threat to an acceptable level is mitigation.
Why the other options are wrong:
- A. Transfer shifts the risk to a third party, such as an insurer or contractor.
- C. Avoidance eliminates the threat entirely, for example by not implementing the new network at all.
- D. Acceptance takes no action to reduce the risk before it occurs.
Question 96
The risk manager for a data center infrastructure project performs a risk audit.
Which of the following represents the primary goals of the audit?
- A. Assess performance of project team members and make required changes.
- B. Document new risks identified and take the appropriate actions.
- C. Assess responsibilities of risks that have occurred and take the appropriate actions.
- D. Document what went well and not so well with the risk management process, and recommend actions to improve.
Show answer and explanation ▾
Correct answer: D
A risk audit examines how effective the risk responses and the risk management process have been. Its goals are to document what worked and what did not, and to recommend improvements.
Why the other options are wrong:
- A. A risk audit evaluates the process, not the performance of individual team members.
- B. Identifying new risks is the purpose of risk reassessment, not of an audit.
- C. A risk audit does not assign blame for risks that have occurred.
Question 97
What is the best source of project information which could result in the reduction of risk?
- A. Determine the risks by using brainstorming techniques.
- B. Sensitivity analysis.
- C. Review organizational process assets, lessons learned from previous projects similar in nature.
- D. Make observations/conversations on the current projects.
Show answer and explanation ▾
Correct answer: C
Organizational process assets hold the lessons learned from earlier, similar projects. They show which risks actually occurred and which responses worked, which makes them the best source of information for reducing risk on a new project.
Why the other options are wrong:
- A. Brainstorming generates ideas from the current team and is a technique, not a source of historical information.
- B. Sensitivity analysis shows which risks have the most effect and is not a source of project information.
- D. Observations on current projects lack the complete outcomes that finished projects provide.
Question 98
At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks had occurred, and the impact was significantly larger than expected. While the project remained on schedule, the project budget increased by 50%. The project met all risk response milestones and no additional, previously unidentified risks, occurred on the project.
Based on this information, what risk management process improvement should the risk manager recommend for future similar projects?
- A. Increase frequency of risk management meetings with the project manager.
- B. Revise the level of accuracy of probability and impact scores.
- C. Document the risk audit report and capture it in the lessons learned database.
- D. Expand the use of risk identification techniques.
Show answer and explanation ▾
Correct answer: C
The audit found that impacts were underestimated on this type of project. Documenting the audit report and storing it in the lessons learned database makes that finding available to the teams that plan future similar projects.
Why the other options are wrong:
- A. The project met all its risk response milestones, so meeting frequency was not the weakness.
- B. A change to the scoring scales is not the improvement that carries this finding forward to future projects.
- D. No unidentified risks occurred, so risk identification was not the weakness.
Question 99
A project risk manager is concerned about the low performance of risk management on a mission-critical project. After assessing the situation, the risk manager finds that the communication style may be the main contributor.
What could the project risk manager do to adjust the approach to influence team members to improve performance?
- A. Use follow-up emails, adopt an open door policy, and ask for feedback.
- B. Seek hidden agendas, vent frustrations, and allow others to vent frustrations.
- C. Provide continuous support, counseling, build trust, and open communications.
- D. Conduct one-on-one meetings, more frequent follow-up meetings, and implement the management by walking around technique.
Show answer and explanation ▾
Correct answer: D
One-on-one meetings, more frequent follow-up and management by walking around replace distant communication with direct, personal contact. That change of style lets the risk manager influence team members and see risk work first hand.
Why the other options are wrong:
- A. Emails and an open door policy are passive and wait for team members to come forward.
- B. Seeking hidden agendas and venting frustrations damages trust instead of improving performance.
- C. Support and counseling are general leadership behaviors, not a concrete change in how the risk manager communicates.
Question 100
A project's risk manager successfully implements the risk management plan and the risk register. Furthermore, the risk analysis and the risk response planning are finalized. All results have been documented, and the project management plan and other project documents have been updated accordingly.
What should the risk manager do next?
- A. Perform a lessons learned document update with the defined risks.
- B. Perform regular reserve analysis to ensure that the assigned risk reserve budgets are sufficient.
- C. Perform risk date quality assessments.
- D. Perform continuous risk re-evaluation throughout the project life cycle to ensure risk management effectiveness.
Show answer and explanation ▾
Correct answer: D
Once planning, analysis and response planning are complete, the next step is monitoring. Risks are re-evaluated continuously throughout the project life cycle to confirm that responses work and to catch new or changed risks.
Why the other options are wrong:
- A. Lessons learned are updated as experience is gained, not as the next step after response planning.
- B. Reserve analysis is one technique within monitoring, not the complete next step.
- C. Risk data quality assessment is part of qualitative risk analysis, which is already finished.
Question 101
Which of the following success factors will enhance the
Perform Qualitative Risk Analysis process as the risk occurrence gets closer?
- A. Agreed-upon definition
- B. Iterative analysis
- C. High quality information
- D. Agreed-upon approach
Show answer and explanation ▾
Correct answer: D
Using an agreed-upon approach is a critical success factor for Perform Qualitative Risk Analysis. When every risk is assessed in the same agreed way, the results stay consistent and credible each time the analysis is repeated.
Why the other options are wrong:
- A. Agreed definitions of risk terms support the analysis but are not the factor the question describes.
- B. Iterative analysis is not the factor the question describes.
- C. High quality information supports the analysis but is not the factor the question describes.
Question 102
A project team member identifies, but does not document, a risk early in the project, because it is considered to be trivial. This risk occurs later and negatively impacts the project.
What could the project manager do to avoid this situation?
- A. Conduct team meetings early in the project to ensure team member are familiar with risk identification requirements.
- B. Communicate the punishment and rewards policy to the project team during the project kick-off meeting.
- C. Provide project team members with access to simulation tools and decision tree diagrams.
- D. Provide team members with a risk management prompt list early in the project to ensure risks are not missed.
Show answer and explanation ▾
Correct answer: A
Team members must know that every identified risk is to be documented, however small it seems. Early team meetings that explain the risk identification requirements set that expectation before risks go unrecorded.
Why the other options are wrong:
- B. A punishment and rewards policy discourages open reporting instead of explaining what must be documented.
- C. Simulation tools and decision trees are analysis tools and do not make people record risks.
- D. A prompt list helps people think of risks, but this risk was already identified and simply not documented.
Question 103
A project in the execution phase at the customer's site has an issue concerning new parts that do not fit properly into a machine. The site project manager cannot find this high probability risk in the risk register.
What action should the site project manager take?
- A. Variance analysis
- B. Workaround
- C. Risk assessment
- D. Risk audit
Show answer and explanation ▾
Correct answer: B
The problem has already occurred and was never recorded in the risk register, so no planned response exists. The response to an unplanned risk event is a workaround.
Why the other options are wrong:
- A. Variance analysis measures deviation from the plan and does not resolve the problem on site.
- C. A risk assessment evaluates uncertain future events, and this event has already happened.
- D. A risk audit reviews the effectiveness of the risk process and does not fix the immediate problem.
Question 104
Which of the following represents the best description of the role of project manager for project risk management?
- A. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the risk management, assessing the impact of proposed scope changes
- B. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the project management plan, participating in all aspects of the project risk management process
- C. Approving the risk management plan, participating in all aspects of the project risk management process, auditing the risk management processes in the project
- D. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the risk management plan, participating in all aspects of the project risk management process
Show answer and explanation ▾
Correct answer: D
For project risk management, the project manager determines the acceptable levels of risk in consultation with stakeholders, approves the risk management plan and takes part in every aspect of the risk management process.
Why the other options are wrong:
- A. This description leaves out participation in all aspects of the risk management process.
- B. Approving the project management plan is not the risk-specific responsibility, which is approving the risk management plan.
- C. This description leaves out determining the acceptable levels of risk with stakeholders.
Question 105
A risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex, but has rigorous implementation timelines, and very little cost reserve available to address potential problems. The project manager indicates that completing the project on time is critical, but should not be done at the expense of performance.
Which aspect of risk impact is most important when designing the risk impact scale?
- A. Technical performance
- B. Cost
- C. Technical requirements
- D. Schedule
Show answer and explanation ▾
Correct answer: A
The project manager states that meeting the schedule must not come at the expense of performance. Performance is therefore the objective that cannot be traded away, and the impact scale must weight technical performance most heavily.
Why the other options are wrong:
- B. Cost reserve is limited, but cost is not the objective the project manager places above the others.
- C. Technical requirements are not complex on this project and are not an impact dimension the project manager singles out.
- D. Schedule is critical, but the project manager places performance ahead of it.
Question 106
A risk manager works with the project team, senior management team, subject matter experts and other stakeholders to identify the project risks.
Which of the following tools/methods from the risk management plan can be used to identify a risk, which is based on project objectives by category?
- A. Affinity diagram
- B. Risk breakdown structure
- C. Decision tree method
- D. Work breakdown structure
Show answer and explanation ▾
Correct answer: B
A risk breakdown structure is a hierarchical representation of potential sources of risk, grouped by category. It is defined in the risk management plan and gives a framework for identifying risks category by category.
Why the other options are wrong:
- A. An affinity diagram groups ideas after they are generated and is not a component of the risk management plan.
- C. The decision tree method evaluates alternative decisions and does not categorize risks.
- D. A work breakdown structure decomposes the project deliverables, not the sources of risk.
Question 107
Which of the following describes a difference between qualitative and quantitative risk analysis?
- A. Quantitative risk analysis addresses individual risks descriptively; qualitative risk analysis predicts likely project outcomes based on combined effects of risks.
- B. Quantitative risk analysis adds to the risk register; qualitative risk analysis leads to quantitative risk analysis.
- C. Quantitative risk analysis prioritizes individual risks for subsequent treatment: qualitative risk analysis leads to quantitative risk analysis.
- D. Qualitative risk analysis addresses individual risks descriptively; quantitative risk analysis predicts likely project outcomes based on combined effects of risks.
Show answer and explanation ▾
Correct answer: D
Qualitative risk analysis assesses individual risks descriptively, by probability, impact and other characteristics, in order to prioritize them. Quantitative risk analysis numerically models the combined effect of risks to predict likely overall project outcomes.
Why the other options are wrong:
- A. This statement reverses the two analyses.
- B. It is qualitative analysis that may lead to quantitative analysis, not the other way around.
- C. Prioritizing individual risks for subsequent treatment is the role of qualitative analysis, not quantitative.
Question 108
As a result of the Control Risk process, the project manager updates the project risk documents using outcomes from which of the following?
- A. Risk reserve analysis and risk thresholds
- B. Risk response strategies and risk analysis
- C. Risk reviews and risk register analysis
- D. Risk assessments and risk audits
Show answer and explanation ▾
Correct answer: D
Control Risks updates the risk register and other risk documents with the outcomes of risk reassessments, risk audits and periodic risk reviews. Those outcomes include changes to probability, impact, priority and response plans.
Why the other options are wrong:
- A. Risk thresholds are set in the risk management plan and are not outcomes of controlling risks.
- B. Risk response strategies are produced by response planning, not by the control process.
- C. Risk register analysis is not a defined technique whose outcomes update the documents.
Question 109
The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks:
Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring.
Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring.
Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring.
Risk 4 has a US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring.
Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?
- A. Risk 1
- B. Risk 2
- C. Risk 3
- D. Risk 4
Show answer and explanation ▾
Correct answer: A
Multiplying each impact by its probability gives Risk 1 US$125,000 and 15 days. Risks 2, 3 and 4 each come to US$120,000, with 12, 9 and 14 days. Risk 1 is highest on both cost and schedule.
Why the other options are wrong:
- B. Risk 2 has an expected value of US$120,000 and 12 days, below Risk 1.
- C. Risk 3 has an expected value of US$120,000 and 9 days, below Risk 1.
- D. Risk 4 has an expected value of US$120,000 and 14 days, below Risk 1.
Question 110
The expected monetary value of a project is above USS1 million. The risk manager is concerned about this situation, and decides to review the related plans and processes to evaluate the degree of variation from the baseline. Next, the risk manager needs to document the results of such an analysis.
What is the best document for the project manager to reference to find out where the results of such an analysis should be documented?
- A. Communications management plan
- B. Issues log
- C. Risk management plan
- D. Lessons learned
Show answer and explanation ▾
Correct answer: A
The communications management plan defines what project information is recorded and reported, in what format, where it is stored and who receives it. It tells the project manager where the results of the analysis should be documented.
Why the other options are wrong:
- B. The issues log tracks current problems and does not define where analysis results are documented.
- C. The risk management plan describes how risk management is performed and is not the reference for where project information is recorded and distributed.
- D. Lessons learned capture experience for future projects and do not prescribe where results are documented.
Question 111
The project manager requests a method to analyze risk data in a simple format.
Which of the following formats should the risk manager suggest for preliminary review of the data?
- A. Monte Carlo analysis
- B. Fishbone diagram
- C. Latin Hypercube analysis
- D. Data tables
Show answer and explanation ▾
Correct answer: D
Data tables present risk data in plain rows and columns. They are the simplest format for a preliminary review, before any modeling or deeper analysis is carried out.
Why the other options are wrong:
- A. Monte Carlo analysis is a simulation technique, not a simple format for reviewing data.
- B. A fishbone diagram explores the causes of a single problem and is not a format for reviewing risk data.
- C. Latin Hypercube analysis is a simulation sampling method, not a simple data format.
Question 112
A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits of early completion.
What document should be updated at the end of the review?
- A. Risk register
- B. Risk response plan
- C. Risk management plan
- D. Risk identification plan
Show answer and explanation ▾
Correct answer: A
Opportunities are risks with a positive effect, and identified risks are recorded in the risk register. The opportunities found during the document review are therefore added to the register at the end of the review.
Why the other options are wrong:
- B. Responses are developed after the opportunities have been recorded and analyzed.
- C. The risk management plan describes how risk management is performed and does not list individual risks.
- D. A risk identification plan is not a standard project document.
Question 113
The feasibility of the risk management planning is dependent upon which of the following aspects of the organization?
- A. Competitive market share
- B. Level of risk management maturity
- C. Alignment with industry standard requirements
- D. Culture, people and infrastructure capabilities
Show answer and explanation ▾
Correct answer: D
Risk management planning has to fit the organization that will carry it out. Its feasibility depends on the organization's culture, the capability of its people and its infrastructure.
Why the other options are wrong:
- A. Competitive market share does not determine whether risk management planning is feasible.
- B. Maturity level alone is not the organizational aspect that determines feasibility.
- C. Alignment with industry standards does not determine whether the organization can carry out the planning.
Question 114
Company A sells a new machine to company B. During the risk assessment, the stakeholders of company A do not want the risk of transporting the machine from their facility. Instead, they want company B to take responsibility and liability once the machine leaves company A's facility.
What strategy is company A using to deal with the risk?
- A. Avoid
- B. Transfer
- C. Mitigate
- D. Accept
Show answer and explanation ▾
Correct answer: B
Transfer shifts the negative impact of a threat, together with ownership of the response, to another party. Making company B responsible and liable once the machine leaves the facility transfers the transport risk.
Why the other options are wrong:
- A. Avoidance would eliminate the transport risk, and the machine is still being transported.
- C. Mitigation would reduce the probability or impact of the risk, not move the liability.
- D. Acceptance would leave the risk and its consequences with company A.
Question 115
The team has just completed a risk response planning session and identified responses for all the high and medium priority risks.
What should the team do with the remaining low priority risks?
- A. Create risk responses later, as time allows.
- B. Add the risks to a watchlist for periodic monitoring.
- C. Remove the risks from the risk register.
- D. Conduct a low priority risk response planning workshop with key stakeholders.
Show answer and explanation ▾
Correct answer: B
Low priority risks that do not warrant a planned response are placed on a watch list in the risk register. They are monitored periodically in case their probability or impact changes.
Why the other options are wrong:
- A. Leaving responses for later with no monitoring lets the risks change unnoticed.
- C. Removing the risks from the register loses the record and stops monitoring.
- D. A dedicated response workshop spends effort that low priority risks do not justify.
Question 116
PESTLE, TECOP, and SPECTRUM are three examples of prompt lists that can be used during risk management activities. Prompt lists are used to do which of the following?
- A. Simulate risk identification.
- B. Perform a simulation with all prompted risks varying simultaneously.
- C. Identify basic causes of risks of more fundamental forces.
- D. Achieve the relative weighting of the risks.
Show answer and explanation ▾
Correct answer: A
A prompt list is a predetermined set of risk categories, such as the political, economic, social, technological, legal and environmental headings of PESTLE. It is used as a framework to help the team generate ideas during risk identification.
Why the other options are wrong:
- B. Varying all risks simultaneously in a simulation describes Monte Carlo analysis, not a prompt list.
- C. Finding the fundamental causes of risks describes root cause analysis.
- D. Relative weighting of risks is a prioritization activity and is not what prompt lists are for.
Question 117
During a major project review, the project manager discovers that large groups of internal management issues are obstructing progress. In reviewing the risk management plan, the project risk categories largely contain technical and customer relationship type risks. The project manager wants the risk management plan revised to account for these risk areas, particularly because the project has several more months before completion.
Who should the project manager collaborate with to revise the risk management plan at this stage of the project?
- A. Risk manager, technical manager, and customers
- B. Project sponsor, product owner, and risk owners
- C. Risk manager, product owner, and risk owners
- D. Risk manager, risk owners, and project sponsor
Show answer and explanation ▾
Correct answer: A
The plan's categories were built around technical and customer relationship risks, so the risk manager revises it together with the technical manager and the customers who shaped those categories, widening them to cover the internal management risks now obstructing progress.
Why the other options are wrong:
- B. This group leaves out the risk manager, who maintains the risk management plan.
- C. The product owner and risk owners manage individual items and do not redefine the plan's risk categories.
- D. Risk owners and the sponsor are not the group that reworks the existing risk categories at this stage.
Question 118
A risk manager is conducting a risk audit review at project completion.
Which of the following represents the order that the steps should be performed to complete the full risk audit review?
- A. Identify participants, conduct risk meeting, document findings, update risk management plan
- B. Arrange risk audit review, identify participants, prepare recommendations, update risk management plan
- C. Identify participants, conduct risk audit reviews, prepare recommendations, document the risk audit report
- D. Prepare recommendations, identify participants, conduct risk audit reviews, document the risk audit report
Show answer and explanation ▾
Correct answer: C
A risk audit starts by identifying who takes part, then the audit reviews are conducted, recommendations are prepared from the findings, and the results are recorded in the risk audit report.
Why the other options are wrong:
- A. A risk meeting followed by a plan update is not a full audit, which ends with a documented audit report.
- B. This sequence never conducts the reviews and ends with a plan update instead of the audit report.
- D. Recommendations cannot be prepared before the participants are identified and the reviews are held.
Question 119
The risk manager of a medium-sized project is performing risk response planning with the project team. The proposed action for one specific, primary risk introduces a secondary risk.
What should the risk manager and the risk owner of the primary risk do about this situation?
- A. Take no action, as secondary risks are not important for the successful execution of a project.
- B. Inform the project manager about the occurrence of a secondary risk and propose to increase the management reserve.
- C. Perform an analysis to calculate the estimated required budget for the secondary risk and propose to increase the management reserve accordingly.
- D. Produce an agreed risk description, assess the probability, impacts, and select an appropriate response strategy for the secondary risk
Show answer and explanation ▾
Correct answer: D
A secondary risk arises as a direct result of implementing a risk response and is managed like any other risk: it is described, assessed for probability and impact, and given its own response strategy.
Why the other options are wrong:
- A. Secondary risks can affect project objectives and must be managed.
- B. The secondary risk has been identified, not occurred, and management reserve is not meant for identified risks.
- C. Identified risks are handled through analysis and a response strategy, not by enlarging the management reserve.
Question 120
During a project review meeting, an executive scrutinizes the risk section, including risks on the watch list, and demands action to close them out.
What is the executive's risk attitude?
- A. Averse
- B. Seeking
- C. Neutral
- D. Tolerant
Show answer and explanation ▾
Correct answer: A
Demanding that even low priority watch list risks be closed out shows discomfort with uncertainty, which is the mark of a risk averse attitude.
Why the other options are wrong:
- B. A risk seeking person welcomes uncertainty and would not push to eliminate minor risks.
- C. A risk neutral person weighs risk against long term payoff and does not demand closure of every item.
- D. A risk tolerant person is comfortable leaving low priority risks on a watch list.
Question 121
Which input could be utilized to perform quantitative risk analysis to reduce uncertainty?
- A. Risk categorization
- B. Organizational process assets
- C. Stakeholder register
- D. Expert judgment
Show answer and explanation ▾
Correct answer: B
Organizational process assets, such as historical information and risk databases from completed similar projects, are an input to quantitative risk analysis and give the estimates a factual basis, which reduces uncertainty in the model.
Why the other options are wrong:
- A. Risk categorization is a technique of qualitative analysis, not an input to quantitative analysis.
- C. The stakeholder register lists people and their interests and does not supply data for numerical modeling.
- D. Expert judgment is a tool and technique, not an input.
Question 122
To properly ensure risk information is incorporated into the overall project management framework, risk data must be provided to the schedule analysts and cost estimators on a periodic basis.
How frequently should this be performed?
- A. As defined in the risk plan
- B. At least once per month
- C. At the end of the financial quarter
- D. As defined in the company standards
Show answer and explanation ▾
Correct answer: A
The risk management plan sets the timing and frequency of risk activities for the project, including when risk data is passed to the schedule and cost functions, so the cycle to follow is the one the plan defines.
Why the other options are wrong:
- B. A monthly cycle is not a fixed rule, since frequency depends on the project.
- C. Financial quarters are an accounting cycle and are not tied to the project's risk process.
- D. Company standards feed into the plan, and the project's own risk plan is what defines the frequency for this project.
Question 123
What quantitative tools and techniques are used to perform risk analysis in order to support stakeholder decision making for the project?
- A. Risk probability and impact assessment
- B. Sensitivity analysis
- C. Interviewing
- D. Probability and impact matrix
Show answer and explanation ▾
Correct answer: B
Sensitivity analysis is a quantitative technique that shows which risks or variables have the most potential influence on project outcomes, often displayed as a tornado diagram, which helps stakeholders decide where to focus.
Why the other options are wrong:
- A. Risk probability and impact assessment is a qualitative technique.
- C. Interviewing gathers data and does not itself model outcomes.
- D. The probability and impact matrix is a qualitative prioritization tool.
Question 124
A project is in the planning phase, and the risk manager establishes the risk management for the project.
Which success factors should be taken into account by the risk manager to establish a successful risk management process for the project?
- A. Organizational commitment, scale risk effort to project, early identification of risks
- B. Organizational commitment, scale risk effort required to project, perform quantitative risk analysis
- C. Organizational commitment, scale risk effort required to project, integrate with other project management areas
- D. Organizational commitment, scale risk effort required to project, use Monte Carlo analysis for risk evaluation
Show answer and explanation ▾
Correct answer: C
Critical success factors for project risk management include organizational commitment, scaling the risk effort to the project, and integrating risk management with the other project management areas.
Why the other options are wrong:
- A. Early identification of risks is an activity within the process, not a success factor for establishing it.
- B. Quantitative risk analysis is not required on every project and is not a success factor.
- D. Monte Carlo analysis is one optional technique, not a success factor.
Question 125
The project manager needs to create a risk management plan for a high risk project, but the company's senior management does not see value in spending time documenting major risks instead of leading the project.
What is the most appropriate action for the project manager to take first?
- A. Develop a risk register and present it to the senior management.
- B. Hire a risk consultant to identify the major risks.
- C. Develop a risk management plan and present it to the sponsor.
- D. Document all identified risks.
Show answer and explanation ▾
Correct answer: A
Showing senior management a risk register with the project's major risks makes the exposure concrete and demonstrates the value of risk management, which is the first step toward winning their support for the planning effort.
Why the other options are wrong:
- B. Hiring a consultant spends money before management sees any value in the effort.
- C. A plan presented to the sponsor does not address senior management's doubt about the value of documenting risks.
- D. Documenting risks without presenting them does nothing to change management's view.
Question 126
A common understanding of the value of risk management among key stakeholders is an effective foundation to managing risk effectively. The project manager should ensure training is provided to which of the following groups to create this understanding?
- A. Project team members and customers
- B. Management and external stakeholders
- C. Management and customers
- D. Project team members and management
Show answer and explanation ▾
Correct answer: D
The people who carry out the risk process and those who direct and fund it need a shared view of its value, so training goes to project team members and management.
Why the other options are wrong:
- A. Customers are not the group whose training builds the organization's own understanding of risk management.
- B. This leaves out the project team, who perform risk management day to day.
- C. This leaves out the project team, who perform risk management day to day.
Question 127
During a status meeting, a functional manager complains that the server backup failed, impacting the department. This was a known risk documented in the risk register as an accepted risk. After reviewing the meeting minutes, it is determined that the functional manager had not participated in the risk planning phase.
Which of the identification methods should have been applied?
- A. Qualitative analysis
- B. Sensitivity analysis
- C. Stakeholder analysis
- D. Quantitative analysis
Show answer and explanation ▾
Correct answer: C
Stakeholder analysis identifies everyone affected by the project and their interests. Applying it would have brought the functional manager into risk planning, so the accepted backup risk would not have come as a surprise.
Why the other options are wrong:
- A. Qualitative analysis prioritizes risks already identified and does not determine who should take part.
- B. Sensitivity analysis shows which variables most affect outcomes and does not identify affected people.
- D. Quantitative analysis models numerical effects of risks and does not identify affected people.
Question 128
A pharmaceutical company undertakes a new, year-long research and development (R&D) project. The company pursues high margins on investments and an aggressive growth strategy. They maintain a central program management office (PMO) to assist with new projects and record data on past project performance.
The company leadership regularly makes decisions regarding the full suite of company projects and requires comparative data and reports.
Project leadership is well-versed in risk management and the PMO requires full documentation of project management artifacts.
Based on the characteristics of this new project, which of the following best describes the risk strategy for the project?
- A. Low stakeholder risk appetite: leverage historical project planning data, develop standard metrics and reports, and develop a formal risk management plan.
- B. High stakeholder risk appetite; leverage historical project planning data, develop standard metrics and reports, develop a formal risk management plan.
- C. High stakeholder risk appetite; leverage historical project planning data, utilize informal metrics and reports, develop risk management training.
- D. Low stakeholder risk appetite; collect new project data, create custom metrics and reports, and develop a formal risk management plan.
Show answer and explanation ▾
Correct answer: B
High margins and an aggressive growth strategy signal a high risk appetite. A PMO holding past performance data supports using historical planning data, leadership's need for comparative reports calls for standard metrics, and the PMO's documentation requirement calls for a formal risk management plan.
Why the other options are wrong:
- A. An aggressive growth strategy indicates a high risk appetite, not a low one.
- C. Informal metrics cannot give leadership comparable data, and project leadership is already well versed in risk management.
- D. The appetite is high, and the PMO already holds historical data and needs standard reports.
Question 129
When performing integrated cost-schedule risk analysis, a risk manager must correlate the project costs and activities with the risk baseline.
Why is determining correlation critical in performing this analysis?
- A. Correlation strength is determined by the strength of multiple risks affecting one cost or activity.
- B. Correlation is always negative in projects with high costs.
- C. Correlation implies causality between project costs and activities.
- D. Correlation identifies how each project risk affects project costs or activities.
Show answer and explanation ▾
Correct answer: D
In integrated cost and schedule risk analysis, a single risk can drive several activities and cost items at once. Modeling that correlation shows how each project risk affects costs and activities and keeps the spread of results realistic.
Why the other options are wrong:
- A. Correlation strength reflects how closely elements move together, not how many risks affect one item.
- B. Correlation can be positive or negative regardless of how costly the project is.
- C. Correlation does not imply causality.
Question 130
Most risks are assessed for probability and impact.
Which of the following are other factors that should be considered?
- A. Urgency and complexity
- B. Manageability and cost
- C. Urgency and manageability
- D. Manageability and complexity
Show answer and explanation ▾
Correct answer: C
Beyond probability and impact, qualitative analysis can weigh other characteristics such as urgency, meaning how soon a response is needed, and manageability, meaning how easily the risk can be managed.
Why the other options are wrong:
- A. Complexity describes the project rather than an individual risk.
- B. Cost is one dimension of impact, not a separate factor.
- D. Complexity describes the project rather than an individual risk.
Question 131
A risk manager schedules a project overview meeting with the project sponsor to provide an update on risk management progress. Each functional lead is identifying the most critical information to be presented at an executive level. The information must balance communicating essential information with actions and recommendations.
What risk information should be communicated to the project sponsor?
- A. Significant risks and issues and their planned responses
- B. Risk matrix showing the distribution of high, medium, and low risks
- C. Results of the last project risk brainstorming session
- D. Summary feedback from the previous risk audit
Show answer and explanation ▾
Correct answer: A
A sponsor needs the essentials and what is being done about them: the significant risks and issues together with their planned responses, which gives both the exposure and the actions and recommendations.
Why the other options are wrong:
- B. A distribution of high, medium and low risks gives counts without actions or recommendations.
- C. Brainstorming results are raw working output, not executive level information.
- D. Audit feedback concerns the process and does not report current risks and responses.
Question 132
A project manager wants to represent the distribution of uncertainty around a risk model element. However, good data on the variability of the risk model element has not been collected, and only contains minimum and maximum values.
What curve should the project manager use to represent the distribution?
- A. Uniform
- B. Beta
- C. Normal
- D. Lognormal
Show answer and explanation ▾
Correct answer: C
When good data on the variability of a model element has not been collected, a shape has to be assumed for its uncertainty. The normal curve is the shape used here: a symmetric bell curve between the minimum and maximum values, with values near the middle more likely than values at the extremes.
Why the other options are wrong:
- A. A uniform curve is flat and gives every value between the two limits exactly the same chance.
- B. A beta curve is usually shaped from three estimates, including a most likely value that is not available here.
- D. A lognormal curve is skewed to one side, and nothing in the data points to a skew.
Question 133
The risk register is developed during the initial phases of a virtualized desktop deployment. The register is reviewed by peers, responses are planned, reviewed again, and risks are prioritized. After project completion, the risk register is reviewed as part of the formal lessons learned process. During the review, it is realized that the risk register was not updated, and many responses were not executed during the deployment.
Which of the following options should have been performed during the execution of the project?
- A. Risk monitoring and control process
- B. Risk management process
- C. Risk identification
- D. Response planning
Show answer and explanation ▾
Correct answer: A
Risk monitoring and control is the process that tracks identified risks during execution, confirms that planned responses are carried out, and keeps the risk register up to date. Its absence explains the stale register and the unexecuted responses.
Why the other options are wrong:
- B. The overall risk management process was started, and the gap lies specifically in monitoring during execution.
- C. Risks were already identified in the initial phases.
- D. Responses were planned and reviewed; they were simply not carried out or tracked.
Question 134
The project manager of a project in trouble actively participates in a project risk assessment. After the assessment is complete, the project manager receives the final results.
What is the best recommended action to be taken from this point onward?
- A. Schedule a meeting and present the assessment results.
- B. Use the assessment results in the day-to-day management of project risks.
- C. Schedule a meeting with the project sponsor and discuss the assessment results.
- D. Use the assessment results to review the project hand over plan to operations.
Show answer and explanation ▾
Correct answer: B
A risk assessment has value only when its findings are applied. The project manager should build the results into the day-to-day management of the project's risks, which is what a troubled project needs.
Why the other options are wrong:
- A. Presenting the results in a meeting does not put them to use.
- C. Discussing the results with the sponsor does not by itself manage the risks.
- D. The handover plan to operations is not the main place where the assessment results are applied.
Question 135
A project manager is leading a project review meeting with the risk manager and the other project stakeholders.
Which of the following are typical risk-related agenda items for a project review meeting?
- A. Enterprise environmental factors and the risk register
- B. Risks closed in the last period and the risk appetite of the organization
- C. Organizational process assets and the risk register
- D. Risks closed in the last period and the trigger conditions that have occurred
Show answer and explanation ▾
Correct answer: D
Risk items in a project review cover what changed since the last period, such as risks that were closed and trigger conditions that have occurred and now call for a response.
Why the other options are wrong:
- A. Enterprise environmental factors are background conditions, not a review agenda item.
- B. The organization's risk appetite is set during planning and is not a routine review item.
- C. Organizational process assets are reference material, not a review agenda item.
Question 136
After years of experience, a project manager becomes the lead manager for a company. This new lead manager asks all project managers to use a specific technique when they perform qualitative risk analysis on their projects. This technique consists of achieving the relative weighting of the project's objectives in terms of priority to the stakeholders.
What is the name of this technique?
- A. Relative Weighting of the objectives of Stakeholders (RWS)
- B. Objectives Stakeholders Weighting (OSW)
- C. Quantitative Weighted Analysis (QWA)
- D. Analytic Hierarchy Process (AHP)
Show answer and explanation ▾
Correct answer: C
The technique described sets relative weights for the project's objectives according to their priority to the stakeholders, so that risk impacts on different objectives can be compared on one weighted basis. Quantitative Weighted Analysis is the name used for it here.
Why the other options are wrong:
- A. Relative Weighting of the objectives of Stakeholders restates the description and is not the name of a technique.
- B. Objectives Stakeholders Weighting is not the name of a recognized technique.
- D. The Analytic Hierarchy Process is a general multi-criteria decision method built on pairwise comparisons.
Question 137
A project manager is running a high-cost telecommunications project. There is a monthly status meeting, and the risk manager should provide an update to the project team and project sponsors on major risks.
What risk related information should be included in the monthly status meeting of this complex project?
- A. Top priority risks at present, risks closed in the last period, milestone changes
- B. Top priority risks at present, risks that have occurred, risk management plan
- C. Top priority risks at present, risks that have occurred, changes in scope
- D. Top priority risks at present, risks that have occurred, risks closed in the last period
Show answer and explanation ▾
Correct answer: D
A periodic risk update covers the current top priority risks, the risks that have occurred since the last report, and the risks closed in the last period, which together show how the exposure is changing.
Why the other options are wrong:
- A. Milestone changes are schedule information, not risk status.
- B. The risk management plan describes the process and is not a status item.
- C. Scope changes are reported through change control, not as risk status.
Question 138
What is defined as "an uncertainty that could have a positive or negative effect on the project objectives", and second, what is a "chosen state of mind, mental view or disposition with regard to a fact or state"?
- A. Risk/Response
- B. Risk/Attitude
- C. Opportunity/Response
- D. Opportunity/Attitude
Show answer and explanation ▾
Correct answer: B
A risk is an uncertainty that, if it occurs, has a positive or negative effect on project objectives, and an attitude is a chosen state of mind or disposition toward a fact or state.
Why the other options are wrong:
- A. A response is an action taken to address a risk, not a state of mind.
- C. An opportunity covers only positive effects, and a response is an action.
- D. An opportunity covers only positive effects.
Question 139
Who is the most appropriate person to conduct a risk identification brainstorming session?
- A. Facilitator
- B. Subject matter expert
- C. Project manager
- D. Project sponsor
Show answer and explanation ▾
Correct answer: A
A brainstorming session works best under a neutral facilitator who keeps the group on track, draws ideas from every participant and prevents any one voice from dominating.
Why the other options are wrong:
- B. A subject matter expert contributes ideas and can bias the session toward one field.
- C. The project manager has a stake in the outcome and can inhibit open input.
- D. The sponsor's seniority tends to suppress candid contributions.
Question 140
A regional vendor for custom manufactured steel oil derricks, is awarded a contract to design, manufacture, and install 40 offshore oil platforms.
Installation of these derricks requires precision placement and stable seas for the transport and installation ships to properly install the deep water structure. There are several schedule and cost incentives for early completion, and the project manager asks the project risk coordinator to perform an analysis, which will predict the probability of meeting the incentive dates. While researching methods that could be used for performing this analysis, the risk manager realizes that there are readily available spreadsheets within the organization. The risk manager is considering performing a Method of Moments (PERT) analysis with software already owned, or the other option is to buy a commercial risk analysis software suite that will perform Latin Hypercube Monte Carlo simulations at a cost of US$975.
What would be the best analytical option for this probability assessment?
- A. Schedule based Method of Moments analysis is a time proven, highly accurate method for schedule risk and is not impacted by Monte Carlo simulation's limitation of summation modeling where only addition and subtraction of uncertain values are used.
- B. The commercial product that performs the Monte Carlo simulations is the best option, because a schedule risk assessment involves summation of uncertainties added or subtracted from or to schedule dates.
- C. Because a schedule risk assessment involves multiplication and division of schedule durations against specific risk events, a spreadsheet and using a Method of Moments analysis is the best option.
- D. Since a schedule risk assessment involves multiplication and division of schedule durations against specific risk events, the Monte Carlo simulation software is the best option.
Show answer and explanation ▾
Correct answer: D
Applying specific risk events to schedule durations means multiplying and dividing uncertain values. Monte Carlo simulation handles those operations, while the Method of Moments is suited to summing uncertain values, so the simulation software is the better choice.
Why the other options are wrong:
- A. The summation limitation belongs to the Method of Moments, not to Monte Carlo simulation.
- B. The assessment is not limited to adding and subtracting uncertainties, so this reasoning does not fit.
- C. The Method of Moments is not suited to multiplying and dividing uncertain values.
Question 141
During a company's audit, it is found that no risk management information exists within the lessons learned database
What could the company do to increase the amount of risk management organizational process assets?
- A. Require the project manager to record significant risk management information, to provide concrete data in the lessons learned database for future projects.
- B. Require the PMO to merge and distribute risk logs to all key stakeholders associated with risk management.
- C. Require the project manager to update the project management office (PMO) policy and procedures on an iterative basis to ensure relevancy to current projects.
- D. Require the PMO to perform quality audits on all active projects, to ensure alignment with communication industry standards.
Show answer and explanation ▾
Correct answer: A
Risk-related organizational process assets grow only when projects contribute to them. Requiring project managers to record significant risk management information puts concrete data into the lessons learned database for future projects.
Why the other options are wrong:
- B. Distributing risk logs to stakeholders does not add anything to the lessons learned database.
- C. Updating PMO policy and procedures does not capture project risk experience.
- D. Quality audits check compliance and do not record risk lessons.
Question 142
The project manager wants risk metrics established for the new project.
Which of the following metrics listed is best suited for this purpose?
- A. Effectiveness of the work breakdown structure
- B. Number of approved project change requests
- C. Number of defects identified
- D. Effectiveness of response plans
Show answer and explanation ▾
Correct answer: C
A metric has to be an objective count that can be tracked over time. The number of defects identified is measurable data that shows whether quality-related risks are materializing.
Why the other options are wrong:
- A. Effectiveness of the work breakdown structure is not a measurable risk indicator.
- B. Approved change requests measure change control activity, not risk.
- D. Effectiveness of response plans is a judgment that needs an underlying measure before it can serve as a metric.
Question 143
Which of the following templates may be included in the risk management plan?
- A. Formal structure for a risk statement
- B. Work performance report
- C. Structure for a SWOT diagram
- D. Formal brainstorming list
Show answer and explanation ▾
Correct answer: A
The risk management plan can define formats and templates for the process, including a formal structure for writing risk statements so that every risk is described consistently.
Why the other options are wrong:
- B. A work performance report is a project output, not a template held in the risk management plan.
- C. A SWOT diagram layout is not a template the risk management plan defines.
- D. A brainstorming list is session output, not a template in the plan.
Question 144
The risk manager is currently performing the monitoring and reporting process.
Which of the following is an input for schedule metrics?
- A. Work breakdown structure
- B. Risk breakdown structure
- C. Critical path method
- D. Organizational breakdown structure
Show answer and explanation ▾
Correct answer: A
Schedule metrics are measured against the activities and milestones that come from decomposing the project work, so the work breakdown structure is the input that defines what is measured.
Why the other options are wrong:
- B. The risk breakdown structure categorizes risks and does not define scheduled work.
- C. The critical path method is a scheduling technique, not an input.
- D. The organizational breakdown structure shows reporting relationships, not scheduled work.
Question 145
The risk manager is about to go on medical leave, but before departing, conducts a risk response planning review meeting with stakeholders. A new risk manager is assigned to the project, and during the first status meeting an issue is identified.
What is the appropriate course of action in this case?
- A. Perform a project review.
- B. Perform a risk reserve analysis.
- C. Implement an action plan to resolve the issue.
- D. Delegate to the action owner.
Show answer and explanation ▾
Correct answer: C
An issue is an event that has already happened, so it is handled by putting an action plan in place to resolve it rather than by further risk analysis.
Why the other options are wrong:
- A. A project review does not resolve the issue that has just been raised.
- B. Reserve analysis checks remaining reserves and does not resolve the issue.
- D. Delegation comes after an action plan exists that gives the owner something to carry out.
Question 146
In order to monitor risks in an infrastructure improvement project, the risk manager uses methods to support effective responses to risks that have occurred.
Which of the following is an example of such a method?
- A. Risk analysis and performance reports preparation
- B. Ongoing risk response analysis and risk audits as required
- C. Risk analysis and risk register review
- D. Risk audits and change request review
Show answer and explanation ▾
Correct answer: B
Monitoring supports effective responses by continuing to analyze how well the responses to occurred risks are working and by auditing the risk process when needed, so that weak responses are corrected.
Why the other options are wrong:
- A. Preparing performance reports records status and does not evaluate responses.
- C. Reviewing the register and analyzing risks does not test how well responses are working.
- D. Change request review is part of change control, not a method for supporting risk responses.
Question 147
A risk manager assessed all project risks, and the team is now identifying common groupings of risks.
What tool or technique is used to perform this risk assessment?
- A. Risk breakdown structure (RBS)
- B. Risk probability and impact assessment
- C. Risk register
- D. Risk identification checklist
Show answer and explanation ▾
Correct answer: A
Grouping risks by common source is risk categorization, and the risk breakdown structure is the hierarchical tool that shows those groupings and where exposure is concentrated.
Why the other options are wrong:
- B. Probability and impact assessment rates individual risks and does not group them.
- C. The risk register records risks and is not a grouping technique.
- D. A checklist is used to identify risks, not to group assessed ones.
Question 148
What are critical success factors for the Plan Risk Responses process?
- A. Collect high-quality information about risks, address threats and opportunities, address interaction of risks and responses, and specify timing of responses
- B. Define roles and responsibilities, address threats and opportunities, address interaction of risks and responses, and specify timing of responses
- C. Define roles and responsibilities, address threats and opportunities, categorize risk causes, and addresses interaction of risks and responses
- D. Identify appropriate project model, define roles and responsibilities, address threats and opportunities, and addresses interaction of risks and responses
Show answer and explanation ▾
Correct answer: B
Critical success factors for Plan Risk Responses include clearly defined risk-related roles and responsibilities, addressing both threats and opportunities, addressing the interaction of risks and responses, and specifying the timing of responses.
Why the other options are wrong:
- A. Collecting high-quality information about risks belongs to risk analysis, not response planning.
- C. Categorizing risk causes belongs to analysis, and this list leaves out the timing of responses.
- D. Identifying an appropriate project model belongs to quantitative analysis, not response planning.
Question 149
During the execution of a multi-million dollar project, the project manager learns of the theft of important installation materials at one of the most time-critical sites.
The project manager contacts the risk manager to discuss further steps, based on the risk register and the defined risk strategy for the risk of theft. However, the risk manager clarifies that the risk of theft was not identified in the risk management process.
What should the project manager do next?
- A. Deal with the issue and instruct the risk manager to include the risk of theft in the issue log.
- B. Update the project schedule and inform the stakeholders about the project schedule delay.
- C. Instruct the risk manager to transfer the risk of theft to an insurance company and capture the experience in the lessons learned.
- D. Make the risk manager responsible for the damage caused by the missing risk strategy for theft and update the project schedule.
Show answer and explanation ▾
Correct answer: C
The theft shows that the remaining materials and sites are exposed, so the risk needs a response now. Insurance transfers the financial impact to a third party, and recording the missed risk in lessons learned helps future projects identify it.
Why the other options are wrong:
- A. A risk is recorded in the risk register, not in the issue log.
- B. Updating the schedule alone leaves the theft exposure unaddressed.
- D. Assigning blame does nothing to protect the project from further theft.
Question 150
Which form of communication minimizes misunderstandings and reinforces teamwork?
- A. Status reports
- B. Discussion threads
- C. Face-to-face discussions
- D. Project archives
Show answer and explanation ▾
Correct answer: C
Face-to-face discussion allows immediate questions, clarification and feedback, which keeps misunderstandings to a minimum and builds working relationships within the team.
Why the other options are wrong:
- A. Status reports are one-way and leave room for misreading.
- B. Discussion threads lack tone and immediate clarification.
- D. Project archives store records and are not a form of active communication.
Question 151
A risk facilitator is creating an outline for the risk management plan. To ensure alignment with the project's objectives, and to develop and recommend the project's risk strategy, what should be referenced to create this?
- A. Project management plan, project charter, stakeholder register, and organizational process assets
- B. Risk register, project charter, stakeholder register, and organizational process assets
- C. Project management plan, risk register, stakeholder register, and organizational process assets
- D. Strengths, weaknesses, opportunities, and threats (SWOT) analysis, project charter, stakeholder register, and organizational process assets
Show answer and explanation ▾
Correct answer: A
The risk management plan is developed from the project management plan, the project charter, the stakeholder register and organizational process assets, which together supply the objectives, stakeholder information and existing templates and policies.
Why the other options are wrong:
- B. The risk register does not exist until risks are identified, which happens after the plan is written.
- C. The risk register does not exist until risks are identified, and this list omits the project charter.
- D. SWOT analysis is an identification technique, not a reference for writing the plan.
Question 152
A project manager is creating a risk management plan. The project sponsor does not see the need for additional risk management, believing that the only risks to the project are financial risks.
What procedure could the project manager use to identify other potential topics such as technical, quality, performance, project management, internal and external risks?
- A. Review enterprise environmental factors.
- B. Perform Monte Carlo analysis and Delphi technique.
- C. Perform decision tree analysis and create an Ishikawa diagram.
- D. Use existing prompt lists and risk breakdown structure.
Show answer and explanation ▾
Correct answer: D
Prompt lists and a risk breakdown structure set out standard categories of risk sources, such as technical, quality, performance, project management, internal and external, so they prompt the team to look beyond financial risks.
Why the other options are wrong:
- A. Enterprise environmental factors are background conditions and do not provide a structured set of risk categories.
- B. Monte Carlo analysis quantifies risks already identified and does not reveal new categories.
- C. Decision trees and Ishikawa diagrams analyze specific decisions or causes and do not survey categories of risk.
Question 153
Two companies merge. The executive leadership team for the newly formed company hires a project risk manager to integrate both companies' technology platforms into a single global platform. Since success of this integration project is critical for the new company, the project risk manager determines that risk management is vital.
What factors does risk response planning include?
- A. People, planning, and analysis
- B. People, planning, and avoidance
- C. Planning, avoidance, and analysis
- D. People, avoidance, and analysis
Show answer and explanation ▾
Correct answer: A
Response planning involves people, because owners must be assigned and must agree to act; planning, because actions, timing and resources are set; and analysis, because options are evaluated before a strategy is chosen.
Why the other options are wrong:
- B. Avoidance is one response strategy, not a factor of response planning itself.
- C. Avoidance is one response strategy, and this list leaves out people.
- D. Avoidance is one response strategy, and this list leaves out planning.
Question 154
The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database. A ) Effectiveness of risk response B ) Unexpected or undocumented risks which occur C ) Relevant risk data D ) Management reserve report Which of the following should be included?
- A. A, B, C
- B. A, C, D
- C. B, C, D
- D. A, B, D
Show answer and explanation ▾
Correct answer: A
Lessons learned from monitoring cover how effective the risk responses were, any unexpected or undocumented risks that occurred, and relevant risk data that future projects can use.
Why the other options are wrong:
- B. A management reserve report is a financial record, and this set leaves out unexpected risks.
- C. A management reserve report is a financial record, and this set leaves out response effectiveness.
- D. A management reserve report is a financial record, and this set leaves out relevant risk data.
Question 155
The risk manager for a project successfully establishes the risk management plan, the risk register and performs the qualitative risk analysis with the team. As the first step of the analysis, the risk manager develops the probability and impact scales. The scales are presented to the project manager, who refuses to accept the proposed scales.
What did the risk manager overlook prior to developing probability and impact scales?
- A. Gaining approvals for the developed risk register from the project manager
- B. Informing the project manager about the risk management process
- C. Evaluating and understanding the risk appetite of the stakeholders
- D. Interviewing the stakeholders and related parties
Show answer and explanation ▾
Correct answer: B
Probability and impact scales are part of the agreed risk management process. Had the project manager been informed about that process and where the scales fit in it, the proposed scales would not have been rejected on first sight.
Why the other options are wrong:
- A. The risk register lists risks and does not define the scales.
- C. Stakeholder risk appetite is not what the project manager objected to in this scenario.
- D. Interviews gather information about risks and are not the step that was missed here.
Question 156
A new risk manager has been hired on a project and meets with the project director. The project director supplies the project’s risk register and asks the risk manager for an analysis of its effectiveness.
What two actions should the risk manager do next? (Choose two.)
- A. Check for risk classification and that probability and impact are identified.
- B. Check to ensure that the risk is supported by a Monte Carlo simulation.
- C. Check to ensure the risk meeting agenda and supporting documents are distributed.
- D. Check to ensure that risk origin, triggering event, and ownership is identified.
- E. Check to ensure that the risks are gathered using Delphi technique.
Show answer and explanation ▾
Correct answer: C, D
A register is effective when each risk is fully described, with its origin, triggering event and owner, and when it is actively used, which shows in risk meetings whose agenda and supporting documents are distributed to participants.
Why the other options are wrong:
- A. Classification and probability and impact ratings alone do not show that risks are owned and acted on.
- B. A Monte Carlo simulation is not required for every risk in a register.
- E. The technique used to gather the risks does not determine whether the register is effective.
Question 157
During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing.
What should the risk manager do?
- A. Take note of the extensive impact of these risks in the risk register
- B. Address the unique characteristics of these risks on a case-by-case basis
- C. Include an escalation process in the risk management plan
- D. Contact the risk managers of the other projects and inform them
Show answer and explanation ▾
Correct answer: D
Risks that reach beyond the project cannot be managed inside it alone, so the people accountable for the affected projects must be told. Informing the other projects' risk managers lets them assess the risks and respond.
Why the other options are wrong:
- A. A note in this project's risk register does not alert the other projects.
- B. Handling the risks case by case inside this project leaves the other projects unaware.
- C. A process written into the plan does not by itself notify the affected projects.
Question 158
An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.
What should the risk manager do next?
- A. Utilize different tools to identify the risks
- B. Update the risk register with the identified risks
- C. Add only the threats to the risk register
- D. Plan risk responses to the threats
Show answer and explanation ▾
Correct answer: B
The opportunities and threats found in a SWOT analysis are identified risks, so the next step is to record them in the risk register before any analysis or response planning.
Why the other options are wrong:
- A. The risks have just been identified, so recording them comes first.
- C. Opportunities are risks too and belong in the register.
- D. Responses are planned after risks are recorded and analyzed, and they cover opportunities as well as threats.
Question 159
A risk manager documents the causes of a risk in the risk register but needs to ensure the risk is adequately described.
Which aspect is critical for the risk manager to consider when describing the causes?
- A. Each cause is documented clearly and concisely
- B. The causes represent actual conditions
- C. Each cause has a degree of uncertainty
- D. The causes represent hypothetical scenarios
Show answer and explanation ▾
Correct answer: C
A risk description should show how firmly the team knows what lies behind the risk. Considering the degree of uncertainty attached to each cause keeps the description from overstating what is known.
Why the other options are wrong:
- A. Clear and concise wording is good practice for every register entry and is not specific to describing causes.
- B. Stating that the causes are actual conditions does not show how firmly each one is established.
- D. Causes are not hypothetical scenarios, they are the conditions that give rise to the risk.
Question 160
A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization’s risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges.
What two actions should the risk owner take? (Choose two.)
- A. Update and communicate assessments of the secondary risk’s impact.
- B. Implement the secondary risk response and update the project documents.
- C. Set the corresponding trigger conditions to the secondary risk.
- D. Engage the project manager to authorize the secondary risk’s response.
- E. Conduct meeting with all stakeholder to agree on post impact solutions.
Show answer and explanation ▾
Correct answer: A, B
The secondary risk was registered with an agreed response, so when it emerges the risk owner carries out that response and updates the project documents, and also reassesses its impact and communicates the updated assessment.
Why the other options are wrong:
- C. Trigger conditions are defined before a risk occurs, not after it has emerged.
- D. The response was already agreed when the risk was registered, so no new authorization is needed.
- E. A meeting of all stakeholders is not required for a risk that sits within the agreed thresholds.
Question 161
A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors.
What should the project manager do when engaging stakeholders?
- A. Include all stakeholders in the project’s governance.
- B. Ignore any risks beyond stakeholders’ tolerance.
- C. Communicate response strategies to all stakeholders.
- D. Consider stakeholders’ positions and opinions regarding the project’s output.
Show answer and explanation ▾
Correct answer: D
Engaging a wide mix of stakeholders means understanding each group's position and opinion on what the project will deliver, since those views shape their risk attitudes and the risks the project faces.
Why the other options are wrong:
- A. Governance includes only those with decision authority, not every stakeholder.
- B. Risks beyond stakeholder tolerance demand attention and cannot be ignored.
- C. Response strategies are shared with those who need them, not with every stakeholder.
Question 162
In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.
How should the project manager address this concern with the health authorities?
- A. Assess and record associated secondary risks and proceed to treat them as any other risks.
- B. Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.
- C. Proceed with the project as normal since a minor number of residents will be affected negatively.
- D. Suspend the project as the secondary risk will negatively impact residents’ health which is not acceptable.
Show answer and explanation ▾
Correct answer: A
Health effects from the pesticides are a secondary risk created by the response to the insect threat. Secondary risks are assessed, recorded and managed in the same way as any other risk while the justified response goes ahead.
Why the other options are wrong:
- B. A trigger alone does not assess or manage the secondary risk.
- C. Proceeding as normal leaves an identified risk to residents unmanaged.
- D. The assessment shows that not acting has far more serious consequences, so suspension is not justified.
Question 163
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?
- A. Discuss the risk response strategies with the stakeholders.
- B. Ensure the risk register includes all identified risks.
- C. Develop a communication plan to share updates on risks.
- D. Add buffers to the schedule to accommodate risk.
Show answer and explanation ▾
Correct answer: C
Stakeholders who want clear visibility of risks and progress are served by a communication plan that sets out what risk information is shared, with whom and how often.
Why the other options are wrong:
- A. A single discussion of response strategies does not provide ongoing visibility.
- B. A complete register does not by itself keep stakeholders informed.
- D. Schedule buffers address risk exposure, not the stakeholders' need for visibility.
Question 164
A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.
How should a professional risk manager manage the risks in such situations?
- A. Conduct weekly risk management meetings with all stakeholders.
- B. Utilize proper documentation to help manage the risks.
- C. Adopt agile approaches to manage the risks.
- D. Adopt a predictive approach to manage the risks.
Show answer and explanation ▾
Correct answer: C
When conditions change often and long-term plans cannot be predicted, agile approaches fit best: work is planned in short iterations and risks are reviewed and reprioritized frequently as new information arrives.
Why the other options are wrong:
- A. Weekly meetings with all stakeholders add overhead without changing how the work adapts to change.
- B. Documentation alone does not help the team respond to changing conditions.
- D. A predictive approach depends on stable long-term plans, which this environment lacks.
Question 165
What are three examples of risk thresholds? (Choose three.)
- A. A risk with a less than one-month schedule delay will be communicated through the areas of concerns section in the project status report instead of the risk register.
- B. An organization seeks to establish a consistent method for evaluating and responding to risk across the enterprise.
- C. A project has defined the project level risk rating matrix based on the likelihood of occurrence and possible consequences of schedule and cost.
- D. A business unit agreed that top project risks with more than US$100 million impacts would be escalated.
- E. A construction company walks away from a joint venture project proposal due to a 30% chance of loss.
Show answer and explanation ▾
Correct answer: A, D, E
A risk threshold is a specific level of exposure at which a defined action applies: a delay under one month is reported outside the risk register, an impact above US$100 million is escalated, and a 30% chance of loss leads the company to decline a proposal.
Why the other options are wrong:
- B. A consistent enterprise-wide method describes a risk management framework, not a threshold.
- C. A risk rating matrix is a tool for scoring risks, not a limit that triggers an action.
Question 166
A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.
What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)
- A. Scope of work and requirements
- B. Organization chart for city permit department
- C. List of pre-approved contractors
- D. Risk management plan
- E. Monte Carlo analysis from a similar project
Show answer and explanation ▾
Correct answer: A, D
An inexperienced team prepares for risk identification by learning what the project must deliver, from the scope of work and requirements, and how risk management will be carried out, from the risk management plan.
Why the other options are wrong:
- B. An outside agency's organization chart does not prepare the team to identify project risks.
- C. A contractor list does not explain the project's scope or its risk process.
- E. Monte Carlo results from another project are quantitative output and do not prepare a team for identification.
That was 166 of 560.
The full PMI-RMP pack has all 560 questions, each with the answer, the explanation and why the other options are wrong, plus a questions-only copy for timed runs. $39.00 USD, paid once, with free monthly updates and a pass-or-your-money-back guarantee.
Get the full packNot ready yet? Get the first 178 free as one PDF by email. Get the Half Pack →
About the PMI-RMP exam
These 166 PMI-RMP questions are free here. The free PDF has 178, free by email.
They are drawn from the same bank as the full PMI-RMP pack, which has 560 questions in total.