Question 1

Which is a purpose of using a risk maturity model?

  • A. Identify where the application of risk management within an organization can be improved
  • B. Understand the nature of risks facing an organization and the actions needed to respond
  • C. Provide independent risk information at key decision points within a program or project
  • D. Show to which organizational activities risk management should be applied
Show answer and explanation ▾

Correct answer: A

A risk maturity model scores how well risk management is applied today, which shows where it can be improved.

Why the other options are wrong:

  • B. Understanding the risks an organization faces and the responses needed is the job of risk identification and assessment.
  • C. Independent risk information at decision points is the purpose of assurance, not a maturity model.
  • D. Deciding which activities need risk management is a scoping decision, not what a maturity model does.

Question 2

Which does the SWOT analysis technique help to identify about an organization?

  • A. Long-term trends
  • B. Stakeholder views
  • C. Corporate governance requirements
  • D. Internal strengths
Show answer and explanation ▾

Correct answer: D

SWOT looks at an organization from the inside (strengths and weaknesses) and outside (opportunities and threats). Of the choices, only internal strengths is a SWOT output.

Why the other options are wrong:

  • A. Long-term trends are better shown by a PESTLE-type analysis.
  • B. Stakeholder views come from stakeholder analysis.
  • C. Governance requirements come from policies and regulation, not SWOT.

Question 3

Which technique can be used to clarify potential sources of risks across an activity?

  • A. Probabilistic risk models
  • B. Summary risk profiles
  • C. Risk breakdown structure
  • D. Decision trees
Show answer and explanation ▾

Correct answer: C

A risk breakdown structure splits an activity into categories of risk source, so it clarifies where risks could come from.

Why the other options are wrong:

  • A. Probabilistic risk models quantify exposure rather than clarify sources.
  • B. A summary risk profile shows the overall level of risk, not its sources.
  • D. Decision trees compare choices and outcomes, not sources of risk.

Question 4

What objectives are associated with decisions on risks to the achievement of long-term goals?

  • A. Strategic
  • B. Programme
  • C. Project
  • D. Operational
Show answer and explanation ▾

Correct answer: A

Strategic objectives describe the long-term goals of the organization, so decisions on the risks to them are strategic.

Why the other options are wrong:

  • B. Programme objectives relate to a programme, not the organization's long-term goals.
  • C. Project objectives are limited to a single project.
  • D. Operational objectives cover day-to-day delivery.

Question 5

Which explains a use of the risk management policy in the identify context' step?

  • A. Identifies changes to the organization's market
  • B. Identifies how past events could become sources of risk
  • C. Describes how corporate governance will affect the risk management process
  • D. Understand the maximum amount of risk that should be taken
Show answer and explanation ▾

Correct answer: D

The risk management policy sets the organization's appetite, which tells you how much risk it is willing to take when you identify the context.

Why the other options are wrong:

  • A. Changes in the market are found by analysing the environment, not from the policy.
  • B. How past events became risk sources comes from lessons learned and history.
  • C. How corporate governance affects the process is a matter for the framework, not the use of the policy in this step.

Question 6

What step is used to determine those risks which have the greatest effect on the objectives of a planned activity?

  • A. Identify
  • B. Assess
  • C. Plan
  • D. Implement
Show answer and explanation ▾

Correct answer: B

The assess step estimates the probability, impact and proximity of each identified risk so that risks can be prioritized. This shows which risks have the greatest effect on the objectives of the planned activity.

Why the other options are wrong:

  • A. Identify finds and describes the risks but does not rank their effect on objectives.
  • C. Plan prepares responses to risks that have already been assessed.
  • D. Implement carries out the planned responses and monitors their effectiveness.

Question 7

Which is NOT a reason for carrying out an ‘M_o_R health check?

  • A. Identify areas for improvement
  • B. Help gain maximum value from investment in risk management
  • C. Provide a snapshot of the current status of identified risks
  • D. Review how well risk management practices have been embedded
Show answer and explanation ▾

Correct answer: C

A health check examines how well risk management itself is being applied in the organization. A snapshot of the current status of identified risks comes from the risk records and reporting of an activity, not from a health check.

Why the other options are wrong:

  • A. Identifying areas for improvement is a core reason for running a health check.
  • B. Helping the organization gain maximum value from its investment in risk management is a reason for a health check.
  • D. Reviewing how well risk management practices have been embedded is a reason for a health check.

Question 8

Which is NOT an action needed to achieve the goal of the 'assess - evaluate' step?

  • A. Determine which other risks will occur if a risk occurs
  • B. Calculate the total risk exposure for the activity
  • C. Evaluate the effectiveness of risk management across the organization
  • D. Determine which risks are independent of other risks
Show answer and explanation ▾

Correct answer: C

The evaluate step looks at the combined effect of the risks facing one activity. Judging how effective risk management is across the whole organization belongs to embedding and reviewing, not to this step.

Why the other options are wrong:

  • A. Working out which risks are triggered by other risks is part of understanding the aggregated risk picture.
  • B. Calculating the total risk exposure for the activity is the central purpose of the evaluate step.
  • D. Establishing which risks are independent of others is needed to combine risks correctly.

Question 9

Which role provides sponsorship to ensure that risk management is embraced within the organization?

  • A. Senior manager
  • B. Manager
  • C. Assurance
  • D. Risk specialist
Show answer and explanation ▾

Correct answer: A

The senior manager role provides the sponsorship that makes sure risk management is embraced and applied within the organization.

Why the other options are wrong:

  • B. The manager role applies risk management on an activity instead of sponsoring it for the organization.
  • C. Assurance checks that risk management is being applied effectively and does not sponsor it.
  • D. The risk specialist provides expertise and support for risk management and is not the sponsoring role.

Question 10

What step is used to determine the time period when a risk might occur?

  • A. Identify - risks
  • B. Assess - estimate
  • C. Assess - evaluate
  • D. Identify-context
Show answer and explanation ▾

Correct answer: B

The estimate step assesses each risk in terms of probability, impact and proximity. Proximity is the time period in which the risk might occur.

Why the other options are wrong:

  • A. The identify risks step finds and describes threats and opportunities without estimating their timing.
  • C. The evaluate step looks at the combined effect of all risks, not the timing of an individual risk.
  • D. The identify context step gathers information about the activity and its objectives before risks are identified.

Question 11

How is the risk progress report used in the 'implement' step?

  • A. Identify the status against the activity's stated measures for risk management
  • B. Identify the scales used to measure the probability and impact of a risk
  • C. Describe actions to enhance how risk management is performed
  • D. Gain agreement for the amount of risk that can be taken
Show answer and explanation ▾

Correct answer: A

The risk progress report gives regular information on how risk management is progressing within an activity. In the implement step it shows the status against the measures set for risk management on that activity.

Why the other options are wrong:

  • B. The scales for probability and impact are set out in the risk management strategy.
  • C. Actions to enhance how risk management is performed belong in a risk improvement plan.
  • D. Agreement on the amount of risk that can be taken is reached when risk appetite and tolerance are set, not through this report.

Question 12

Which document describes how risk management activities will support the achievement of corporate objectives throughout an organization?

  • A. Risk management strategy
  • B. Risk management process guide
  • C. Risk progress report
  • D. Risk management policy
Show answer and explanation ▾

Correct answer: D

The risk management policy communicates how risk management will be implemented throughout the organization to support the achievement of its corporate objectives.

Why the other options are wrong:

  • A. The risk management strategy describes the risk management activities for one particular organizational activity.
  • B. The risk management process guide describes the steps of the process and how they are carried out.
  • C. The risk progress report gives regular progress information on risk management within an activity.

Question 13

Which is a goal of the 'assess - evaluate' step?

  • A. Evaluate the impact, probability and how soon risks might occur
  • B. Calculate the net effect of risks facing the activity
  • C. Assess and evaluate the effectiveness of procedures for managing risks
  • D. Evaluate the net cost of planned risk responses
Show answer and explanation ▾

Correct answer: B

The goal of the evaluate step is to understand the net effect of the identified threats and opportunities on the activity when they are aggregated together.

Why the other options are wrong:

  • A. Assessing impact, probability and proximity of individual risks is the work of the estimate step.
  • C. Assessing the effectiveness of procedures for managing risks is part of embedding and reviewing.
  • D. The cost of planned risk responses is considered in the plan step.

Question 14

Which of the M_o_R framework core concepts is informed by corporate governance principles and the international standard for risk management

ISO31000:2009?

  • A. M_o_R approach
  • B. M_o_R principles
  • C. M_o_R process
  • D. Embedding and reviewing M_o_R
Show answer and explanation ▾

Correct answer: B

The M_o_R principles are informed by corporate governance principles and by the international standard for risk management, ISO 31000:2009.

Why the other options are wrong:

  • A. The M_o_R approach is how the principles are adapted and documented for the organization.
  • C. The M_o_R process is the set of steps used to identify, assess, plan and implement.
  • D. Embedding and reviewing makes sure the principles, approach and process are applied consistently and improved over time.

Question 15

What ensures that an organization's implementation of the M_o_R approach' and 'M_o_R process' undergoes frequent improvement to remain effective?

  • A. Corporate governance
  • B. Internal controls
  • C. Embedding and reviewing
  • D. Contingency planning
Show answer and explanation ▾

Correct answer: C

Embedding and reviewing ensures that the approach and process are applied consistently across the organization and are regularly reviewed and improved so that they remain effective.

Why the other options are wrong:

  • A. Corporate governance is the system by which organizations are directed and controlled, not the M_o_R concept for improving risk management.
  • B. Internal controls are measures that manage risk and do not drive improvement of the approach and process.
  • D. Contingency planning prepares responses for use if a risk occurs and does not improve the framework.

Question 16

Identify the missing words in the following sentence. The lack of [ ? ] is a common barrier to implementing the risk management process.

  • A. a high-risk appetite
  • B. appropriate responses to risks
  • C. clear guidance for managers and staff
  • D. an assigned risk owner
Show answer and explanation ▾

Correct answer: C

A lack of clear guidance for managers and staff is one of the common barriers to implementing the risk management process, because people do not know what is expected of them.

Why the other options are wrong:

  • A. A high risk appetite is not a requirement for implementing the risk management process.
  • B. A missing response to a risk is a gap in applying the process, not a common barrier to implementing it.
  • D. A missing risk owner is a gap in managing an individual risk, not a common barrier to implementing the process.

Question 17

What step is used to determine the likelihood of a risk occurring?

  • A. Identify - risks
  • B. Assess - estimate
  • C. Assess - evaluate
  • D. Identify-context
Show answer and explanation ▾

Correct answer: B

The estimate step assesses each identified risk in terms of its probability, impact and proximity. Probability is the likelihood of the risk occurring.

Why the other options are wrong:

  • A. The identify risks step finds and describes risks without estimating their likelihood.
  • C. The evaluate step looks at the combined effect of all risks on the activity.
  • D. The identify context step gathers information about the activity and its objectives.

Question 18

What is risk exposure?

  • A. Amount of risk the organization, or subset of it, is willing to accept
  • B. Maximum amount of risk that an organization can bear
  • C. Combined effect of risks to a set of objectives
  • D. System by which organizations are directed and controlled
Show answer and explanation ▾

Correct answer: C

Risk exposure is the extent of risk borne by the organization at a given time, shown as the combined effect of the risks to a set of objectives.

Why the other options are wrong:

  • A. The amount of risk an organization, or a subset of it, is willing to accept is risk appetite.
  • B. The maximum amount of risk that an organization can bear is risk capacity.
  • D. The system by which organizations are directed and controlled is corporate governance.

Question 19

Which activity is focused on when the 'aligns with objectives' principle is applied to the project perspective?

  • A. Implementing business strategy to improve organizational performance
  • B. Developing plans to improve the overall efficiency of the organization
  • C. Maintaining the appropriate levels of service delivery to new and existing customers
  • D. Delivering defined business change products within budget and on time
Show answer and explanation ▾

Correct answer: D

Project objectives are about delivering defined business change products within set constraints such as time and budget, so aligning risk management with objectives at this perspective focuses on that delivery.

Why the other options are wrong:

  • A. Implementing business strategy to improve organizational performance goes beyond the delivery of defined products that a project is set up for.
  • B. Improving the overall efficiency of the organization is not the focus of the project perspective.
  • C. Maintaining appropriate levels of service delivery to customers is the focus of the operational perspective.

Question 20

Which BEST describes an area of uncertainty at the operational perspective?

  • A. Changes to the delivery schedule of business products
  • B. Conflicts during the implementation of business strategy
  • C. Capabilities of the infrastructure to deliver services
  • D. Opinions of stakeholders that may affect the organizational reputation
Show answer and explanation ▾

Correct answer: C

The operational perspective is concerned with maintaining day-to-day business services, so uncertainty about whether the infrastructure can deliver those services sits at this level.

Why the other options are wrong:

  • A. Changes to the delivery schedule of business products are a project perspective uncertainty.
  • B. Conflicts during the implementation of business strategy relate to turning strategy into change, not to day-to-day service delivery.
  • D. Stakeholder opinions that may affect the reputation of the organization concern the organization as a whole, not day-to-day service delivery.

Question 21

Which task will be carried out while performing the 'identify - risks' step?

  • A. Calculating when an identified risk is likely to occur
  • B. Ranking the importance of the stakeholders involved in the activity
  • C. Ensuring that all participants agree on the identified risks
  • D. Developing an appropriate response to the identified risks
Show answer and explanation ▾

Correct answer: C

The identify risks step is where the threats and opportunities facing the activity are found and described. Bringing the participants to an agreed view of those risks belongs to this step, before any estimating or response planning begins.

Why the other options are wrong:

  • A. Working out when a risk is likely to occur is proximity, which is assessed in the estimate step.
  • B. Ranking the importance of stakeholders is stakeholder analysis, which belongs to the identify context step.
  • D. Developing responses to identified risks is done in the plan step.

Question 22

Identify the missing word in the following sentence. The impact of risks to organizational goals at the [ ? ] perspective may only become noticeable far into the future.

  • A. strategic
  • B. programme
  • C. project
  • D. operational
Show answer and explanation ▾

Correct answer: A

The strategic perspective deals with the long-term direction and goals of the whole organization, so the effect of risks at this level may only be seen far into the future.

Why the other options are wrong:

  • B. The programme perspective covers delivery of business change over the medium term.
  • C. The project perspective covers delivery of defined products within set time and cost limits, a shorter horizon.
  • D. The operational perspective covers day-to-day service delivery, where effects are felt in the short term.

Question 23

Which is NOT a recommended risk response option for an 'opportunity'?

  • A. Enhance
  • B. Transfer
  • C. Share
  • D. Reduce
Show answer and explanation ▾

Correct answer: D

Reduce is a response to a threat, used to lower its probability or impact. Opportunities are handled with responses such as exploit, enhance, transfer, share and accept.

Why the other options are wrong:

  • A. Enhance is a recommended response for an opportunity, making it more likely or more beneficial.
  • B. Transfer is a recommended response that can be applied to an opportunity as well as a threat.
  • C. Share is a recommended response that can be applied to an opportunity as well as a threat.

Question 24

Which is a purpose of the 'risk management policy'?

  • A. Explain the actions required to implement risk management
  • B. Define the Specific risk management activities that will be performed for an activity
  • C. Describe how risk management practices will be implemented throughout an organization
  • D. Record information about threats and opportunities for an organizational activity
Show answer and explanation ▾

Correct answer: C

The risk management policy communicates how risk management will be implemented throughout the organization to support the achievement of its objectives.

Why the other options are wrong:

  • A. The policy states how risk management will be implemented across the organization, not the individual actions needed to put it in place.
  • B. Defining the specific risk management activities for one activity is the purpose of the risk management strategy.
  • D. Recording information about threats and opportunities for an activity is the purpose of the risk register.

Question 25

What is the goal of the 'assess - estimate' step?

  • A. Identify the threats and opportunities facing the organizational activity
  • B. Estimate and agree the budget required to manage risks to the activity
  • C. Assess the effectiveness of the risk management processes within an organization
  • D. Determine the risks with the greatest effect on activities objectives
Show answer and explanation ▾

Correct answer: D

The goal of the estimate step is to prioritize each identified risk so that it is clear which risks matter most to the objectives of the activity. It does this by assessing probability, impact and proximity.

Why the other options are wrong:

  • A. Identifying the threats and opportunities facing the activity is the goal of the identify risks step.
  • B. Agreeing a budget for managing risks is not the goal of the estimate step.
  • C. Assessing the effectiveness of risk management processes in the organization is part of embedding and reviewing.

Question 26

Which BEST describes an area of uncertainty at the programme perspective?

  • A. Disruptions to operations during business change implementation
  • B. Introduction of new laws that affect core business activities
  • C. Availability of resources for the day-to-day delivery of services to customers
  • D. Changes to the scope of defined business products
Show answer and explanation ▾

Correct answer: A

The programme perspective is concerned with delivering business change, so the risk of disrupting operations while that change is being implemented is an uncertainty at this level.

Why the other options are wrong:

  • B. New laws that affect core business activities concern the organization as a whole and are not specific to delivering business change.
  • C. Availability of resources for day-to-day service delivery is an operational perspective uncertainty.
  • D. Changes to the scope of defined business products are a project perspective uncertainty.

Question 27

Which heading in a 'risk register is used to record the area of uncertainty?

  • A. Cause
  • B. Event
  • C. Effect
  • D. Probability
Show answer and explanation ▾

Correct answer: B

A risk is described as a cause, an event and an effect. The event is the area of uncertainty, described as the threat or opportunity that may occur.

Why the other options are wrong:

  • A. The cause is the source of the risk, the situation that gives rise to it.
  • C. The effect is the impact the risk would have on objectives if it occurred.
  • D. Probability records how likely the risk is to occur, not what the uncertainty is.

Question 28

Which perspective ensures risk management maintains a view of the adequacy of controls that support service delivery to satisfy the fits the context principle?

  • A. Strategic
  • B. Programme
  • C. Operational
  • D. Project
Show answer and explanation ▾

Correct answer: C

The operational perspective is concerned with maintaining day-to-day business services, so here risk management keeps a view of whether the controls that support service delivery are adequate.

Why the other options are wrong:

  • A. The strategic perspective is concerned with the long-term direction of the organization, not service delivery controls.
  • B. The programme perspective is concerned with delivering business change, not ongoing service delivery.
  • D. The project perspective is concerned with delivering defined products within time and cost limits.

Question 29

Which BEST describes an area of uncertainty at the programme perspective?

  • A. Schedule of business products to time and cost
  • B. Availability of skills to deliver services to new and existing customers
  • C. Implementing new business practices across organizational boundaries
  • D. Legislation that affects core business activities
Show answer and explanation ▾

Correct answer: C

The programme perspective is concerned with delivering business change that turns strategy into new ways of working, so introducing new business practices across organizational boundaries is an uncertainty at this level.

Why the other options are wrong:

  • A. The schedule of business products against time and cost is a project perspective uncertainty.
  • B. Availability of skills to deliver services to customers is an operational perspective uncertainty.
  • D. Legislation that affects core business activities concerns the organization as a whole and is not specific to delivering business change.

Question 30

Which is a common barrier to implementing the risk management process?

  • A. Lack of a high-risk appetite at senior management level
  • B. Lack of an appropriate response to a risk in an activity's risk register
  • C. Lack of an assigned risk owner
  • D. Lack of policies, processes, strategies and plans
Show answer and explanation ▾

Correct answer: D

A lack of policies, processes, strategies and plans is one of the common barriers to implementing the risk management process, because there is no agreed framework for people to follow.

Why the other options are wrong:

  • A. A high risk appetite is not a requirement for implementing the risk management process.
  • B. A missing response to one risk is a gap in applying the process, not a common barrier to implementing it.
  • C. A missing risk owner is a gap in managing an individual risk, not a common barrier to implementing the process.

Question 31

What are the M_o_R principles informed by?

  • A. Statements of internal control
  • B. International standard for risk management ISO31000:2009
  • C. Public Company Accounting and Reform and Investor Protection Act
  • D. Basel Accord (Basel II)
Show answer and explanation ▾

Correct answer: B

The M_o_R principles are informed by corporate governance principles and by the international standard for risk management, ISO 31000:2009.

Why the other options are wrong:

  • A. Statements of internal control are a governance reporting output, not the basis of the principles.
  • C. This Act is legislation on corporate accountability and is not what the principles are informed by.
  • D. The Basel Accord is banking regulation and is not what the principles are informed by.

Question 32

Who does a 'risk actionee' keep up to date on progress when implementing a response to a risk?

  • A. Senior team
  • B. Audit committee
  • C. Risk owner
  • D. Team
Show answer and explanation ▾

Correct answer: C

A risk actionee carries out a risk response on behalf of the risk owner and keeps the risk owner informed of progress. The risk owner remains responsible for managing the risk.

Why the other options are wrong:

  • A. The senior team sets the overall direction for risk management and does not receive progress on individual responses from the actionee.
  • B. The audit committee oversees assurance and is not who the actionee reports response progress to.
  • D. The team takes part in risk management on the activity but is not who the actionee reports response progress to.

Question 33

Identify the missing word in the following sentence. Applying the 'aligns with objectives' principle at the [ ? ] perspective ensures risk management is responsive to changes to objectives that meet shareholder needs, reputation and demand for services.

  • A. operational
  • B. project
  • C. programme
  • D. strategic
Show answer and explanation ▾

Correct answer: D

Shareholder needs, reputation and demand for services are concerns of the whole organization. Objectives of this kind are set at the strategic perspective, so that is where risk management must respond to changes in them.

Why the other options are wrong:

  • A. Operational objectives are about maintaining day-to-day service delivery.
  • B. Project objectives are about delivering defined products within time and cost limits.
  • C. Programme objectives are about delivering business change and its benefits.

Question 34

Which BEST describes an area of uncertainty at the programme perspective?

  • A. Changes to customer requirements for business products
  • B. Interdependences between business change initiatives
  • C. Ability of the infrastructure to meet the required level of service
  • D. Operational activities that may affect the organizational reputation
Show answer and explanation ▾

Correct answer: B

A programme coordinates a set of related projects and change activities, so the interdependencies between business change initiatives are an uncertainty at the programme perspective.

Why the other options are wrong:

  • A. Changes to customer requirements for business products are a project perspective uncertainty.
  • C. The ability of the infrastructure to meet the required level of service is an operational perspective uncertainty.
  • D. Operational activities that may affect the reputation of the organization are not a programme perspective uncertainty.

Question 35

Identify the missing words in the following sentence. Because organizations [ ? ] they need to use the environmental risk management' specialism.

  • A. are concerned about stakeholder perceptions
  • B. see brand and reputation as key assets
  • C. face financial penalties for polluting waterways
  • D. fail to deliver minimum standards
Show answer and explanation ▾

Correct answer: C

Environmental risk management deals with the harm an organization may cause to the environment and the consequences that follow, such as financial penalties for polluting waterways.

Why the other options are wrong:

  • A. Concern about stakeholder perceptions relates to reputation, not to the environmental specialism.
  • B. Protecting brand and reputation as assets relates to reputational risk management.
  • D. Failing to deliver minimum standards is not the driver for environmental risk management.

Question 36

Which action is NOT needed in order for risk management to be effective?

  • A. Identify the risk
  • B. Eliminate the risk
  • C. Assess the risk
  • D. Control the risk
Show answer and explanation ▾

Correct answer: B

For risk management to be effective, risks need to be identified, assessed and controlled. Risk cannot be removed altogether, and some risk taking is needed to achieve objectives, so eliminating risk is not required.

Why the other options are wrong:

  • A. Risks must be identified before anything can be done about them.
  • C. Risks must be assessed so that they can be prioritized.
  • D. Risks must be controlled through planned responses that are carried out and monitored.

Question 37

Which is a benefit of effective risk management?

  • A. Activity plans are agreed before the activity commences
  • B. Staff members are better prepared to respond to incidents
  • C. Removes the organization's need to take risks
  • D. Guarantees business benefits will be delivered
Show answer and explanation ▾

Correct answer: B

Effective risk management means threats have been thought through in advance, so staff are better prepared to respond when incidents occur and there are fewer surprises.

Why the other options are wrong:

  • A. Agreeing activity plans before work starts is a planning matter, not a benefit of risk management.
  • C. Organizations must still take risks to achieve their objectives.
  • D. Risk management improves the chance of success but cannot guarantee that benefits will be delivered.

Question 38

What is a 'central risk function'?

  • A. A group with formal responsibility for supporting strategic risk management
  • B. A group that may pose a risk to objectives through its opposition to plans
  • C. A group responsible for approving the funding for risk management
  • D. A group that acts on risks escalated from other perspectives
Show answer and explanation ▾

Correct answer: A

A central risk function is a group with formal responsibility for supporting risk management at the strategic level of the organization.

Why the other options are wrong:

  • B. A group that may oppose plans and so pose a risk to objectives describes a source of risk, not a function that supports risk management.
  • C. Approving the funding for risk management is not what defines a central risk function.
  • D. Acting on risks escalated from other perspectives is not what defines a central risk function.

Question 39

Which is a use of the risk management policy in the 'identify - context' step for an activity?

  • A. Recording departures from the risk management process guide
  • B. Identifying the activity-specific categories to be used for grouping risks
  • C. Providing guidance on setting risk tolerance thresholds
  • D. Defining the records to be used
Show answer and explanation ▾

Correct answer: C

The risk management policy sets out the risk appetite and capacity of the organization and gives guidance on tolerance thresholds. In the identify context step this guidance is used to set the tolerances for the activity.

Why the other options are wrong:

  • A. Departures from the risk management process guide are recorded in the risk management strategy.
  • B. Activity-specific risk categories are set in the risk management strategy.
  • D. The records to be used for the activity are defined in the risk management strategy.

Question 40

Which effect on the organization's objectives could the PESTLE analysis technique help to identify

  • A. Risk exposure trends
  • B. Current external factors
  • C. Long-term developments
  • D. Internal strengths
Show answer and explanation ▾

Correct answer: B

PESTLE analysis examines the political, economic, social, technological, legal and environmental factors around an organization. It helps identify the current external factors that could affect its objectives.

Why the other options are wrong:

  • A. Risk exposure trends are shown by tracking risk information over time, not by PESTLE analysis.
  • C. Long-term developments are identified through horizon scanning.
  • D. Internal strengths are identified through SWOT analysis.

Question 41

Which BEST describes an area of uncertainty at the operational perspective?

  • A. Variation to the schedule of a defined business product
  • B. Availability of skills required to deliver services to customers
  • C. Minimizing disruptions to customer services during transformational change
  • D. Damage to the organization's infrastructure
Show answer and explanation ▾

Correct answer: B

The operational perspective is concerned with maintaining day-to-day services, so uncertainty about having the skills needed to deliver services to customers sits at this level.

Why the other options are wrong:

  • A. Variation to the schedule of a defined business product is a project perspective uncertainty.
  • C. Minimizing disruption to customer services during transformational change is a programme perspective concern.
  • D. Damage to the infrastructure describes an impact, not an area of uncertainty about delivering services to customers.

Question 42

Which M_o_R principle advocates that an organization's risk appetite should be within the organization's risk capacity?

  • A. Aligns with objectives
  • B. Fits the context
  • C. Informs decision-making
  • D. Provides clear guidance
Show answer and explanation ▾

Correct answer: A

The aligns with objectives principle covers how much risk the organization can bear and how much it is willing to take in pursuit of its objectives. It requires risk appetite to stay within risk capacity.

Why the other options are wrong:

  • B. Fits the context is about tailoring risk management to the internal and external environment of the organization.
  • C. Informs decision-making is about using risk information when decisions are taken.
  • D. Provides clear guidance is about giving stakeholders coherent guidance on how to apply risk management.

Question 43

Which is a benefit of effective risk management?

  • A. Successful completion of all change activities
  • B. Organizations are better prepared to recover from unplanned incidents
  • C. Eliminates risk-taking within an organization
  • D. Guarantees business benefits will be delivered
Show answer and explanation ▾

Correct answer: B

Effective risk management means possible incidents and their consequences have been considered in advance, so the organization is better prepared to recover when something unplanned happens.

Why the other options are wrong:

  • A. Risk management improves the chance of success but cannot ensure every change activity succeeds.
  • C. Organizations must still take risks to achieve their objectives.
  • D. Risk management cannot guarantee that business benefits will be delivered.

Question 44

Which BEST describes the 'reduce the threat' risk response option?

  • A. Changing the planned tasks in an activity
  • B. Performing an action to minimize the chance of a risk impacting objectives
  • C. Monitoring a risk to ensure it remains within acceptable tolerance
  • D. Partaking in a pain/gain contract with another party for a specified risk
Show answer and explanation ▾

Correct answer: B

Reducing a threat means taking action now to lower the probability of the risk occurring or to limit its impact on objectives if it does occur.

Why the other options are wrong:

  • A. Changing the planned tasks so the risk can no longer occur describes avoiding a threat.
  • C. Monitoring a risk without taking action describes accepting it.
  • D. A pain/gain contract with another party describes sharing a risk.

Question 45

What is defined as the level of risk exposure that, once exceeded, will trigger an escalation?

  • A. Risk appetite
  • B. Risk capacity
  • C. Risk tolerance
  • D. Risk perception
Show answer and explanation ▾

Correct answer: C

Risk tolerance is the threshold level of risk exposure that, when exceeded, triggers an escalation to the next level of management.

Why the other options are wrong:

  • A. Risk appetite is the amount of risk the organization is willing to accept.
  • B. Risk capacity is the maximum amount of risk the organization can bear.
  • D. Risk perception is how a stakeholder views a risk, not a threshold.

Question 46

Which information is NOT found in the risk management process guide?

  • A. Which templates are to be used on a project
  • B. Why standard forms should be used
  • C. Where to find a blank risk register
  • D. How to use an issue register
Show answer and explanation ▾

Correct answer: A

The risk management process guide gives guidance on the process, tools, techniques and templates for the organization as a whole. What is used on one particular project is decided for that project and set out in its risk management strategy.

Why the other options are wrong:

  • B. The reason for using standard forms is organization-wide guidance that the process guide gives.
  • C. The location of standard templates, such as a blank risk register, is given in the process guide.
  • D. Guidance on using standard records is organization-wide information that the process guide gives.

Question 47

Which can be used to measure the impact a risk management awareness programme has on an organization?

  • A. Gateway reviews
  • B. Benchmarking
  • C. Risk questionnaires
  • D. Brainstorming
Show answer and explanation ▾

Correct answer: B

Benchmarking compares risk management practice against a reference point, so repeating it shows the change that an awareness programme has made in the organization.

Why the other options are wrong:

  • A. Gateway reviews assess a programme or project at decision points and do not measure the effect of an awareness programme.
  • C. Risk questionnaires are a technique for identifying risks.
  • D. Brainstorming is a technique for identifying risks.

Question 48

Which is NOT a use of the 'SWOT analysis' technique?

  • A. Identify external factors that may have an effect on the organization's objectives
  • B. Create an understanding of a current market position
  • C. Identify long-term developments that could affect the organization's objectives
  • D. Provide an internal and external environmental analysis when used with other techniques
Show answer and explanation ▾

Correct answer: C

SWOT analysis looks at the current strengths, weaknesses, opportunities and threats of an organization. Identifying long-term developments that could affect objectives is the use of horizon scanning.

Why the other options are wrong:

  • A. The opportunities and threats in SWOT are external factors that may affect objectives.
  • B. SWOT is used to build an understanding of the current position of the organization in its market.
  • D. SWOT can be combined with other techniques to analyze the internal and external environment.

Question 49

Which is a responsibility of the senior team role?

  • A. Approve assessments of risk probability, impact and proximity
  • B. Specify the required budget to fund risks
  • C. Document the importance of risk management towards achieving organizational objectives
  • D. Agree the timing of risk progress reports for an activity
Show answer and explanation ▾

Correct answer: C

The senior team sets the overall direction for risk management and is responsible for the risk management policy, which states why risk management matters for achieving the objectives of the organization.

Why the other options are wrong:

  • A. Approving assessments of probability, impact and proximity is done at the level of the activity, not by the senior team.
  • B. Specifying the budget needed to fund risks is not a senior team responsibility.
  • D. Agreeing the timing of risk progress reports for an activity is done at the level of the activity.

Question 50

Which is a common barrier to implementing the risk management process?

  • A. Lack of a high-risk appetite at senior management level
  • B. Lack of an appropriate response to a risk in an activity's risk register
  • C. Lack of an assigned risk owner
  • D. Lack of risk facilitation resources and time
Show answer and explanation ▾

Correct answer: D

A lack of risk facilitation resources and time is one of the common barriers to implementing the risk management process, because the steps cannot be carried out properly without them.

Why the other options are wrong:

  • A. A high risk appetite is not a requirement for implementing the risk management process.
  • B. A missing response to one risk is a gap in applying the process, not a common barrier to implementing it.
  • C. A missing risk owner is a gap in managing an individual risk, not a common barrier to implementing the process.

Question 51

What may be recorded in the risk register during the 'identify - risks' step?

  • A. The probability and impact of an identified risk
  • B. An action required to mitigate an identified risk
  • C. A risk description expressed as a cause, event and effect
  • D. The risk actionee for an identified risk response
Show answer and explanation ▾

Correct answer: C

In the identify risks step each threat and opportunity is entered in the risk register with a description of its cause, event and effect.

Why the other options are wrong:

  • A. Probability and impact are added in the estimate step.
  • B. Actions to respond to a risk are added in the plan step.
  • D. The risk actionee for a response is named in the plan step.

Question 52

Which is a benefit of effective risk management?

  • A. Successful completion of all change activities
  • B. Eliminates risk-taking within an organization
  • C. Improves the chances of organizational changes being successful
  • D. Guarantees business benefits will be delivered
Show answer and explanation ▾

Correct answer: C

Effective risk management helps an organization anticipate threats and opportunities when it makes changes, which improves the chances of those changes being successful.

Why the other options are wrong:

  • A. Risk management cannot ensure that every change activity is completed successfully.
  • B. Organizations must still take risks to achieve their objectives.
  • D. Risk management cannot guarantee that business benefits will be delivered.

Question 53

Which is a purpose of the risk management process guide?

  • A. Explain how the risk management steps will be carried out across the organization
  • B. Describe the specific risk management activities that will be performed on a particular organizational activity
  • C. Explain how risk management practices will be implemented throughout an organization
  • D. Describe the steps required to improve the level of risk management within an organization
Show answer and explanation ▾

Correct answer: A

The risk management process guide describes the series of steps in the risk management process and how they will be carried out across the organization.

Why the other options are wrong:

  • B. Describing the risk management activities for one particular activity is the purpose of the risk management strategy.
  • C. Explaining how risk management will be implemented throughout the organization is the purpose of the risk management policy.
  • D. Steps to improve the level of risk management belong in a risk improvement plan.

Question 54

What is the purpose of using an M_o_R 'health check'?

  • A. Understand the nature of risks facing an organization and the actions needed to respond
  • B. Provide alternative assurance and approval processes at key decision points within a programme
  • C. Examine an organization's current risk management practices to identify areas for improvement
  • D. Show which organizational activities that risk management should be applied to
Show answer and explanation ▾

Correct answer: C

An M_o_R health check examines how risk management is currently practiced in an organization or activity in order to identify areas for improvement.

Why the other options are wrong:

  • A. Understanding the risks facing the organization and the responses needed is the work of the risk management process.
  • B. Assurance and approval at decision points in a programme is the role of gateway reviews.
  • D. Showing which organizational activities risk management should be applied to is not the purpose of a health check.

Question 55

What objectives are associated with decisions about risks to the delivery of business change capabilities?

  • A. Strategic
  • B. Enterprise
  • C. Programme
  • D. Operational
Show answer and explanation ▾

Correct answer: C

Programmes turn strategy into new ways of working by delivering business change capabilities, so decisions about risks to that delivery relate to programme objectives.

Why the other options are wrong:

  • A. Strategic objectives concern the long-term direction and goals of the whole organization.
  • B. Enterprise is not the perspective associated with delivering business change capabilities.
  • D. Operational objectives concern maintaining day-to-day service delivery.

That was 55 of 140.

The full PeopleCert M_o_R Foundation pack has all 140 questions, each with the answer, the explanation and why the other options are wrong, plus a questions-only copy for timed runs. $39.00 USD, paid once, with free monthly updates and a pass-or-your-money-back guarantee.

Get the full pack

Not ready yet? Get the first 55 free as one PDF by email. Get the Half Pack →

About the M_o_R Foundation exam

These 55 PeopleCert M_o_R Foundation questions are free here, and as a free PDF by email.

They are drawn from the same bank as the full M_o_R Foundation pack, which has 140 questions in total.

Back to blog