Question 1

Which two of the following auditors would not participate in a first-party audit? (Choose two.)

  • A. An auditor trained in the IRCA scheme
  • B. An auditor employed by an external consultancy organization
  • C. An auditor from a customer
  • D. An auditor certified by IRCA
  • E. An auditor from an interested party
  • F. An auditor trained in-house
Show answer and explanation ▾

Correct answer: B, C

A first-party audit is an internal audit of the organization's own management system. An auditor from a customer carries out second-party audits, and an auditor employed by an external consultancy organization is not one of the organization's own auditors.

Why the other options are wrong:

  • A. Training under the IRCA scheme says nothing about who the auditor works for, so it does not exclude an internal auditor.
  • D. IRCA certification is a personal credential and does not prevent someone from auditing their own organization.
  • E. Interested parties include the organization's own people, so this description does not rule an auditor out of an internal audit.
  • F. An auditor trained in-house is a typical internal auditor.

Question 2

The following actions need to be carried out during a third-party audit planning stage.

Which two actions correspond to the individual(s) managing the audit program before the involvement of the audit team leader? (Choose two.)

  • A. Select the audit team members
  • B. Review the reports of previous audits
  • C. Assign responsibilities within the audit team
  • D. Provide the resources needed
  • E. Prepare the audit plan
  • F. Prepare the checklists
Show answer and explanation ▾

Correct answer: B, D

The individual(s) managing the audit program set up each audit before a team leader is involved. That includes taking the reports of previous audits into account and making sure the resources needed are provided.

Why the other options are wrong:

  • A. Selecting the audit team includes appointing its leader, so it is not an action that comes before the team leader is involved.
  • C. Assigning work within the team is the audit team leader's task.
  • E. The audit plan is prepared by the audit team leader.
  • F. Checklists are working documents prepared by the audit team members.

Question 3

In the context of a third-party certification audit, it is very important to have effective communication.

Which is not the responsibility of the audit team leader?

  • A. Planning formal communication arrangements, so an auditee can communicate with the auditor any time during the audit.
  • B. Confirming formal communication channels between the audit team and the auditee during the opening meeting.
  • C. If audit objectives are unattainable, reporting the reasons to the accreditation body.
  • D. Communicating the progress, any significant findings and any concerns to the auditee and audit client, as appropriate.
Show answer and explanation ▾

Correct answer: C

The audit team leader is responsible for communication with the auditee and the client. Reporting to an accreditation body that objectives cannot be met is not one of those duties; the leader reports to the audit client.

Why the other options are wrong:

  • A. Planning formal communication arrangements is a team leader responsibility.
  • B. Confirming formal communication channels at the opening meeting is the team leader's job.
  • D. Communicating progress and significant findings to the auditee and client is the team leader's job.

Question 4

Which two of the following are included in the objectives of the ‘stage I initial certification audit’? (Choose two.)

  • A. To evaluate the internal audit and management review processes.
  • B. To evaluate the preparedness of the organization for a Stage 2 audit.
  • C. To evaluate the performance of monitoring and reviewing activities.
  • D. To make a decision on certification to ISO 9001:2015.
  • E. To review the quality manual.
  • F. To evaluate the operational processes of the organization.
Show answer and explanation ▾

Correct answer: A, B

Stage 1 of an initial certification audit checks whether the organization is ready for stage 2. That includes confirming that internal audits and management reviews are being planned and performed, and judging the overall preparedness of the management system for the stage 2 audit.

Why the other options are wrong:

  • C. The performance of monitoring and reviewing activities is evaluated in stage 2.
  • D. The certification decision is made by the certification body after stage 2, not during stage 1.
  • E. ISO 9001:2015 does not require a quality manual, so reviewing one is not a stage 1 objective.
  • F. Operational processes are evaluated for implementation and effectiveness in stage 2.

Question 5

Which two of the following may be changed once a Stage 2 certification audit has commenced? (Choose two.)

  • A. Agreed language of the audit
  • B. Audit scope
  • C. Audit plan
  • D. Agreed standard for the audit criteria
  • E. Audit checklists
  • F. Increase of audit duration
Show answer and explanation ▾

Correct answer: C, E

The audit plan is meant to be flexible, so the team leader can adjust it as the audit progresses, in agreement with the auditee. Audit checklists are working documents of the auditors and can be amended as information is gathered.

Why the other options are wrong:

  • A. The language of the audit is agreed before the audit starts as part of its arrangements and is not a working document the audit team adjusts.
  • B. The audit scope is agreed before the audit as part of the certification arrangements and is not a working document the audit team adjusts.
  • D. The standard used as audit criteria is fixed for the certification being sought.
  • F. Audit duration is determined by the certification body when the audit is arranged and is not a working document the audit team adjusts.

Question 6

On behalf of organization ‘ABC’, you are preparing a second-party audit of the quality management system of an external provider ‘XYZ’.

‘XYZ’has already sent to you a list with all documented procedures and work instructions related to the services provided to ‘ABC’ (a quality manual is not included in the list).

To complete the audit planning which additional information would you ask to XYZ to submit? (Choose four).

  • A. XYZ’s organizational structure
  • B. The list of risks and opportunities determined by XYZ
  • C. Information to understand XYZ’s operations
  • D. The results of XYZ’s last internal audit
  • E. A description of responsibilities and authorities of the key roles of XYZ
  • F. The number of personnel involved in activities related to the quality management system
  • G. The results of the last two management reviews
  • H. The quality manual
Show answer and explanation ▾

Correct answer: A, B, C, E

To plan the audit you need enough information to understand the provider: how it is organized, what its operations involve, who holds the main responsibilities and authorities, and which risks and opportunities it has determined. With the procedures already received, these let you decide what to audit and whom to interview.

Why the other options are wrong:

  • D. Internal audit results are examined as evidence during the audit and are not needed to plan it.
  • F. The headcount in quality activities does not show which processes and functions the audit has to cover.
  • G. Management review results are examined as evidence during the audit and are not needed to plan it.
  • H. ISO 9001:2015 does not require a quality manual, so the provider is not obliged to have one to submit.

Question 7

You have been nominated audit team leader of a third-party audit.

Which of the following could be the two most relevant objectives of this audit?

  • A. Evaluate the capability of the management system to establish and achieve objectives
  • B. Evaluate the benefits obtained since the implementation of the management system
  • C. Evaluate the satisfaction of interested parties
  • D. Identify opportunities for improvement
  • E. Identify the need for resources
  • F. Evaluate the effectiveness of the management system
Show answer and explanation ▾

Correct answer: A, F

A third-party certification audit determines whether the management system conforms to the audit criteria and works. The most relevant objectives are evaluating its effectiveness and its capability to establish and achieve the organization's objectives.

Why the other options are wrong:

  • B. Measuring the benefits gained from the system is a matter for the organization, not an objective of a certification audit.
  • C. Customer satisfaction is monitored by the organization itself; the auditor checks that this is done.
  • D. Opportunities for improvement are a by-product of the audit, not one of its two main objectives.
  • E. Determining resource needs is the organization's responsibility, not an audit objective.

Question 8

Select one of the options that best describes the purpose of conducting a document review: (Choose one.)

  • A. To detect any nonconformity of the system if documented, with audit criteria and to identify information to support the audit plan.
  • B. To determine the conformity of the system, as far as documented, with audit criteria and to gather information to support the audit activities.
  • C. To reveal whether the documented system is nonconforming with audit criteria and to gather evidence to support the audit report.
  • D. To establish nonconformity in the documented system with audit criteria and to gather information to compile the audit report.
  • E. To decide about the conformity of the documented system with audit standards and to gather findings to support the audit process.
Show answer and explanation ▾

Correct answer: B

A document review determines the conformity of the system, as far as it is documented, with the audit criteria, and gathers information to support the audit activities. It is neutral: it looks for conformity and prepares the auditor for what follows.

Why the other options are wrong:

  • A. A document review is not aimed at detecting nonconformity, and its output supports the audit activities, not only the plan.
  • C. The review does not set out to reveal nonconformity or to collect evidence for the report.
  • D. The review does not set out to establish nonconformity or to compile the audit report.
  • E. The review does not decide conformity and does not gather findings.

Question 9

Even though past audits have highlighted a consistently large number of nonconformities within an organization’s design team, the organization has not varied the frequency or duration of audits on its audit plan.

The decision for whether this situation is acceptable or not should be governed by which of the following?

  • A. The authority of the audit team leader
  • B. The organization’s reasoning behind the lack of change to the audit plan
  • C. The availability of competent internal auditors
  • D. A risk-based approach to the audit programme
Show answer and explanation ▾

Correct answer: D

Audit frequency and duration should reflect the importance of the processes and the results of previous audits. Whether an unchanged schedule is acceptable for an area with repeated nonconformities is judged by applying a risk-based approach to the audit programme.

Why the other options are wrong:

  • A. The audit team leader manages an individual audit and does not determine whether the programme is adequate.
  • B. The organization's reasoning is information to consider, but it is not the principle that governs the decision.
  • C. Auditor availability is a resource matter and does not determine whether the programme addresses the risk.

Question 10

Which one of the following documents addresses audit time calculation for third-party certification audits? (Choose one.)

  • A. ISO 17021-1
  • B. ISO 19011
  • C. ISO 9001
  • D. ISO 9000
Show answer and explanation ▾

Correct answer: A

ISO/IEC 17021-1 sets the requirements for bodies that audit and certify management systems, and it requires the certification body to have documented procedures for determining audit time for each client.

Why the other options are wrong:

  • B. ISO 19011 gives guidance on auditing management systems and does not set audit time for certification audits.
  • C. ISO 9001 states the quality management system requirements and does not address audit time.
  • D. ISO 9000 covers quality management fundamentals and vocabulary.

Question 11

Noitol is an organization specializing in the design and production of e-learning training materials for the insurance market. During an ISO 9001 audit of the development department, the auditor asks the Head of Development about the process used for validation of the final course design.

She states that they usually ask customers to validate the product with volunteers. She says that the feedback received often leads to key improvements.

The auditor samples the design records for a recently completed course for the 247 Insurance organization. Design verification was carried out but there was no validation report. The Head of Development advises that this customer required the product on an urgent basis, so the validation stage was omitted.

When asked, the Head estimates that this occurs about 50% of the time. She confirms that they always ask for feedback and often make changes. There is no record of feedback in the design file for the course.

The auditor raises a nonconformity against ISO 9001.

Which one of the following options is the basis for the non-conformity? (Choose one.)

  • A. 8.3.5-The improvements made the course designs are not documented. Feedback from customers is not always actioned.
  • B. 8.6-Course materials are released without proper approval. A course for 247 Insurance was released on an urgent basis.
  • C. 8.3.4.d-Design validation is not always conducted. It is omitted about half of the time.
  • D. 8.3.2.c-Design planning does not include design validation. Design verification is part of the planning process.
Show answer and explanation ▾

Correct answer: C

Clause 8.3.4 d requires validation activities to be conducted to ensure the resulting products and services meet the requirements for their intended use. The organization skips validation about half of the time, so this control is not applied consistently.

Why the other options are wrong:

  • A. Clause 8.3.5 concerns design and development outputs, not whether validation was carried out.
  • B. Clause 8.6 concerns release of products and services, while the evidence is about a missing design control.
  • D. Validation is part of the organization's design process; the failure is that it is not carried out, not that it is unplanned.

Question 12

An audit team leader arrives at a printing organization to carry out a Stage 2 audit for a certification body. At a meeting with the Quality Manager, she is told that they have won their biggest contract from a computer manufacturer to print and compile computer documentation packages. They have leased the unit next door for space reasons but have never worked in this sector before. The Quality Manager wants the ISO 9001 certificate to cover the new contract.

During the audit, a team member finds that a number of print jobs have been rejected by several clients over a number of months due to spelling errors in the print run. The Print Manager blames the new employees they have had to take on because of a big contract. The auditor raises a nonconformance against clause 10.2.1.b of ISO 9001.

Which one of the evidence statements would support this finding? (Choose one.)

  • A. There was no record that the organization evaluated the effectiveness of the training given to new employees.
  • B. The action taken to deal with customer complaints did not prevent recurrence of the problem.
  • C. There was no evidence that a check of spelling took place before the release of printing to the client.
  • D. The organization did not provide the correct resources to prevent nonconformity.
Show answer and explanation ▾

Correct answer: B

Clause 10.2.1 b requires the organization to evaluate the need for action to eliminate the causes of a nonconformity so that it does not recur. Print jobs rejected for the same spelling errors over several months show the action taken did not prevent recurrence.

Why the other options are wrong:

  • A. Evaluating the effectiveness of training is a competence requirement in clause 7.2.
  • C. A missing check before release relates to clause 8.6 on release of products and services.
  • D. Provision of resources is a clause 7.1 requirement.

Question 13

During a third-party surveillance audit, the auditor finds that the management review meeting minutes record that the improvement actions set by the previous reviewer have not been completed for a second year running. It states that a new Quality Manager has been brought in at the middle management level to rectify the situation. You learn that top management is not involved in the QMS other than being copied into the minutes of the management review meeting.

The audit reveals that the new Quality Manager was given responsibility by top management to a) take accountability for the effectiveness of the QMS, b) select, approve, and monitor improvement actions without involving and reporting to top management, c) promote the improvement of the QMS and d) make efficient use of the limited financial and personnel resources allocated for the QMS by top management.

The auditor considers whether there is a nonconformity against clause 5.1.1 of ISO 9001.

Select two options of the evidence required for such a nonconformity. (Choose two.)

  • A. Top management is not accountable for the effectiveness of the QMS.
  • B. The Quality Manager avoids giving improvement actions to the Chief Executive.
  • C. The Chief Executive never attends the management review meetings in person.
  • D. The Quality Manager is on target to complete only half of the improvement actions.
  • E. The Quality Manager only reports to one designated senior manager.
  • F. The Quality Manager does not have access to the resources needed for the QMS.
Show answer and explanation ▾

Correct answer: A, C

Clause 5.1.1 requires top management to take accountability for the effectiveness of the quality management system and to show its commitment personally. Passing accountability to a middle manager, and the Chief Executive never attending management review in person, are evidence that this is not happening.

Why the other options are wrong:

  • B. This describes the Quality Manager's conduct, not a failure by top management to lead.
  • D. Progress on improvement actions does not show whether top management demonstrates leadership.
  • E. The Quality Manager's reporting line is not a clause 5.1.1 requirement.
  • F. Access to resources is not supported by the scenario, which states that resources were allocated.

Question 14

You are carrying out an audit at an organization seeking certification to ISO 9001 for the first time. The organization offers regulatory consultancy services to manufacturers of cosmetics. The business operates from ten regional offices.

You are nearing the end of the audit and need to decide if sufficient evidence of top management leadership and commitment with respect to the quality management system has been gathered.

Which four of the following would demonstrate top management leadership and commitment with respect to the quality management system?

(Choose four.)

  • A. Promoting the importance of following procedures
  • B. Chairing management review meetings
  • C. Investing time and money in corrective actions arising from nonconformities
  • D. Briefing staff on the development of an improvement culture
  • E. Not attending audit closing meeting
  • F. Approving company car budgets for the fiscal year
  • G. Conducting staff disciplinary meetings
Show answer and explanation ▾

Correct answer: A, B, C, D

Top management shows leadership and commitment by promoting conformity with the system, taking part in management review, supporting corrective action with time and money, and promoting improvement among staff. Each of these four is visible, personal involvement in the quality management system.

Why the other options are wrong:

  • E. Staying away from the audit closing meeting shows a lack of involvement.
  • F. Approving company car budgets is a general business task unrelated to the quality management system.
  • G. Conducting disciplinary meetings is a personnel matter and does not demonstrate commitment to the quality management system.

Question 15

XYZ Corporation is an organization that employs 100 people. As the audit team leader, you are conducting a certification audit at Stage 1. When reviewing the quality management system (QMS) documentation, you find that quality objectives have been set for every employee in the organization except top management. The Quality Manager complaints that this has created a lot of resistance to the QMS, and the Chief Executive is asking questions about how much it will cost. He asks for your opinion on whether this is the correct method of setting objectives.

How would you respond with the following options? (Choose three.)

  • A. Inform the Quality Manager that you will comment on the subject in your audit report.
  • B. Suggest asking the certification body for guidance on this matter.
  • C. Suggest the all employees undertake a training course on ISO 9001.
  • D. Indicate that ISO 9001 requires a minimum of two quality objectives.
  • E. Suggest that the Quality Manager obtains external consultancy on the use of quality objectives.
  • F. Advise the Quality Manager that you will raise an opportunity for improvement if the quality objectives are not addressed properly.
  • G. Advise the Quality Manager to read the ISO 9001 standard and interpret in relation to the organization’s requirements.
  • H. Advise the Quality Manager that, as an auditor, you cannot provide advice to the organization on how it should operate its QMS.
Show answer and explanation ▾

Correct answer: A, F, H

A certification auditor must stay impartial and cannot advise an organization on how to run its quality management system. The proper response is to say so, address the subject through the audit report, and raise an opportunity for improvement where the quality objectives are not handled properly.

Why the other options are wrong:

  • B. The certification body does not give guidance on how an organization should set its objectives.
  • C. Recommending a training course is advice on a specific solution.
  • D. ISO 9001 does not set a minimum number of quality objectives.
  • E. Recommending external consultancy is advice on a specific solution.
  • G. Directing the Quality Manager on how to interpret the standard for the organization is advice on operating the system.

Question 16

Takeup is a small fabrication organization that manufactures steel fencing, stairs and platforms for the construction sector. It has been certified to ISO 9001 for some time and has appointed a new Quality Manager. The audit plan during a surveillance audit covers the organization’s improvement actions and the auditor asks to see the most recent management review meeting minutes.

The auditor finds that the management review report records that none of the improvement actions set by the previous review has been realized for a second time. A new Quality Manager has been brought in at the middle management level to rectify the situation as the organization is concerned that it might lose its certification.

Select three options that would provide evidence of conformance with clause 10.3 of ISO 9001. (Choose three.)

  • A. Removing expensive external providers from the database.
  • B. The certification body auditor reporting fewer nonconformities.
  • C. An enhanced customer satisfaction survey score than in the previous year.
  • D. Outsource more processes to external providers
  • E. A quality objective to achieve lower reject rates by quality control.
  • F. Considering results from the analysis of the effectiveness of corrective actions to determine improvement opportunities.
  • G. Automate the fabrication process to increase profitability.
  • H. An increase in the number of quality staff.
Show answer and explanation ▾

Correct answer: C, E, F

Clause 10.3 requires the organization to continually improve the suitability, adequacy and effectiveness of the quality management system, using the results of analysis and evaluation. A higher customer satisfaction score, an objective to cut reject rates, and using corrective action results to find opportunities all show this.

Why the other options are wrong:

  • A. Removing expensive providers is a cost decision and does not show the system has improved.
  • B. The number of nonconformities an external auditor reports depends on sampling and is not the organization's own evidence of improvement.
  • D. Outsourcing more processes is a business choice, not evidence of improvement.
  • G. Automation aimed at profitability does not show improvement of the quality management system.
  • H. More quality staff is a resource input, not a result that shows improvement.

Question 17

Noitol is an organization specializing in the design and production of e-learning training materials for the insurance market. During an ISO 9001 audit of the development department, the auditor asks the Head of Development about the process used for validation of the final course design.

She states that they usually ask customers to validate the product with volunteers. She says that the feedback received often leads to key improvements.

The auditor samples the design records for a recently completed course for the 247 Insurance organization. Design verification was carried out but there was no validation report. The Head of Development advises that this customer required the product on an urgent basis, so the validation stage was omitted.

When asked, the Head estimates that this occurs about 50% of the time. She confirms that they always ask for feedback and often make changes. There is no record of feedback in the design file for the course.

The auditor decides to review the training course design process in more depth.

Select three options that provide a meaningful audit trail for this process. (Choose three).

  • A. What risks and opportunities have been notified to interested parties?
  • B. How is customer feedback integrated into the course?
  • C. How is design documentation controlled and managed?
  • D. How is technical content of courses verified as correct?
  • E. What are the qualifications of the administrative staff?
  • F. How is the cost of the course calculated?
  • G. How are students advised about prior learning requirements?
  • H. How is the tutor trained to deliver the completed course?
Show answer and explanation ▾

Correct answer: B, C, D

A meaningful audit trail follows the design process itself: how customer feedback is fed into the course, how design documentation is controlled, and how technical content is verified. These link directly to the design inputs, controls and outputs the auditor is examining.

Why the other options are wrong:

  • A. Notifying interested parties of risks and opportunities is not part of the course design process.
  • E. Qualifications of administrative staff do not bear on the design process.
  • F. Course costing is a commercial matter outside the design controls being audited.
  • G. Advising students on prior learning relates to course delivery, not design.
  • H. Tutor training relates to delivering the finished course, not designing it.

Question 18

Whistlekleen is a national dry cleaning and laundry organization with 50 shops. You are conducting a surveillance audit of the Head Office and are sampling customer complaints. 80% of complaints originate from five shops in the same region. Most of these complaints relate to customer laundry not being cleaned as customers require.

The Quality Manager tells you that these are the oldest shops in the company. The cleaning equipment needs replacing but the company cannot afford it now. You learn that the shop managers were told to dismiss most of the complaints based on the poor quality of the laundered materials.

On raising the matter with senior management, you are told that there are plans to replace the equipment in these shops over the next five years.

You raised a nonconformity against clause 8.5.1 of ISO 9001.

Based on the scenario, select the three options which best describe the evidence for raising such a nonconformity. (Choose three.)

  • A. The organization failed to maintain all of its equipment to an adequate standard.
  • B. Customer complaints are not taken seriously by the organization.
  • C. The operators did not check the condition of the customer’s product upon receipt.
  • D. Some equipment used was not suitable for the laundry process.
  • E. The management failed in planning to replace obsolete equipment.
  • F. The operators did not check laundry before release to the customer.
  • G. The organization failed to control the laundry operations in 5 shops adequately.
  • H. Shop managers were told to make excuses to customers with complaints.
Show answer and explanation ▾

Correct answer: A, D, G

Clause 8.5.1 requires production and service provision under controlled conditions, including the use of suitable infrastructure. Poorly maintained equipment, equipment that is no longer suitable for the laundry process, and inadequate control of operations in five shops are the evidence for this nonconformity.

Why the other options are wrong:

  • B. How complaints are treated relates to customer satisfaction and corrective action, not clause 8.5.1.
  • C. Checking customer property on receipt belongs to clause 8.5.3, and the scenario gives no evidence on it.
  • E. Planning equipment replacement is a resource decision and not evidence of how operations are controlled.
  • F. Checks before release belong to clause 8.6, and the scenario gives no evidence on them.
  • H. What shop managers tell customers relates to customer communication, not control of the laundry process.

Question 19

An internal auditor of a manufacturer of polystyrene packaging products for the electronics industry raised a nonconformity against section 10.3 of ISO 9001 in Report IA202. The nonconformity (NC 3) stated:

“The reject rate of the finished product of 9.7% needs improvement as it doesn’t meet the stated objective of top management of 5%.” As the third-party auditor reviewing the internal audit process, you come across the nonconformity. For corrective action, the Quality Manager conducted an investigation into the reject rates. He reported that the collection baskets for products ejecting from the moulding machines were not large enough. About 5% of products fell onto the wet and dirty factory floor. Management stated that replacing the baskets was too costly and ordered the Maintenance Manager to ensure that the floor was kept clean and dry to prevent rejects. The auditor later checked the factory floor, which was wet and dirty in places.

From the following nonconformities, select three that the auditor could raise to ISO 9001. (Choose three.)

  • A. 7.3-Staff were not aware that products were failing onto the factory floor.
  • B. 10.3-The organization did not continuously improve. Reject rates were unchanged.
  • C. 7.1.4-The factory environment is not suitably maintained to prevent dirty products.
  • D. 9.2.2-Report IA202 contained a poorly worded nonconformity (NC 3).
  • E. 8.5.1-Production operations were not properly controlled to avoid reject products.
  • F. 8.6-Dirty products were released to the customer.
  • G. 7.1.1-The organization failed to provide the required resources to prevent nonconforming products.
  • H. 10.2.1-Conduct of an investigation was not sufficient to understand the cause of the nonconformity.
Show answer and explanation ▾

Correct answer: B, C, E

The evidence supports three findings. The reject rate did not improve, which relates to 10.3. The floor was still wet and dirty, so the process environment under 7.1.4 was not maintained. Products kept falling to the floor, so production was not carried out under controlled conditions as 8.5.1 requires.

Why the other options are wrong:

  • A. There is no evidence about what staff were or were not aware of.
  • D. The wording of one internal audit finding is not evidence that the internal audit requirement was not met.
  • F. There is no evidence that dirty products reached the customer; they were rejected.
  • G. The evidence points to how the environment and production were controlled, not to a general failure to determine and provide resources.
  • H. An investigation was carried out and it identified the cause of the rejects.

Question 20

An audit team of three people is conducting a Stage 2 audit to ISO 9001 of an engineering organization which manufactures sacrificial anodes for the oil and gas industry in marine environments. These are aluminum products designed to prevent corrosion of submerged steel structures. As one of the auditors, you find that the organization has shipped anodes for Project DK in the Gulf of Mexico before the galvanic efficiency test results for the anodes have been fully analyzed and reported as required by the customer. The Quality Manager explains that the Managing Director authorized the release of the anodes to avoid late delivery as penalties would be imposed. The customer was not informed since the tests rarely fall below the required efficiency. You raise a nonconformity against clause 8.6 of ISO 9001.

During the audit team meeting in preparation for the Closing meeting, the second auditor disagreed with the clause of ISO 9001 selected for the above nonconformity. He thinks it should be clause 9.1.1.

Choose three options for how the audit team leader should best respond to the situation: (Choose three.)

  • A. Advise that he will think about the clause and announce his decision during the Closing meeting.
  • B. Try to obtain a consensus between you and the second auditor after a discussion of the different options.
  • C. Immediately overrule the objection of the second auditor with no discussion of the clause.
  • D. The audit team leader will refer to the quality manager to determine which clause they agree with.
  • E. Immediately agree with the second auditor that clause 9.1.1 would be better.
  • F. Review the evidence with you and the second auditor, and then decide which clause of ISO 9001 would best apply.
  • G. Invite you and the second auditor to fully explain your point of view and then decide which clause to select.
  • H. Suggest that neither clause is accurate and instead propose clause 9.1.3 as the best one for the nonconformity.
Show answer and explanation ▾

Correct answer: B, F, G

The audit team leader is responsible for the audit conclusions and should resolve differences within the team before the closing meeting. The right approach is to hear both auditors, review the evidence against the clauses, seek consensus, and then decide which clause applies.

Why the other options are wrong:

  • A. The clause must be settled before the closing meeting, not announced during it.
  • C. Overruling without discussion ignores the evidence and the second auditor's reasoning.
  • D. The auditee does not decide which clause the audit team cites.
  • E. Agreeing at once without reviewing the evidence is no better than overruling at once.
  • H. Proposing a third clause without evidence does not resolve the disagreement.

Question 21

A Health Trust has contracted with Servitup,a catering services company that has been certified to ISO 9001 for one year. It provides services to 10 small rural hospitals in remote locations involving the purchase and storage of dry goods and fresh produce, preparing meals and loading heated trolleys for ward service by hospital staff. You, as auditor, are conducting the first surveillance audit at one site with the Deputy Catering Manager (DCM).

DCM: “I apologize for the absence of the Catering Manager. He has called in sick today and we are really short of staff.” You: “I see. It really shouldn’t affect the QMS the audit can progress as normal.” DCM: “The Catering Manager set up the system. I’m afraid I’m not as familiar with it as he is.” You: “OK, let’s start with the Quality Policy.

What are the main issues for the QMS here?” DCM: Give me a minute. I need to look at the Quality Policy on the noticeboard in his office.

You find that two internal audits have been carried out in the first year by the Catering Manager. One of them indicates that complaints from patients are increasing in number, mainly due to food being served too cold. The DCM comments that the trolley thermometer is often unreliable.

Which two of the following actions would be “corrective action” in dealing with the complaints? (Choose two.)

  • A. Keep records of patient complaints of cold food.
  • B. Purchase a new thermometer to replace the unreliable one used for the ward trolleys.
  • C. Monitor and record the temperature of food on the trolleys against defined standards before release to the wards.
  • D. Calibrate thermometers more frequently to ensure the accuracy of readings for food temperature on the trolleys.
  • E. Request patients taste the food to check if it is too cold.
  • F. Plug trolleys into ward electricity sockets to heat food to the correct temperature after a patient complains.
Show answer and explanation ▾

Correct answer: B, D

Corrective action eliminates the cause of a nonconformity so it does not recur. Food is reaching patients cold because the trolley thermometer is unreliable, so replacing it and calibrating thermometers more often both act on that cause.

Why the other options are wrong:

  • A. Recording complaints documents the problem and does nothing to remove its cause.
  • C. Monitoring food temperature before release detects cold food but does not remove the cause.
  • E. Asking patients to taste the food detects the problem after it has occurred.
  • F. Reheating food after a complaint is a correction of one occurrence, not corrective action.

Question 22

At the end of a second-party audit, the audit team enters the meeting room to hold the closing meeting; only two people are present and waiting for them: the Health and Safety supervisor and the Administrative Officer. Neither has participated in the audit. However, the team had previously agreed with the auditee Quality Manager on two nonconformities identified during the audit (NC1 and NC2).

They said:

Health and Safety Supervisor: “Good evening. We are sorry to inform you that the general manager was involved in a serios car accident, and the other two managers have had to leave urgently to attend to the emergency.” The Administration Officer: “Concerning ‘nonconformity 2’, the General Manager left a message asking us to tell you that he does not accept it and requests you not to include it in the audit report. Here is a note in which he explains why.”

Which one of the following would be your preferred answer (as learn leader) to the General Manager’s request?

  • A. Please, tell him that this nonconformity has been previously accepted by the quality manager during the audit and will stand. I will include it in the report, along with the concern of the General Manager about it.
  • B. Please tell him that I will phone him in two days and will discuss the issue. Could you please give me his mobile phone number?
  • C. OK, I will get in contact with my company tomorrow to ask for instructions on what to do with this non-conformity.
  • D. OK. Please, let me review the message. I will try to see if I can change the text of the nonconformity if necessary. Let’s take a 10-minute break, as I would like to discuss this issue with the audit team.
Show answer and explanation ▾

Correct answer: D

Diverging opinions about audit findings should be discussed and, where possible, resolved at the closing meeting. The team leader should read the General Manager's explanation, confer with the audit team, and then decide whether the wording of the nonconformity needs to change.

Why the other options are wrong:

  • A. Declaring that the nonconformity stands without reading the General Manager's explanation does not consider his objection.
  • B. Deferring the matter for two days leaves the audit conclusions open at the closing meeting.
  • C. The audit team leader is responsible for the audit conclusions and does not need instructions from the company to handle an objection.

Question 23

At the end of a second-party audit, the audit team enters the meeting room to hold the closing meeting; only two people are present and waiting for them: the Health and Safety supervisor and the administrative officer. Neither has participated in the audit. However, the team had previously agreed with the auditee Quality Manager on two nonconformities identified during the audit (NC1 and NC2).

They said:

Health and Safety supervisor. “Good evening. We are sorry to inform you that the general manager was involved in a serious car accident, and the other two managers have had to leave urgently to attend to the emergency.” Administration officer: “Our quality manager, before leaving, left a written message about ‘NC2’. He declares that the correction and corrective action have been already implemented and has attached some documents to the message as evidence of these actions. Therefore, he expects that ‘NC2’ will not be included in the report.”

Which one of the following would be your preferred answer to the Quality Manager’s request?

  • A. The scope of the audit does not allow auditors to review actions taken in response to the nonconformity. There would not be enough time for the full cycle of corrective action to take effect
  • B. OK. Let’s all go to the workshop to see the supervisor. I hope he will be able to explain what they did to correct the nonconformity and prevent its recurrence
  • C. OK. I will record in the audit report that ‘nonconformity 2’ was closed during the Closing meeting
  • D. Let me review the message and documents, and I will give you my answer in a few minutes
Show answer and explanation ▾

Correct answer: D

The team leader should look at the message and the attached documents before responding, and can do so in a few minutes. Any decision on how the nonconformity is reported has to rest on evidence the audit team has reviewed.

Why the other options are wrong:

  • A. Refusing without looking at the documents supplied gives the request no consideration.
  • B. Going back to the workshop reopens auditing during the closing meeting, with people who took no part in the audit.
  • C. A nonconformity cannot be recorded as closed before the audit team has reviewed the evidence of the actions taken.

Question 24

TIX provides services to the informatic equipment of large organizations. They operate an ISO 9001:2015 QMS that is being audited by an important customer (second-party audit). During the audit, the audit team has identified two nonconformities.

When preparing the Closing meeting, the audit team discussed and agreed both nonconformities with TIX’s quality manager. The Closing meeting was planned for 6 pm with the general manager, quality manager and service manager at the meeting room.

At 6 pm, when the audit team enters the meeting room, only two people are present and waiting form them: the Health and Safety supervisor and the warehouse supervisor. Neither have participated in the audit.

The dialog among them is as follows:

Audit team leader: “Good evening, could you please inform the three managers that we are ready to start with the Closing meeting?” Health and Safety supervisor: “Good evening. We are sorry to inform you that the general manager was involved in a serious car accident, and the other two managers have had to leave urgently to attend the emergency.” Warehouse supervisor: “They have asked us to listen to what you need to say and to sign whatever we need to sign. We also have a message from them about the two nonconformities. They wanted us to ask you if you could contact them in a couple of days to determine how to proceed.”

Which one of the following options would be your preferred response to the final comment made by the warehouse managers?

  • A. We will hear what you were asked to tell us and then leave. Please ask the managers to contact us as soon as the emergency is over to agree on a new date to carry out the Closing meeting.
  • B. We will hear what you were asked to tell us and will ask you to sign the nonconformity reports as evidence that you have accepted them. Please ask the managers to contact us as soon as the emergency is over to agree on a new date to complete the Closing meeting.
  • C. We will hear what you were asked to tell us and will leave copies of the nonconformity reports that have been agreed with the quality manager. Please tell the managers that we will consider this as the Closing meeting and that the individual(s) managing the audit programme will send the full report in five days.
  • D. Sorry, but we cannot proceed with the Closing meeting. So, we are leaving now, and please tell the quality manager that I will phone him tomorrow early in the morning.
Show answer and explanation ▾

Correct answer: C

Both nonconformities were already agreed with the quality manager, so the audit can be closed with the representatives the managers sent. The team hears their message, leaves copies of the agreed nonconformity reports, treats the session as the closing meeting, and the audit report follows as planned.

Why the other options are wrong:

  • A. Rescheduling is unnecessary because the findings were already agreed with the quality manager.
  • B. Supervisors who took no part in the audit cannot accept nonconformities by signing them.
  • D. Leaving without holding the closing meeting ignores the representatives who were sent to receive the results.

Question 25

The ISO 9001 clause 5.1.1 states top management shall demonstrate leadership and commitment with respect to the quality management system.

In the context of the ISO 9001 management system certification, select the one correct description of top management’s responsibilities.

  • A. Depending on the size, complexity and business context, some of the 5.1.1 requirements can be excluded.
  • B. Top management needs only to comply with 50% of the 5.1.1 requirements.
  • C. Top management shall ensure that all requirements are fulfilled.
  • D. Depending on the organization’s available resources, top management can comply with one or more of the 5.1.1 requirements.
Show answer and explanation ▾

Correct answer: C

Clause 5.1.1 lists the ways top management shall demonstrate leadership and commitment, and every item is a requirement. For certification, top management has to ensure that all of them are fulfilled.

Why the other options are wrong:

  • A. Size, complexity and context affect how the requirements are met, not whether they apply.
  • B. ISO 9001 has no partial compliance threshold for clause 5.1.1.
  • D. Limited resources do not allow top management to choose which clause 5.1.1 requirements to meet.

Question 26

An ISO 9001 certified organization sells packaged food. To maximize the benefits of third-party certification to the organization and stakeholders, the organization has labelled their product ‘ISO 9001 certified product’ and is selling it as ‘quality food’.

Which two of the following describes this situation in the context of the purpose and benefits of third-party ISO 9001 certification? (Choose two.)

  • A. ISO 9001 certification can be used to identify opportunities for improvement of the management system
  • B. ISO 9001 certified food can increase customer confidence and satisfaction
  • C. ISO 9001 certified food can increase revenue
  • D. ISO 9001 is not for product certification
  • E. The organization will be able to increase its market share
  • F. The product from an ISO 9001 certified organization will taste better
Show answer and explanation ▾

Correct answer: A, D

ISO 9001 certification applies to the organization's quality management system and is not a product certification, so labeling food as an ISO 9001 certified product misrepresents it. The real benefit of third-party certification lies in the system, including identifying opportunities to improve it.

Why the other options are wrong:

  • B. There is no such thing as ISO 9001 certified food, so this claim cannot build legitimate customer confidence.
  • C. There is no such thing as ISO 9001 certified food, so revenue from this claim is not a benefit of certification.
  • E. Market share gained from a misleading product label is not a benefit of certification.
  • F. ISO 9001 certification says nothing about how a product tastes.

Question 27

Read the following role descriptions.

Select two roles that are not directly involved in the audit process. (Choose two.)

  • A. An auditor-in-training-a person who accompanies the audit team leader or team members during the audit.
  • B. A technical expert-a person who provides specific knowledge or expertise to the audit team but is not normally an auditor.
  • C. An audit team leader-a person responsible for managing an audit until the audit is completed.
  • D. An interpreter-a person who witnesses the audit to assist the auditors with language issues.
  • E. An observer-a person who sees the performance of the audit team leader, audit team members and/or auditee.
  • F. A guide-a person who is appointed by the auditee to assist the audit team during the audit.
Show answer and explanation ▾

Correct answer: D, E

An interpreter only helps with language and an observer only watches the audit. Neither collects audit evidence or acts for the auditee, so neither is directly involved in the audit process.

Why the other options are wrong:

  • A. An auditor-in-training takes part in the audit under the direction of an auditor.
  • B. A technical expert supplies specific knowledge that the audit team uses during the audit.
  • C. The audit team leader manages and takes part in the audit.
  • F. A guide is appointed by the auditee and actively assists the audit team during the audit.

Question 28

Knowledge is one of the requirements of the auditor’s competence.

Select two from the following topics of generic knowledge that apply to every member of an audit team auditing an ISO 9001 quality management system.

  • A. Detailed requirements of all the auditee’s interested parties
  • B. How to review the requirements for products and services
  • C. How to select and determine audit methods
  • D. Organization’s expansion plans for the next 2 years
  • E. Organization’s processes, procedures and work instructions
  • F. Organization’s recruitment policies
Show answer and explanation ▾

Correct answer: B, C

Generic knowledge is what any auditor on the team needs regardless of the auditee. Knowing how to select and determine audit methods, and how to review the requirements for products and services, applies to every ISO 9001 audit.

Why the other options are wrong:

  • A. Detailed requirements of the auditee's interested parties are specific to one auditee, not generic knowledge.
  • D. An organization's expansion plans are specific to one auditee, not generic knowledge.
  • E. An organization's processes, procedures and work instructions are specific to one auditee, not generic knowledge.
  • F. An organization's recruitment policies are specific to one auditee, not generic knowledge.

Question 29

In the context of a third-party certification audit, it is very important to have effective communication.

Which is not the responsibility of the audit team leader?

  • A. During the opening meeting, confirm formal communication channels between the audit team and the auditee.
  • B. Ensuring that the auditees attend the audit as agreed in the plan.
  • C. Ensuring that the functions included in the audit plan are audited even if there is not much activity in them.
  • D. Planning formal communication arrangements, so an auditee can communicate with the auditor at any time during the audit.
Show answer and explanation ▾

Correct answer: B

Making sure its own people attend as agreed in the audit plan is the auditee's responsibility. The audit team leader manages communication and the conduct of the audit but has no authority over the auditee's staff.

Why the other options are wrong:

  • A. Confirming formal communication channels at the opening meeting is a team leader responsibility.
  • C. Making sure every function in the audit plan is audited is a team leader responsibility.
  • D. Planning the formal communication arrangements for the audit is a team leader responsibility.

Question 30

In a third-party audit to ISO 9901, select two options of when the organization is required to act in response to reported findings. (Choose two.)

  • A. A finding of conformity is reported.
  • B. A finding of good practice is reported.
  • C. A major non-conformity is raised.
  • D. A minor non-conformity is raised.
  • E. A recommendation is given in the report.
  • F. An opportunity for improvement is raised.
Show answer and explanation ▾

Correct answer: C, D

Any nonconformity, major or minor, means a requirement has not been fulfilled. The organization is required to respond with correction and corrective action for both grades.

Why the other options are wrong:

  • A. A finding of conformity requires no action.
  • B. A finding of good practice requires no action.
  • E. A recommendation in the report is not binding on the organization.
  • F. An opportunity for improvement is for the organization to consider and does not require action.

Question 31

Confidence in the audit process and its ability to achieve its objectives depends on the competence of those involved in performing audits:

According to ISO 19011, select the two participants who need to be competent in performing audits. (Choose two.)

  • A. Auditor(s)
  • B. Auditee
  • C. Guides
  • D. Observers
  • E. Translators
  • F. Audit team leaders
Show answer and explanation ▾

Correct answer: A, F

ISO 19011 ties confidence in the audit process to the competence of the people who perform audits, which means auditors and audit team leaders. Both need the knowledge and skills to carry out audit activities.

Why the other options are wrong:

  • B. The auditee is the organization being audited and does not perform the audit.
  • C. Guides assist the audit team and do not perform the audit.
  • D. Observers accompany the audit team and do not perform the audit.
  • E. Translators help with language and do not perform the audit.

That was 31 of 107.

The full PECB ISO 9001 Lead Auditor pack has all 107 questions, each with the answer, the explanation and why the other options are wrong, plus a questions-only copy for timed runs. $39.00 USD, paid once, with free monthly updates and a pass-or-your-money-back guarantee.

Get the full pack

Not ready yet? Get the first 43 free as one PDF by email. Get the Half Pack →

About the ISO 9001 Lead Auditor exam

These 31 PECB ISO 9001 Lead Auditor questions are free here. The free PDF has 43, free by email.

They are drawn from the same bank as the full ISO 9001 Lead Auditor pack, which has 107 questions in total.

Back to blog