GAQM APM-001 Practice Questions with Explanations

Free GAQM APM-001 practice questions. 261 of them, each with the correct answer, a full explanation, and the reason every other option is wrong.

APM-001 practice questions

Question 1

Which document defines how a project is executed, monitored and controlled, and closed?

  • A. Strategic plan
  • B. Project charter
  • C. Project management plan
  • D. Service level agreement
Show answer and explanation ▾

Correct answer: C

The project management plan describes how the project is executed, monitored and controlled, and closed.

Why the other options are wrong:

  • A. A strategic plan covers organization-level direction, not how one project runs.
  • B. A project charter authorizes the project but does not define how it is run.
  • D. A service level agreement sets service commitments, not project execution.

Question 2

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

  • A. Risk and uncertainty increase; the cost of changes increases.
  • B. Risk and uncertainty increase; the cost of changes decreases,
  • C. Risk and uncertainty decrease; the cost of changes increases.
  • D. Risk and uncertainty decrease; the cost of changes decreases.
Show answer and explanation ▾

Correct answer: C

Risk and uncertainty are highest at the start and fall as work is done, while the cost of changes rises as the project progresses.

Why the other options are wrong:

  • A. Risk and uncertainty do not rise over the life cycle.
  • B. Risk does not rise, and change costs do not fall, as work advances.
  • D. Change becomes more expensive later, not cheaper.

Question 3

Which tool or technique is used in the Plan Scope Management process?

  • A. Document analysis
  • B. Observations
  • C. Product analysis
  • D. Expert judgment
Show answer and explanation ▾

Correct answer: D

Expert judgment is a tool used when planning scope management. The other options are tools of other processes such as collecting requirements.

Why the other options are wrong:

  • A. Document analysis is used in requirements work, not scope planning.
  • B. Observations are a requirements-gathering technique.
  • C. Product analysis belongs to defining scope.

Question 4

Which tool or technique is an examination of industry and specific vendor capabilities?

  • A. Independent estimates
  • B. Market research
  • C. Analytical techniques
  • D. Bidder conferences
Show answer and explanation ▾

Correct answer: B

Market research examines industry and specific vendor capabilities to inform procurement decisions.

Why the other options are wrong:

  • A. Independent estimates check the price of a bid, not vendor capability.
  • C. Analytical techniques are general analysis methods, not a review of vendors.
  • D. Bidder conferences are meetings with vendors before bids.

Question 5

An input used in developing the communications management plan is:

  • A. Communication models.
  • B. Enterprise environmental factors.
  • C. Organizational communications,
  • D. Organizational cultures and styles.
Show answer and explanation ▾

Correct answer: B

Enterprise environmental factors, such as organizational culture and structure, are an input to planning communications management.

Why the other options are wrong:

  • A. Communication models are a tool or technique, not an input.
  • C. Organizational communications is not the input named for this process.
  • D. Organizational cultures and styles are part of the environmental factors, not a separate input.

Question 6

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

  • A. Expert judgment
  • B. Forecasting methods
  • C. Earned value management
  • D. Analytical techniques
Show answer and explanation ▾

Correct answer: D

Analytical techniques are used to forecast potential outcomes based on possible variations of project or environmental variables. Regression analysis, FMEA, fault tree analysis and trend analysis are all listed examples, alongside root cause analysis, reserve analysis and variance analysis.

Why the other options are wrong:

  • A. Expert judgment is knowledge supplied by people with specialized experience or training, not a set of analysis methods.
  • B. Forecasting methods predict future performance such as the estimate at completion and do not include FMEA or fault tree analysis.
  • C. Earned value management measures performance by combining scope, schedule and resource measurements.

Question 7

The

Perform Quality Assurance process occurs in which Process Group?

  • A. Executing
  • B. Monitoring and Controlling
  • C. Initiating
  • D. Planning
Show answer and explanation ▾

Correct answer: A

Perform Quality Assurance audits the quality requirements and the results of quality control measurements while the work is being carried out, so it belongs to the Executing Process Group.

Why the other options are wrong:

  • B. Monitoring and Controlling contains Control Quality, not Perform Quality Assurance.
  • C. Initiating contains only Develop Project Charter and Identify Stakeholders.
  • D. Planning contains Plan Quality Management, which sets the quality requirements and standards.

Question 8

Enterprise environmental factors are an input to which process?

  • A. Control Scope
  • B. Define Scope
  • C. Plan Scope Management
  • D. Collect Requirements
Show answer and explanation ▾

Correct answer: C

Plan Scope Management takes the project management plan, the project charter, enterprise environmental factors and organizational process assets as inputs. Factors such as organizational culture, infrastructure and marketplace conditions shape how scope will be defined and controlled.

Why the other options are wrong:

  • A. Control Scope uses organizational process assets, not enterprise environmental factors, as an input.
  • B. Define Scope uses the scope management plan, project charter, requirements documentation and organizational process assets.
  • D. Collect Requirements uses the scope, requirements and stakeholder management plans, the project charter and the stakeholder register.

Question 9

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

  • A. Identify Risks
  • B. Control Risks
  • C. Plan Risk Management
  • D. Plan Risk Responses
Show answer and explanation ▾

Correct answer: D

Plan Risk Responses develops options and actions to enhance opportunities and to reduce threats to project objectives. It addresses risks by priority and inserts resources and activities into the budget, schedule and project management plan as needed.

Why the other options are wrong:

  • A. Identify Risks determines which risks may affect the project and documents their characteristics.
  • B. Control Risks implements response plans, tracks identified risks and evaluates how well the risk process is working.
  • C. Plan Risk Management defines how risk management activities will be conducted for the project.

Question 10

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

  • A. Plan Schedule Management.
  • B. Develop Project Charter.
  • C. Develop Schedule.
  • D. Plan Scope Management.
Show answer and explanation ▾

Correct answer: A

Plan Schedule Management establishes the policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule. It gives guidance and direction on how the schedule will be managed throughout the project.

Why the other options are wrong:

  • B. Develop Project Charter produces the document that formally authorizes the project.
  • C. Develop Schedule analyzes activity sequences, durations, resources and constraints to create the schedule model.
  • D. Plan Scope Management documents how the project scope will be defined, validated and controlled.

Question 11

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

  • A. Issue log
  • B. Change log
  • C. Expert judgment
  • D. Change requests
Show answer and explanation ▾

Correct answer: B

The change log documents the changes that occur during a project. In Manage Stakeholder Engagement, these changes and their impact on time, cost and risk are communicated to the appropriate stakeholders.

Why the other options are wrong:

  • A. The issue log is an output of Manage Stakeholder Engagement that records issues and their resolution.
  • C. Expert judgment is a tool or technique, not an input.
  • D. Change requests are an output of Manage Stakeholder Engagement, not the input that records changes.

Question 12

An input to the Plan Stakeholder Management process is:

  • A. The project charter.
  • B. The stakeholder analysis.
  • C. A communication management plan.
  • D. A stakeholder register.
Show answer and explanation ▾

Correct answer: D

The stakeholder register provides the information needed to plan appropriate ways to engage project stakeholders. The other inputs to Plan Stakeholder Management are the project management plan, enterprise environmental factors and organizational process assets.

Why the other options are wrong:

  • A. The project charter is an input to Identify Stakeholders, not to Plan Stakeholder Management.
  • B. Stakeholder analysis is a technique used in Identify Stakeholders, not an input.
  • C. The communications management plan is not listed as a separate input to this process.

Question 13

An input to the Plan Cost Management process is:

  • A. Cost estimates.
  • B. Resource calendars,
  • C. The project charter,
  • D. The risk register.
Show answer and explanation ▾

Correct answer: C

The project charter provides the summary budget from which the detailed project costs are developed, and it defines the approval requirements that influence how costs are managed. That makes it an input to Plan Cost Management.

Why the other options are wrong:

  • A. Cost estimates are an output of Estimate Costs, which comes after cost management planning.
  • B. Resource calendars are an input to Determine Budget, not to Plan Cost Management.
  • D. The risk register is an input to Estimate Costs and Determine Budget, not to Plan Cost Management.

Question 14

A technique used to determine the cause and degree of difference between baseline and actual performance is:

  • A. Product analysis.
  • B. Variance analysis.
  • C. Document analysis,
  • D. Decomposition.
Show answer and explanation ▾

Correct answer: B

Variance analysis determines the cause and degree of difference between the baseline and actual performance. The result is used to decide whether corrective or preventive action is required.

Why the other options are wrong:

  • A. Product analysis translates high-level product descriptions into tangible deliverables.
  • C. Document analysis elicits requirements by reviewing existing documentation.
  • D. Decomposition divides scope and deliverables into smaller, more manageable parts.

Question 15

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

  • A. Develop Project Team.
  • B. Manage Project Team.
  • C. Acquire Project Team.
  • D. Plan Human Resource Management.
Show answer and explanation ▾

Correct answer: D

Plan Human Resource Management identifies and documents project roles, responsibilities, required skills and reporting relationships, and it creates the staffing management plan.

Why the other options are wrong:

  • A. Develop Project Team improves competencies, team interaction and the overall team environment.
  • B. Manage Project Team tracks team member performance, provides feedback and resolves issues.
  • C. Acquire Project Team confirms resource availability and obtains the team needed for the work.

Question 16

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

  • A. Mandatory
  • B. Discretionary
  • C. Internal
  • D. External
Show answer and explanation ▾

Correct answer: A

Mandatory dependencies are legally or contractually required or inherent in the nature of the work. They often involve physical limitations, such as needing a foundation in place before a structure can be erected, and are also called hard logic.

Why the other options are wrong:

  • B. Discretionary dependencies are based on best practices or a preferred sequence, not on a legal or physical requirement.
  • C. Internal dependencies describe relationships between project activities that are within the project team's control.
  • D. External dependencies link project activities to non-project activities outside the team's control.

Question 17

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

  • A. Monitor and Control Project Work
  • B. Perform Quality Assurance
  • C. Close Project or Phase
  • D. Control Scope
Show answer and explanation ▾

Correct answer: C

In Close Project or Phase, the project manager reviews all prior information from the previous phase closures to ensure that all project work is completed and that the project has met its objectives.

Why the other options are wrong:

  • A. Monitor and Control Project Work tracks and reports progress against the plan during the project.
  • B. Perform Quality Assurance audits quality requirements and quality control results.
  • D. Control Scope monitors scope status and manages changes to the scope baseline.

Question 18

An input to the Manage Project Team process is:

  • A. Work performance reports.
  • B. Change requests.
  • C. Activity resource requirements.
  • D. Enterprise environmental factors.
Show answer and explanation ▾

Correct answer: A

Work performance reports give the project manager documented information on current project status compared with forecasts. That information helps determine future human resource requirements, recognition and rewards, and updates to the staffing management plan.

Why the other options are wrong:

  • B. Change requests are an output of Manage Project Team, not an input.
  • C. Activity resource requirements are an input to Plan Human Resource Management.
  • D. Enterprise environmental factors are not an input to Manage Project Team, although updates to them are an output.

Question 19

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

  • A. Procurement statement of work
  • B. Purchase order
  • C. Source selection criteria
  • D. Bidder conference
Show answer and explanation ▾

Correct answer: A

The procurement statement of work describes the procurement item in enough detail for prospective sellers to decide whether they can provide it. It gives suppliers a clearly stated set of goals, requirements and outcomes on which to base a quantified response.

Why the other options are wrong:

  • B. A purchase order is a form of agreement issued once a seller has been chosen.
  • C. Source selection criteria are used to rate and score seller proposals.
  • D. A bidder conference is a meeting between the buyer and prospective sellers, not an input.

Question 20

A large portion of a projects budget is typically expended on the processes in which Process Group?

  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Closing
Show answer and explanation ▾

Correct answer: B

The Planning Process Group contains more processes than any other Process Group and spans every Knowledge Area. The scope, schedule, cost, quality, human resource, communications, risk, procurement and stakeholder plans are all developed there, so planning takes a substantial share of project management effort.

Why the other options are wrong:

  • A. Executing carries out the work defined in the project management plan.
  • C. Monitoring and Controlling tracks, reviews and regulates progress and performance against the plan.
  • D. Closing finalizes all activities to formally complete the project or phase and involves comparatively little work.

Question 21

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

  • A. Efficient
  • B. Effective
  • C. Push
  • D. Pull
Show answer and explanation ▾

Correct answer: B

Effective communication means the information is provided in the right format, at the right time, to the right audience and with the right impact.

Why the other options are wrong:

  • A. Efficient communication means providing only the information that is needed.
  • C. Push communication is a method of sending information to specific recipients, such as by email or memo.
  • D. Pull communication is a method in which recipients access the content at their own discretion.

Question 22

Scope, schedule, and cost parameters are integrated in the:

  • A. Performance measurement baseline.
  • B. Analysis of project forecasts,
  • C. Summary of changes approved in a period,
  • D. Analysis of past performance.
Show answer and explanation ▾

Correct answer: A

The performance measurement baseline is an approved plan that integrates scope, schedule and cost parameters. Project execution is compared against it to measure and manage performance.

Why the other options are wrong:

  • B. An analysis of project forecasts is content found in work performance reports, not a baseline.
  • C. A summary of changes approved in a period is reporting content and does not integrate the three parameters.
  • D. An analysis of past performance is reporting content, not the integrated baseline.

Question 23

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

  • A. Adaptive
  • B. Predictive
  • C. Incremental
  • D. Iterative
Show answer and explanation ▾

Correct answer: B

In a predictive, or fully plan-driven, life cycle the project scope and the time and cost required to deliver it are determined as early in the life cycle as practically possible.

Why the other options are wrong:

  • A. Adaptive life cycles respond to high levels of change with short iterations and ongoing stakeholder involvement.
  • C. Incremental life cycles add functionality to the product in successive increments.
  • D. Iterative life cycles develop the product through repeated cycles, with scope detailed one iteration at a time.

Question 24

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

  • A. 0.50
  • B. 0.67
  • C. 1.50
  • D. 2.00
Show answer and explanation ▾

Correct answer: A

SPI is earned value divided by planned value. Here that is $50 divided by $100, which equals 0.50, so only half of the planned work has been accomplished.

Why the other options are wrong:

  • B. 0.67 does not result from dividing EV of $50 by PV of $100.
  • C. 1.50 is AC divided by PV, which is not a schedule measure.
  • D. 2.00 is PV divided by EV, the inverse of the SPI formula.

Question 25

Which item is an input to the Define Activities process?

  • A. Schedule data
  • B. Activity list
  • C. Risk register
  • D. Scope baseline
Show answer and explanation ▾

Correct answer: D

The scope baseline supplies the WBS, deliverables, constraints and assumptions that are considered explicitly while defining activities. The other inputs are the schedule management plan, enterprise environmental factors and organizational process assets.

Why the other options are wrong:

  • A. Schedule data is an output of Develop Schedule.
  • B. The activity list is an output of Define Activities, not an input.
  • C. The risk register is not an input to Define Activities.

Question 26

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

  • A. Interactive communication
  • B. Claims administration
  • C. Conflict management
  • D. Performance reporting
Show answer and explanation ▾

Correct answer: B

Claims administration handles contested changes where the buyer and seller cannot agree on compensation or that a change occurred. Claims that the parties cannot resolve themselves are handled through alternative dispute resolution, following the procedures in the contract.

Why the other options are wrong:

  • A. Interactive communication is a method for multidirectional exchange of information, not a way to settle contract disputes.
  • C. Conflict management is used to resolve disagreements within the project team.
  • D. Performance reporting gives management information on how well the seller is meeting contractual objectives.

Question 27

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

  • A. Interrelationship digraphs
  • B. Tree diagram
  • C. Affinity diagram
  • D. Network diagram
Show answer and explanation ▾

Correct answer: B

Tree diagrams, also called systematic diagrams, represent decomposition hierarchies such as the WBS, RBS and OBS. They are useful for visualizing parent-to-child relationships in any hierarchy that follows a systematic set of nesting rules.

Why the other options are wrong:

  • A. Interrelationship digraphs map logical relationships among many intertwined items, not a nested hierarchy.
  • C. Affinity diagrams sort a large number of ideas into groups.
  • D. A network diagram shows the sequence and dependencies of schedule activities.

Question 28

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

  • A. Planning.
  • B. Executing,
  • C. Monitoring and Controlling.
  • D. Closing.
Show answer and explanation ▾

Correct answer: C

Monitoring and Controlling processes track, review and regulate progress and performance throughout the project. They run in the background of the other Process Groups from the start of the project to its end.

Why the other options are wrong:

  • A. Planning establishes the scope, objectives and course of action, and is repeated when changes require it instead of running continuously.
  • B. Executing covers carrying out the work defined in the project management plan.
  • D. Closing takes place when a phase or the project is being formally completed.

Question 29

Organizational theory is a tool used in which Project Human Resource Management process?

  • A. Manage Project Team
  • B. Acquire Project Team
  • C. Develop Project Team
  • D. Plan Human Resource Management
Show answer and explanation ▾

Correct answer: D

Organizational theory provides information on how people, teams and organizational units behave. It is a tool of Plan Human Resource Management, where it shortens the time and effort needed to produce the plan and improves planning efficiency.

Why the other options are wrong:

  • A. Manage Project Team uses observation and conversation, performance appraisals, conflict management and interpersonal skills.
  • B. Acquire Project Team uses pre-assignment, negotiation, acquisition, virtual teams and multi-criteria decision analysis.
  • C. Develop Project Team uses tools such as training, team-building activities, ground rules and colocation.

Question 30

Which tools or techniques are used in the Plan Schedule Management process?

  • A. Benchmarking, expert judgment, and analytical techniques
  • B. Statistical sampling, benchmarking, and meetings
  • C. Negotiations, pre-assignment, and multi-criteria decision analysis
  • D. Expert judgment, analytical techniques, and meetings
Show answer and explanation ▾

Correct answer: D

Plan Schedule Management uses three tools and techniques: expert judgment, analytical techniques and meetings.

Why the other options are wrong:

  • A. Benchmarking is a quality planning and requirements technique, not a schedule planning tool.
  • B. Statistical sampling and benchmarking belong to quality management.
  • C. Negotiation, pre-assignment and multi-criteria decision analysis are used in Acquire Project Team.

Question 31

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

  • A. Projectized
  • B. Weak matrix
  • C. Functional
  • D. Balanced matrix
Show answer and explanation ▾

Correct answer: A

In a projectized organization the project manager works full-time with high to almost total authority, and both the project team and the administrative staff are assigned to the project full-time.

Why the other options are wrong:

  • B. In a weak matrix the project manager acts part-time as a coordinator or expediter with part-time staff.
  • C. In a functional organization the project manager is part-time with little or no authority.
  • D. In a balanced matrix the project manager is full-time, but the administrative staff is part-time.

Question 32

A project charter is an output of which Process Group?

  • A. Executing
  • B. Planning
  • C. Initiating
  • D. Closing
Show answer and explanation ▾

Correct answer: C

Develop Project Charter is one of the two processes in the Initiating Process Group. Its output, the project charter, formally authorizes the project and gives the project manager authority to apply resources.

Why the other options are wrong:

  • A. Executing produces deliverables and work performance data, not the charter.
  • B. Planning produces the project management plan and its subsidiary plans.
  • D. Closing produces the final product, service or result transition.

Question 33

Which tool or technique is effective in a project in which the deliverable is not a service or result?

  • A. Inspection
  • B. Variance analysis
  • C. Decomposition
  • D. Product analysis
Show answer and explanation ▾

Correct answer: D

Product analysis is an effective tool for projects that have a product as a deliverable, as opposed to a service or result. It includes techniques such as product breakdown, systems analysis, requirements analysis and value engineering.

Why the other options are wrong:

  • A. Inspection examines completed work to verify that it meets requirements.
  • B. Variance analysis compares actual performance with the baseline.
  • C. Decomposition subdivides scope and deliverables regardless of the type of deliverable.

Question 34

An element of the project scope statement is:

  • A. Acceptance criteria.
  • B. A stakeholder list.
  • C. A summary budget.
  • D. High-level risks.
Show answer and explanation ▾

Correct answer: A

The project scope statement contains the product scope description, acceptance criteria, deliverables, project exclusions, constraints and assumptions. Acceptance criteria are the conditions that must be met before deliverables are accepted.

Why the other options are wrong:

  • B. A stakeholder list is an element of the project charter.
  • C. A summary budget is an element of the project charter.
  • D. High-level risks are an element of the project charter.

Question 35

Which document describes the necessary information to determine if a project is worth the required investment?

  • A. Cost baseline
  • B. Service level agreement
  • C. Memorandum of understanding
  • D. Business case
Show answer and explanation ▾

Correct answer: D

The business case provides the necessary information from a business standpoint to determine whether the project is worth the required investment. It typically contains the business need and a cost-benefit analysis.

Why the other options are wrong:

  • A. The cost baseline is the approved time-phased project budget.
  • B. A service level agreement is a form of agreement that defines the level of service to be provided.
  • C. A memorandum of understanding is a form of agreement between parties, not an investment justification.

Question 36

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

  • A. Estimate Costs
  • B. Control Costs
  • C. Determine Budget
  • D. Plan Cost Management
Show answer and explanation ▾

Correct answer: B

Control Costs monitors the status of the project to update the project costs and manages changes to the cost baseline. It provides the means to recognize variance from the plan so corrective action can be taken.

Why the other options are wrong:

  • A. Estimate Costs develops an approximation of the monetary resources needed for project activities.
  • C. Determine Budget aggregates the estimated costs to establish an authorized cost baseline.
  • D. Plan Cost Management establishes the policies and procedures for planning, managing and controlling costs.

Question 37

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

  • A. Project team
  • B. Focus group
  • C. Change control board
  • D. Project stakeholders
Show answer and explanation ▾

Correct answer: C

A change control board is a formally chartered group responsible for reviewing, evaluating, approving, delaying or rejecting changes to the project, and for recording and communicating those decisions.

Why the other options are wrong:

  • A. The project team performs the project work and does not hold formal authority over change decisions.
  • B. A focus group is a requirements technique that gathers expectations from prequalified participants.
  • D. Project stakeholders as a whole are affected by changes but are not the chartered decision body.

Question 38

Plan Schedule Management is a process in which Knowledge Area?

  • A. Project Scope Management
  • B. Project Human Resource Management
  • C. Project Integration Management
  • D. Project Time Management
Show answer and explanation ▾

Correct answer: D

Plan Schedule Management is the first process in Project Time Management, the Knowledge Area that covers the processes required to manage the timely completion of the project.

Why the other options are wrong:

  • A. Project Scope Management covers defining and controlling what is included in the project.
  • B. Project Human Resource Management covers organizing, managing and leading the project team.
  • C. Project Integration Management covers unifying and coordinating the various processes and activities.

Question 39

An output of the Validate Scope process is:

  • A. A requirements traceability matrix.
  • B. The scope management plan.
  • C. Work performance reports.
  • D. Change requests.
Show answer and explanation ▾

Correct answer: D

Completed deliverables that are not formally accepted in Validate Scope are documented with the reasons, and they may require a change request for defect repair. The outputs of the process are accepted deliverables, change requests, work performance information and project documents updates.

Why the other options are wrong:

  • A. The requirements traceability matrix is an output of Collect Requirements and an input to Validate Scope.
  • B. The scope management plan is an output of Plan Scope Management.
  • C. Work performance reports are an output of Monitor and Control Project Work.

Question 40

The

Perform Integrated Change Control process occurs in which Process Group?

  • A. Initiating
  • B. Executing
  • C. Monitoring and Controlling
  • D. Planning
Show answer and explanation ▾

Correct answer: C

Perform Integrated Change Control reviews all change requests, approves changes and manages changes to deliverables, documents and the project management plan. It is part of the Monitoring and Controlling Process Group.

Why the other options are wrong:

  • A. Initiating contains only Develop Project Charter and Identify Stakeholders.
  • B. Executing implements approved changes but does not review and decide on them.
  • D. Planning develops the plans and baselines that change control later protects.

Question 41

Which input to the Plan Risk Management process provides information on high-level risks?

  • A. Project charter
  • B. Enterprise environmental factors
  • C. Stakeholder register
  • D. Organizational process assets
Show answer and explanation ▾

Correct answer: A

The project charter provides inputs to Plan Risk Management such as high-level risks, high-level project descriptions and high-level requirements.

Why the other options are wrong:

  • B. Enterprise environmental factors supply the organization's risk attitudes, thresholds and tolerances.
  • C. The stakeholder register supplies details about project stakeholders and an overview of their roles.
  • D. Organizational process assets supply items such as risk categories, templates and lessons learned.

Question 42

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

  • A. Work performance data
  • B. Project documents
  • C. Scope baseline
  • D. Requirements documentation
Show answer and explanation ▾

Correct answer: B

Project documents are an input to Perform Quality Assurance. They may influence quality assurance work and should be monitored within the context of a system for configuration management.

Why the other options are wrong:

  • A. Work performance data is not an input to Perform Quality Assurance.
  • C. The scope baseline is not a listed input to Perform Quality Assurance.
  • D. Requirements documentation is an input to Plan Quality Management, not the input described here.

Question 43

Change requests are processed for review and disposition according to which process?

  • A. Control Quality
  • B. Control Scope
  • C. Monitor and Control Project Work
  • D. Perform Integrated Change Control
Show answer and explanation ▾

Correct answer: D

All change requests, whichever process raises them, are processed for review and disposition through Perform Integrated Change Control. Changes are approved or rejected there, and the decisions are recorded in the change log.

Why the other options are wrong:

  • A. Control Quality can raise change requests but does not decide their disposition.
  • B. Control Scope can raise change requests but does not decide their disposition.
  • C. Monitor and Control Project Work can raise change requests but does not decide their disposition.

Question 44

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

  • A. Work performance information.
  • B. Inspections and audits.
  • C. Payment systems.
  • D. Procurement performance reviews.
Show answer and explanation ▾

Correct answer: D

A procurement performance review is a structured review of the seller's progress in delivering project scope and quality, within cost and on schedule, as compared with the contract.

Why the other options are wrong:

  • A. Work performance information is an output that provides a basis for identifying current or potential problems.
  • B. Inspections and audits verify compliance in the seller's work processes or deliverables.
  • C. Payment systems process payments to the seller after the work is certified as satisfactory.

Question 45

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

  • A. Project Communications Management
  • B. Project Integration Management
  • C. Project Risk Management
  • D. Project Scope Management
Show answer and explanation ▾

Correct answer: B

Project Integration Management identifies, defines, combines, unifies and coordinates the processes and activities within the Process Groups. Because those processes interact and are repeated throughout the project, integration is needed to keep them working together.

Why the other options are wrong:

  • A. Project Communications Management covers planning, distributing and controlling project information.
  • C. Project Risk Management covers identifying, analyzing and responding to project risk.
  • D. Project Scope Management covers defining and controlling what is included in the project.

Question 46

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

  • A. Scope baseline
  • B. Organizational process assets
  • C. Enterprise environmental factors
  • D. Risk register
Show answer and explanation ▾

Correct answer: C

Enterprise environmental factors that influence Estimate Costs include market conditions, which describe what products and services are available and on what terms, and published commercial information such as resource cost rates and seller price lists.

Why the other options are wrong:

  • A. The scope baseline supplies the scope statement, WBS and WBS dictionary.
  • B. Organizational process assets are internal items such as cost estimating policies, templates and historical information.
  • D. The risk register lists identified risks and their responses, not market data.

Question 47

An output of the Develop Project Team process is:

  • A. Organizational process assets.
  • B. Enterprise environmental factors updates.
  • C. Project staff assignments.
  • D. Organizational charts and position descriptions.
Show answer and explanation ▾

Correct answer: B

Develop Project Team has two outputs: team performance assessments and enterprise environmental factors updates. The updates cover items such as personnel administration, employee training records and skill assessments.

Why the other options are wrong:

  • A. Organizational process assets are not an output of Develop Project Team.
  • C. Project staff assignments are an output of Acquire Project Team.
  • D. Organizational charts and position descriptions are a tool of Plan Human Resource Management.

Question 48

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

  • A. Plan Human Resource Management.
  • B. Acquire Project Team.
  • C. Manage Project Team.
  • D. Develop Project Team.
Show answer and explanation ▾

Correct answer: B

Acquire Project Team confirms human resource availability and obtains the team necessary to complete project activities. It guides team selection and responsibility assignment.

Why the other options are wrong:

  • A. Plan Human Resource Management documents roles, responsibilities and reporting relationships.
  • C. Manage Project Team tracks performance, gives feedback and resolves issues.
  • D. Develop Project Team improves competencies, interaction and the team environment.

Question 49

Which item is an example of personnel assessment?

  • A. Resource calendar
  • B. Tight matrix
  • C. Team-building activity
  • D. Focus group
Show answer and explanation ▾

Correct answer: D

Personnel assessment tools give the project manager insight into team strengths and weaknesses. Examples include attitudinal surveys, specific assessments, structured interviews, ability tests and focus groups.

Why the other options are wrong:

  • A. A resource calendar records the time periods when team members are available.
  • B. Tight matrix is another name for colocation, placing team members in the same location.
  • C. Team-building activities are a separate tool of Develop Project Team.

Question 50

The Plan Stakeholder Management process belongs to which Process Group?

  • A. Executing
  • B. Initiating
  • C. Planning
  • D. Monitoring and Controlling
Show answer and explanation ▾

Correct answer: C

Plan Stakeholder Management develops strategies to engage stakeholders throughout the project based on their needs, interests and potential impact. It is a Planning Process Group process.

Why the other options are wrong:

  • A. Executing contains Manage Stakeholder Engagement.
  • B. Initiating contains Identify Stakeholders.
  • D. Monitoring and Controlling contains Control Stakeholder Engagement.

Question 51

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

  • A. Feedback analysis
  • B. Stakeholder analysis
  • C. Communication management plan
  • D. Stakeholder management plan
Show answer and explanation ▾

Correct answer: D

The stakeholder management plan provides guidance on how the various stakeholders can be best involved in the project. It describes the methods and technologies used for stakeholder communication.

Why the other options are wrong:

  • A. Feedback analysis is not an input to Manage Stakeholder Engagement.
  • B. Stakeholder analysis is a technique used in Identify Stakeholders.
  • C. The communications management plan provides guidance on stakeholder communication requirements and information flow.

Question 52

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

  • A. Benchmarking.
  • B. Context diagrams.
  • C. Brainstorming.
  • D. Prototyping.
Show answer and explanation ▾

Correct answer: D

Prototyping obtains early feedback on requirements by providing a working model of the expected product before actually building it. Stakeholders can experiment with the model instead of discussing abstract requirements.

Why the other options are wrong:

  • A. Benchmarking compares practices with those of comparable organizations to identify best practices.
  • B. Context diagrams depict the product scope by showing a business system and how people and other systems interact with it.
  • C. Brainstorming generates and collects multiple ideas without building a model.

Question 53

Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

  • A. Power/influence grid
  • B. Power/interest grid
  • C. Influence/impact grid
  • D. Salience model
Show answer and explanation ▾

Correct answer: A

The power/influence grid groups stakeholders based on their level of authority, which is power, and their active involvement in the project, which is influence.

Why the other options are wrong:

  • B. The power/interest grid uses level of authority and level of concern about project outcomes.
  • C. The influence/impact grid uses active involvement and the ability to effect changes to planning or execution.
  • D. The salience model classifies stakeholders by power, urgency and legitimacy.

Question 54

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

  • A. Facilitation techniques
  • B. Expert judgment
  • C. Analytical techniques
  • D. Variance analysis
Show answer and explanation ▾

Correct answer: C

In Plan Schedule Management, analytical techniques may involve choosing strategic options to estimate and schedule the project, such as the scheduling methodology, scheduling tools and techniques, estimating approaches, formats and project management software.

Why the other options are wrong:

  • A. Facilitation techniques are not a tool of Plan Schedule Management.
  • B. Expert judgment draws on historical information and experience from similar past projects.
  • D. Variance analysis compares actual results with the baseline and is not a tool of this process.

Question 55

Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

  • A. Control charts
  • B. Pareto diagrams
  • C. Ishikavva diagrams
  • D. Checksheets
Show answer and explanation ▾

Correct answer: D

Checksheets, also known as tally sheets, organize facts in a way that makes collecting useful data about a potential quality problem easier. They are especially useful for gathering attributes data while performing inspections to identify defects.

Why the other options are wrong:

  • A. Control charts determine whether a process is stable or has predictable performance.
  • B. Pareto diagrams rank the vital few sources responsible for most of a problem's effects.
  • C. Cause-and-effect diagrams trace a problem back to its root causes.

Question 56

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

  • A. Collect Requirements.
  • B. Conduct Procurements.
  • C. Estimate Activity Durations.
  • D. Estimate Activity Resources.
Show answer and explanation ▾

Correct answer: D

Estimate Activity Resources estimates the type and quantities of material, human resources, equipment or supplies required to perform each activity. This allows more accurate cost and duration estimates.

Why the other options are wrong:

  • A. Collect Requirements determines and documents stakeholder needs.
  • B. Conduct Procurements obtains seller responses, selects a seller and awards a contract.
  • C. Estimate Activity Durations estimates the number of work periods needed to complete each activity.

Question 57

Which input to the

Identify Stakeholders process provides information about internal or external parties related to the project?

  • A. Procurement documents
  • B. Communications plan
  • C. Project charter
  • D. Stakeholder register
Show answer and explanation ▾

Correct answer: C

The project charter can provide information about internal and external parties related to the project and affected by its result or execution, such as the sponsor, customers, team members and participating groups and departments.

Why the other options are wrong:

  • A. Procurement documents come into play when a project stems from a contract, where they name the contract parties and suppliers.
  • B. A communications plan is not an input to Identify Stakeholders.
  • D. The stakeholder register is the output of Identify Stakeholders.

Question 58

The

Identify Stakeholders process is found in which Process Group?

  • A. Initiating
  • B. Monitoring and Controlling
  • C. Planning
  • D. Executing
Show answer and explanation ▾

Correct answer: A

Identify Stakeholders is one of the two processes in the Initiating Process Group, together with Develop Project Charter. Stakeholders are identified early so their interests and influence can shape the project from the start.

Why the other options are wrong:

  • B. Monitoring and Controlling contains Control Stakeholder Engagement.
  • C. Planning contains Plan Stakeholder Management.
  • D. Executing contains Manage Stakeholder Engagement.

Question 59

An input to Develop Project Charter is a/an:

  • A. Business case.
  • B. Activity list.
  • C. Project management plan.
  • D. Cost forecast.
Show answer and explanation ▾

Correct answer: A

The inputs to Develop Project Charter are the project statement of work, the business case, agreements, enterprise environmental factors and organizational process assets. The business case justifies the investment that the charter authorizes.

Why the other options are wrong:

  • B. The activity list is an output of Define Activities, created during planning.
  • C. The project management plan is developed after the charter exists.
  • D. A cost forecast is an output of Control Costs.

Question 60

Which item is a formal proposal to modify any document, deliverable, or baseline?

  • A. Change request
  • B. Requirements documentation
  • C. Scope baseline
  • D. Risk urgency assessment
Show answer and explanation ▾

Correct answer: A

A change request is a formal proposal to modify any document, deliverable or baseline. Approved change requests replace the associated document, deliverable or baseline and may update other parts of the project management plan.

Why the other options are wrong:

  • B. Requirements documentation describes how individual requirements meet the business need.
  • C. The scope baseline is the approved scope statement, WBS and WBS dictionary.
  • D. A risk urgency assessment prioritizes risks that need a near-term response.

Question 61

Which process determines the risks that may affect the project and documents their characteristics?

  • A. Control Risks
  • B. Plan Risk Management
  • C. Plan Risk Responses
  • D. Identify Risks
Show answer and explanation ▾

Correct answer: D

Identify Risks determines which risks may affect the project and documents their characteristics. It gives the project team the knowledge and ability to anticipate events.

Why the other options are wrong:

  • A. Control Risks implements response plans and monitors identified and residual risks.
  • B. Plan Risk Management defines how risk management activities will be conducted.
  • C. Plan Risk Responses develops options and actions to address the risks already identified.

Question 62

An example of a group decision-making technique is:

  • A. Nominal group technique.
  • B. Majority.
  • C. Affinity diagram.
  • D. Multi-criteria decision analysis.
Show answer and explanation ▾

Correct answer: B

Group decision-making techniques are methods of reaching a group decision: unanimity, majority, plurality and dictatorship. A majority decision is one supported by more than 50 percent of the group members.

Why the other options are wrong:

  • A. Nominal group technique is a group creativity technique that ranks brainstormed ideas.
  • C. An affinity diagram is a group creativity technique that sorts ideas into groups.
  • D. Multi-criteria decision analysis is a group creativity technique that uses a decision matrix to evaluate and rank ideas.

Question 63

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

  • A. mitigate
  • B. accept
  • C. transfer
  • D. avoid
Show answer and explanation ▾

Correct answer: C

Transfer shifts the impact of a threat to a third party, together with ownership of the response. It gives another party responsibility for managing the risk without eliminating it, typically through insurance, performance bonds, warranties or guarantees.

Why the other options are wrong:

  • A. Mitigate reduces the probability of occurrence or the impact of a risk.
  • B. Accept acknowledges the risk and takes no action unless it occurs.
  • D. Avoid eliminates the threat or protects the project from its impact.

Question 64

An output of the Plan Quality Management process is:

  • A. A process improvement plan,
  • B. Quality control measurements.
  • C. Work performance information,
  • D. The project management plan.
Show answer and explanation ▾

Correct answer: A

The outputs of Plan Quality Management are the quality management plan, the process improvement plan, quality metrics, quality checklists and project documents updates. The process improvement plan details the steps for analyzing processes to identify activities that enhance their value.

Why the other options are wrong:

  • B. Quality control measurements are an output of Control Quality.
  • C. Work performance information is an output of controlling processes.
  • D. The project management plan is an input to Plan Quality Management.

Question 65

A project manager should document the escalation path for unresolved project risks in the:

  • A. Change control plan
  • B. Stakeholder register
  • C. Risk log
  • D. Communications management plan
Show answer and explanation ▾

Correct answer: D

The communications management plan contains the escalation process, which identifies the time frames and the management chain for escalating matters that cannot be resolved at a lower level.

Why the other options are wrong:

  • A. A change control plan describes how changes are requested and authorized, not how unresolved matters are escalated.
  • B. The stakeholder register records identification, assessment and classification details about stakeholders.
  • C. A risk log lists risks and their status and does not define an escalation path.

Question 66

Which process in Project Time Management includes reserve analysis as a tool or technique?

  • A. Estimate Activity Resources
  • B. Sequence Activities
  • C. Estimate Activity Durations
  • D. Develop Schedule
Show answer and explanation ▾

Correct answer: C

Estimate Activity Durations uses reserve analysis to add contingency reserves, also called time reserves or buffers, to duration estimates to account for schedule uncertainty. The reserve can be a percentage of the estimated duration or a fixed number of work periods.

Why the other options are wrong:

  • A. Estimate Activity Resources uses techniques such as alternative analysis, published estimating data and bottom-up estimating, not reserve analysis.
  • B. Sequence Activities uses the precedence diagramming method, dependency determination, and leads and lags.
  • D. Develop Schedule relies on schedule network analysis, the critical path method, resource optimization and schedule compression.

Question 67

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

  • A. Enhance
  • B. Share
  • C. Exploit
  • D. Accept
Show answer and explanation ▾

Correct answer: C

The exploit strategy is chosen for an opportunity the organization wants to make sure is realized. It removes the uncertainty around that upside risk by making the opportunity definitely happen, for example by assigning the most talented resources to the work.

Why the other options are wrong:

  • A. Enhance increases the probability or the positive impact of an opportunity but does not guarantee it happens.
  • B. Share allocates some or all ownership of the opportunity to a third party best able to capture it.
  • D. Accept means being willing to take advantage of the opportunity if it arises without actively pursuing it.

Question 68

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

  • A. Expert judgment.
  • B. Analytical techniques.
  • C. Earned value management.
  • D. Group decision-making techniques.
Show answer and explanation ▾

Correct answer: B

Payback period, return on investment, internal rate of return, discounted cash flow and net present value are financial analytical techniques. They are used in Plan Cost Management to weigh strategic options such as how to fund the project or whether to make, buy, rent or lease resources.

Why the other options are wrong:

  • A. Expert judgment is knowledge supplied by people with specialized training or experience, not a set of financial calculations.
  • C. Earned value management compares planned value, earned value and actual cost to measure project performance.
  • D. Group decision-making techniques are methods such as unanimity, majority and plurality for reaching a team decision.

Question 69

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

  • A. Timing
  • B. Methodology
  • C. Risk categories
  • D. Budgeting
Show answer and explanation ▾

Correct answer: A

The timing component of the risk management plan defines when and how often the risk management processes will be performed throughout the project life cycle. It also establishes the protocols for applying contingency and management reserves and the risk activities to include in the schedule.

Why the other options are wrong:

  • B. Methodology defines the approaches, tools and data sources that will be used to perform risk management.
  • C. Risk categories provide a way of grouping potential causes of risk, often as a risk breakdown structure.
  • D. Budgeting estimates the funds needed for risk management and sets up the reserves.

Question 70

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

  • A. Negative
  • B. Zero
  • C. Positive
  • D. Free
Show answer and explanation ▾

Correct answer: C

Total float is the difference between the late dates from the backward pass and the early dates from the forward pass. When the backward pass starts from a constraint that is later than the calculated early finish, the late dates fall after the early dates, so total float is positive.

Why the other options are wrong:

  • A. Negative total float results when the constraint date is earlier than the calculated early finish date.
  • B. Zero total float results when the backward pass starts from the same date as the calculated early finish.
  • D. Free float is the time an activity can slip without delaying the early start of its successor and is not a type of total float.

Question 71

A reward can only be effective if it is:

  • A. Given immediately after the project is completed.
  • B. Something that is tangible.
  • C. Formally given during project performance appraisals.
  • D. Satisfying a need valued by the individual.
Show answer and explanation ▾

Correct answer: D

People are motivated when they feel valued, and a reward only works when it satisfies a need that the individual receiving it actually values. Cultural differences and personal preferences should therefore be considered when rewards are chosen.

Why the other options are wrong:

  • A. Recognition should be given throughout the project life cycle rather than held back until the project is completed.
  • B. Intangible rewards such as growth, accomplishment and appreciation can be equally or more effective than tangible ones.
  • C. Rewards may be given formally or informally and are not limited to performance appraisals.

Question 72

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

  • A. Nominal group technique
  • B. Idea/mind mapping
  • C. Affinity diagram
  • D. Brainstorming
Show answer and explanation ▾

Correct answer: C

An affinity diagram allows large numbers of ideas to be classified into groups for review and analysis. It is typically used after ideas have been generated, to organize them into natural categories.

Why the other options are wrong:

  • A. The nominal group technique adds a voting process to rank ideas for further brainstorming or prioritization.
  • B. Idea/mind mapping consolidates ideas into a single map that shows commonality and differences in understanding.
  • D. Brainstorming generates and collects multiple ideas but does not group them.

Question 73

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

  • A. Bottom-up
  • B. Parametric
  • C. Analogous
  • D. Three-point
Show answer and explanation ▾

Correct answer: C

Analogous estimating uses values or measures of scale from a previous, similar project as the basis for estimating the same parameter on the current project. It is generally quicker and less costly than other techniques, but also less accurate.

Why the other options are wrong:

  • A. Bottom-up estimating estimates individual work components and aggregates them to higher levels.
  • B. Parametric estimating applies a statistical relationship between historical data and other variables to calculate an estimate.
  • D. Three-point estimating combines optimistic, pessimistic and most likely estimates to reflect uncertainty.

Question 74

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

  • A. Direct
  • B. Interactive
  • C. Pull
  • D. Push
Show answer and explanation ▾

Correct answer: D

Push communication is sent to specific recipients who need to receive the information. Letters, memos, reports, emails and faxes all distribute information this way, although the method does not confirm that the message actually reached or was understood by the audience.

Why the other options are wrong:

  • A. Direct is not one of the communication methods used to classify how project information is shared.
  • B. Interactive communication is a multidirectional exchange between parties, such as meetings and phone calls.
  • C. Pull communication requires recipients to access the content at their own discretion, such as intranet sites and e-learning.

Question 75

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

  • A. Cost variance (CV)
  • B. Cost performance index (CPI)
  • C. Budget at completion (BAC)
  • D. Variance at completion (VAC)
Show answer and explanation ▾

Correct answer: B

The cost performance index is the ratio of earned value to actual cost (CPI = EV / AC) and measures the cost efficiency of budgeted resources. A value below 1.0 indicates a cost overrun for the work completed, and a value above 1.0 indicates a cost underrun.

Why the other options are wrong:

  • A. Cost variance is a difference, earned value minus actual cost, not a ratio.
  • C. Budget at completion is the sum of all budgets established for the work to be performed.
  • D. Variance at completion is the projected budget deficit or surplus, budget at completion minus estimate at completion.

Question 76

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

  • A. Direct and Manage Project Work
  • B. Develop Project Management Plan
  • C. Plan Quality Management
  • D. Monitor and Control Project Work
Show answer and explanation ▾

Correct answer: B

Develop Project Management Plan is the process of defining, preparing and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The result is a central document that defines the basis of all project work.

Why the other options are wrong:

  • A. Direct and Manage Project Work leads and performs the work defined in the plan and implements approved changes.
  • C. Plan Quality Management identifies quality requirements and standards and produces only the quality-related plans.
  • D. Monitor and Control Project Work tracks, reviews and reports progress against the plan.

Question 77

Inputs to the Plan Schedule Management process include:

  • A. Organizational process assets and the project charter,
  • B. Enterprise environmental factors and schedule tools.
  • C. Time tables and Pareto diagrams.
  • D. Activity attributes and resource calendars.
Show answer and explanation ▾

Correct answer: A

The inputs to Plan Schedule Management are the project management plan, the project charter, enterprise environmental factors and organizational process assets. The charter supplies the summary milestone schedule and approval requirements, and organizational process assets supply templates, policies and historical information.

Why the other options are wrong:

  • B. Schedule tools are not listed as an input to this process.
  • C. Time tables and Pareto diagrams are not inputs to Plan Schedule Management.
  • D. Activity attributes and resource calendars are produced later and feed processes such as Estimate Activity Resources.

Question 78

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

  • A. Identify Risks
  • B. Control Risks
  • C. Perform Quantitative Risk Analysis
  • D. Perform Qualitative Risk Analysis
Show answer and explanation ▾

Correct answer: A

SWOT analysis is a tool of the Identify Risks process. It examines the project from the strengths, weaknesses, opportunities and threats perspectives to widen the range of identified risks, including those that arise from within the organization.

Why the other options are wrong:

  • B. Control Risks uses risk reassessment, risk audits, variance and trend analysis, and reserve analysis.
  • C. Perform Quantitative Risk Analysis uses techniques such as sensitivity analysis, expected monetary value analysis and simulation.
  • D. Perform Qualitative Risk Analysis uses probability and impact assessment, the probability and impact matrix, and risk categorization.

Question 79

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

  • A. Project Risk Management
  • B. Project Human Resource Management
  • C. Project Scope Management
  • D. Project Stakeholder Management
Show answer and explanation ▾

Correct answer: D

Project Stakeholder Management includes the processes required to identify the people, groups or organizations that could impact or be impacted by the project, analyze their expectations and develop strategies to engage them in project decisions and execution.

Why the other options are wrong:

  • A. Project Risk Management covers planning, identifying, analyzing, responding to and controlling project risks.
  • B. Project Human Resource Management organizes, manages and leads the project team.
  • C. Project Scope Management ensures the project includes all the work required, and only the work required.

Question 80

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

  • A. Stakeholder register
  • B. Scope management plan
  • C. Stakeholder management plan
  • D. Project charter
Show answer and explanation ▾

Correct answer: A

The stakeholder register is used in Collect Requirements to identify stakeholders who can provide information on the requirements. It also captures the major requirements and main expectations those stakeholders have for the project.

Why the other options are wrong:

  • B. The scope management plan clarifies how the team will determine which type of requirements to collect.
  • C. The stakeholder management plan describes stakeholder communication needs and the level of engagement required.
  • D. The project charter provides the high-level description of the product, service or result.

Question 81

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

  • A. Plan Procurement Management
  • B. Control Procurements
  • C. Collect Requirements
  • D. Plan Cost Management
Show answer and explanation ▾

Correct answer: A

Plan Procurement Management documents project procurement decisions, specifies the approach and identifies potential sellers. It identifies the project needs that can best be met by acquiring products, services or results from outside the organization, and what, how, how much and when to acquire.

Why the other options are wrong:

  • B. Control Procurements manages procurement relationships and monitors contract performance after a contract is in place.
  • C. Collect Requirements determines and documents stakeholder needs, not the decision to buy from outside.
  • D. Plan Cost Management establishes how project costs will be planned, managed and controlled.

Question 82

Which tool or technique is used to manage change requests and the resulting decisions?

  • A. Change control tools
  • B. Expert judgment
  • C. Delphi technique
  • D. Change log
Show answer and explanation ▾

Correct answer: A

Change control tools are manual or automated tools used in Perform Integrated Change Control to manage change requests and the resulting decisions. They also support communication of approved changes to the stakeholders and assist the change control board in its work.

Why the other options are wrong:

  • B. Expert judgment supplies specialist knowledge to assess a change but does not manage the requests and decisions.
  • C. The Delphi technique gathers anonymous expert opinion to reach consensus and is an information gathering technique.
  • D. The change log is a document that records changes, an output rather than a tool or technique.

Question 83

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

  • A. Work packages.
  • B. Accepted deliverables.
  • C. The WBS dictionary.
  • D. The scope baseline.
Show answer and explanation ▾

Correct answer: A

The planned work is contained within the lowest level of WBS components, which are called work packages. A work package can be scheduled, cost estimated, monitored and controlled.

Why the other options are wrong:

  • B. Accepted deliverables are products that the customer or sponsor has formally signed off in Validate Scope.
  • C. The WBS dictionary is the document that gives detailed information about each WBS component.
  • D. The scope baseline is the approved scope statement, WBS and WBS dictionary taken together.

Question 84

In which Knowledge Area is the project charter developed?

  • A. Project Cost Management
  • B. Project Scope Management
  • C. Project Time Management
  • D. Project Integration Management
Show answer and explanation ▾

Correct answer: D

Develop Project Charter is the first process in the Project Integration Management Knowledge Area. It produces the document that formally authorizes the project and gives the project manager authority to apply organizational resources to project activities.

Why the other options are wrong:

  • A. Project Cost Management covers planning, estimating, budgeting and controlling costs.
  • B. Project Scope Management covers requirements, scope definition, the WBS and scope validation and control.
  • C. Project Time Management covers defining, sequencing and estimating activities and developing and controlling the schedule.

Question 85

The ability to influence cost is greatest during which stages of the project?

  • A. Early
  • B. Middle
  • C. Late
  • D. Completion
Show answer and explanation ▾

Correct answer: A

The ability to influence cost is greatest at the early stages of the project, which makes early scope definition critical. As the project progresses, decisions are locked in and the cost of making changes rises substantially.

Why the other options are wrong:

  • B. By the middle of the project many cost-driving decisions have already been made and committed.
  • C. Late in the project the ability to influence cost is low and the cost of changes is high.
  • D. At completion almost all costs have been incurred, so influence over cost is at its lowest.

Question 86

Which process involves developing an approximation of the monetary resources needed to complete project activities?

  • A. Estimate Costs
  • B. Control Costs
  • C. Determine Budget
  • D. Plan Cost Management
Show answer and explanation ▾

Correct answer: A

Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. It determines the amount of cost required to complete the project work.

Why the other options are wrong:

  • B. Control Costs monitors project status to update costs and manages changes to the cost baseline.
  • C. Determine Budget aggregates the estimated costs to establish an authorized cost baseline.
  • D. Plan Cost Management establishes the policies and procedures for planning, managing and controlling costs.

Question 87

Which tool or technique is used in the Develop Project Management Plan process?

  • A. Pareto diagram
  • B. Performance reporting
  • C. SWOT analysis
  • D. Expert judgment
Show answer and explanation ▾

Correct answer: D

The tools and techniques of Develop Project Management Plan are expert judgment and facilitation techniques. Expert judgment is used to tailor the processes to the project, develop the technical and management details, and decide which documents are subject to formal change control.

Why the other options are wrong:

  • A. A Pareto diagram is a quality tool that ranks causes of problems by frequency.
  • B. Performance reporting is used to collect and distribute performance information, not to build the plan.
  • C. SWOT analysis is a risk identification technique.

Question 88

Lessons learned are created and project resources are released in which Process Group?

  • A. Planning
  • B. Executing
  • C. Closing
  • D. Initiating
Show answer and explanation ▾

Correct answer: C

The Closing Process Group finalizes all activities to formally complete the project or phase. Closing work includes documenting lessons learned, archiving project documents, performing team member assessments and releasing project resources.

Why the other options are wrong:

  • A. Planning establishes the scope, refines the objectives and defines the course of action.
  • B. Executing completes the work defined in the project management plan.
  • D. Initiating defines and authorizes a new project or phase.

Question 89

When should quality planning be performed?

  • A. While developing the project charter
  • B. In parallel with the other planning processes
  • C. As part of a detailed risk analysis
  • D. As a separate step from the other planning processes
Show answer and explanation ▾

Correct answer: B

Quality planning should be performed in parallel with the other planning processes. Changes proposed to the deliverables to meet quality standards may require cost or schedule adjustments and a risk analysis of their effect on the plans.

Why the other options are wrong:

  • A. The project charter is developed during initiating, before detailed quality requirements and standards are planned.
  • C. Quality planning is its own planning process and is not a part of risk analysis.
  • D. Treating quality planning as a separate step ignores its effect on cost, schedule and other plans.

Question 90

A key benefit of the Manage Communications process is that it enables:

  • A. The best use of communication methods.
  • B. An efficient and effective communication flow.
  • C. Project costs to be reduced.
  • D. The best use of communication technology.
Show answer and explanation ▾

Correct answer: B

Manage Communications creates, collects, distributes, stores, retrieves and ultimately disposes of project information in line with the communications management plan. Its stated benefit is that it enables an efficient and effective communications flow between project stakeholders.

Why the other options are wrong:

  • A. Choosing communication methods is part of planning communications and is not the stated benefit of this process.
  • C. Reducing project costs is not the benefit defined for Manage Communications.
  • D. Communication technology is selected when communications are planned and is not the benefit of this process.

Question 91

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

  • A. Human resource management plan.
  • B. Activity resource requirements.
  • C. Personnel assessment tools,
  • D. Multi-criteria decision analysis.
Show answer and explanation ▾

Correct answer: A

The human resource management plan, a part of the project management plan, gives guidance on how project human resources should be defined, staffed, managed and eventually released. It contains the roles and responsibilities, the project organization charts and the staffing management plan.

Why the other options are wrong:

  • B. Activity resource requirements list the types and quantities of resources needed for each activity.
  • C. Personnel assessment tools give insight into team members' strengths and weaknesses during team development.
  • D. Multi-criteria decision analysis is a technique for rating and selecting potential team members.

Question 92

The process of identifying and documenting relationships among the project activities is known as:

  • A. Control Schedule.
  • B. Sequence Activities.
  • C. Define Activities.
  • D. Develop Schedule.
Show answer and explanation ▾

Correct answer: B

Sequence Activities is the process of identifying and documenting relationships among the project activities. It defines the logical sequence of work so that the greatest efficiency can be obtained given all project constraints.

Why the other options are wrong:

  • A. Control Schedule monitors activity status to update progress and manage changes to the schedule baseline.
  • C. Define Activities identifies and documents the specific actions needed to produce the deliverables.
  • D. Develop Schedule analyzes sequences, durations, resources and constraints to create the schedule model.

Question 93

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

  • A. Enterprise environmental factors
  • B. Work performance reports
  • C. Organizational process assets
  • D. Context diagrams
Show answer and explanation ▾

Correct answer: A

Enterprise environmental factors are conditions, not under the control of the project team, that influence, constrain or direct the project. Examples include organizational culture, government or industry standards, marketplace conditions and the existing infrastructure.

Why the other options are wrong:

  • B. Work performance reports are project documents that present performance information for decisions and actions.
  • C. Organizational process assets are the plans, processes, policies, procedures and knowledge bases of the performing organization.
  • D. Context diagrams are scope models that show a business system and how people and other systems interact with it.

Question 94

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

  • A. Responses
  • B. Appetite
  • C. Tolerance
  • D. Attitude
Show answer and explanation ▾

Correct answer: A

Risk responses reflect an organization's perceived balance between risk taking and risk avoidance. The actions an organization chooses in the face of a risk show how much uncertainty it is prepared to accept in exchange for the expected benefit.

Why the other options are wrong:

  • B. Risk appetite is the degree of uncertainty an entity is willing to take on in anticipation of a reward.
  • C. Risk tolerance is the degree, amount or volume of risk an organization or individual will withstand.
  • D. Risk attitude is the general disposition toward risk that is shaped by appetite, tolerance and threshold.

Question 95

An output of the Manage Stakeholder Engagement process is:

  • A. change requests
  • B. enterprise environmental factors
  • C. the stakeholder management plan
  • D. the change log
Show answer and explanation ▾

Correct answer: A

The outputs of Manage Stakeholder Engagement are the issue log, change requests, project management plan updates, project documents updates and organizational process assets updates. Managing engagement can result in a change request to the product or the project.

Why the other options are wrong:

  • B. Enterprise environmental factors are conditions outside the team's control and are not produced by this process.
  • C. The stakeholder management plan is an input that guides how stakeholders are engaged.
  • D. The change log is an input to this process, used to document changes that occur during the project.

Question 96

Which process numerically analyzes the effect of identified risks on overall project objectives?

  • A. Plan Risk Management
  • B. Plan Risk Responses
  • C. Perform Quantitative Risk Analysis
  • D. Perform Qualitative Risk Analysis
Show answer and explanation ▾

Correct answer: C

Perform Quantitative Risk Analysis is the process of numerically analyzing the effect of identified risks on overall project objectives. It produces quantitative risk information to support decision making and reduce project uncertainty.

Why the other options are wrong:

  • A. Plan Risk Management defines how to conduct risk management activities for the project.
  • B. Plan Risk Responses develops options and actions to enhance opportunities and reduce threats.
  • D. Perform Qualitative Risk Analysis prioritizes risks by assessing probability and impact rather than numerically analyzing their overall effect.

Question 97

An input to the Plan Procurement Management process is:

  • A. Source selection criteria.
  • B. Market research.
  • C. A stakeholder register.
  • D. A records management system.
Show answer and explanation ▾

Correct answer: C

The stakeholder register is an input to Plan Procurement Management. It provides details on the project participants and their interests in the project, which helps shape procurement decisions.

Why the other options are wrong:

  • A. Source selection criteria are an output of Plan Procurement Management.
  • B. Market research is a tool and technique of Plan Procurement Management.
  • D. A records management system is a tool and technique used in controlling and closing procurements.

Question 98

Reserve analysis is a tool and technique used in which process?

  • A. Plan Risk Management
  • B. Plan Risk Responses
  • C. Identify Risks
  • D. Control Risks
Show answer and explanation ▾

Correct answer: D

Control Risks uses reserve analysis to compare the amount of contingency reserves remaining with the amount of risk remaining at any time in the project, in order to determine whether the remaining reserve is adequate.

Why the other options are wrong:

  • A. Plan Risk Management uses analytical techniques, expert judgment and meetings.
  • B. Plan Risk Responses uses strategies for threats and opportunities, contingent response strategies and expert judgment.
  • C. Identify Risks uses techniques such as documentation reviews, information gathering, checklists and SWOT analysis.

Question 99

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

  • A. Close Project or Phase
  • B. Conduct Procurements
  • C. Control Procurements
  • D. Close Procurements
Show answer and explanation ▾

Correct answer: D

Close Procurements produces closed procurements and organizational process assets updates. Those updates include the procurement file, the formal written notice of deliverable acceptance from the buyer, and lessons learned documentation.

Why the other options are wrong:

  • A. Close Project or Phase finalizes the whole project or phase and transitions the final product, service or result.
  • B. Conduct Procurements produces selected sellers and agreements.
  • C. Control Procurements produces work performance information and change requests while the contract is still being performed.

Question 100

Risk categorization is a tool or technique used in which process?

  • A. Plan Risk Responses
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis
Show answer and explanation ▾

Correct answer: C

Risk categorization is a tool and technique of Perform Qualitative Risk Analysis. Risks are grouped by source, by affected area of the project or by other useful categories to find the areas most exposed to uncertainty and to develop effective responses.

Why the other options are wrong:

  • A. Plan Risk Responses uses response strategies for threats and opportunities, not risk categorization.
  • B. Plan Risk Management uses analytical techniques, expert judgment and meetings.
  • D. Perform Quantitative Risk Analysis uses data gathering and quantitative modeling techniques.

Question 101

A regression line is used to estimate:

  • A. Whether or not a process is stable or has predictable performance.
  • B. How a change to the independent variable influences the value of the dependent variable.
  • C. The upper and lower specification limits on a control chart.
  • D. The central tendency, dispersion, and shape of a statistical distribution.
Show answer and explanation ▾

Correct answer: B

On a scatter diagram, a regression line is calculated to show the relationship between two variables. It is used to estimate how a change to the independent variable will influence the value of the dependent variable.

Why the other options are wrong:

  • A. Process stability and predictable performance are assessed with a control chart.
  • C. Specification limits are set from the requirements in the agreement and are not estimated by a regression line.
  • D. Central tendency, dispersion and the shape of a distribution are shown by a histogram.

Question 102

An input to Conduct Procurements is:

  • A. Independent estimates.
  • B. Selected sellers.
  • C. Seller proposals.
  • D. Resource calendars.
Show answer and explanation ▾

Correct answer: C

Seller proposals, prepared in response to a procurement document package, are an input to Conduct Procurements. They form the basic information that an evaluation body uses to select one or more successful bidders.

Why the other options are wrong:

  • A. Independent estimates are a tool and technique of Conduct Procurements.
  • B. Selected sellers are an output of Conduct Procurements.
  • D. Resource calendars are an output of Conduct Procurements.

Question 103

What are the Project Procurement Management processes?

  • A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
  • B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
  • C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
  • D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements
Show answer and explanation ▾

Correct answer: C

Project Procurement Management consists of four processes: Plan Procurement Management, Conduct Procurements, Control Procurements and Close Procurements. Together they cover deciding what to acquire, selecting sellers, managing the contracts and completing each procurement.

Why the other options are wrong:

  • A. Integrate Procurements is not a process, and this list leaves out Plan Procurement Management.
  • B. Estimate Procurements, Integrate Procurements and Validate Procurements are not processes.
  • D. Perform Procurements and Validate Procurements are not processes.

Question 104

Which tool or technique is used to develop the human resource management plan?

  • A. Ground rules
  • B. Expert judgment
  • C. Team-building activities
  • D. Interpersonal skills
Show answer and explanation ▾

Correct answer: B

Plan Human Resource Management uses organization charts and position descriptions, networking, organizational theory, expert judgment and meetings. Expert judgment is used to list the required skills, assess the roles needed and determine the effort and number of resources required.

Why the other options are wrong:

  • A. Ground rules are a technique of Develop Project Team.
  • C. Team-building activities are a technique of Develop Project Team.
  • D. Interpersonal skills are used when developing and managing the project team.

Question 105

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

  • A. Only once, at the beginning
  • B. At the beginning and the end
  • C. Once during each phase
  • D. Repeatedly
Show answer and explanation ▾

Correct answer: D

As more project information is gathered and understood, additional planning is likely to be required. Significant changes during the project trigger a need to revisit planning processes, so planning is iterative and ongoing, a progressive detailing of the plan known as progressive elaboration.

Why the other options are wrong:

  • A. Planning is not finished at the beginning of the project, because plans are refined as information becomes available.
  • B. Planning is not confined to the beginning and the end of the project.
  • C. Planning is not limited to a single pass in each phase, since changes can trigger replanning at any time.

Question 106

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

  • A. A risk urgency assessment.
  • B. The scope baseline.
  • C. Work performance information.
  • D. Procurement audits.
Show answer and explanation ▾

Correct answer: C

Work performance information from Control Procurements provides a basis for identifying current or potential problems to support later claims or new procurements. By reporting on vendor performance, the organization also improves its forecasting, risk management and decision making.

Why the other options are wrong:

  • A. A risk urgency assessment identifies risks that need a near-term response.
  • B. The scope baseline is the approved scope statement, WBS and WBS dictionary.
  • D. Procurement audits are structured reviews of the procurement process performed when procurements are closed.

Question 107

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

  • A. Requirements documentation
  • B. Requirements traceability matrix
  • C. Project management plan updates
  • D. Project documents updates
Show answer and explanation ▾

Correct answer: B

The requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them. It helps ensure that each requirement adds business value and that approved requirements are delivered at the end of the project.

Why the other options are wrong:

  • A. Requirements documentation describes how individual requirements meet the business need but does not link them to deliverables.
  • C. Project management plan updates are not an output of Collect Requirements.
  • D. Project documents updates are not an output of Collect Requirements.

Question 108

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

  • A. Cost management plan.
  • B. Work performance information.
  • C. Quality management plan.
  • D. Work breakdown structure.
Show answer and explanation ▾

Correct answer: A

The cost management plan establishes the units of measure, level of precision, level of accuracy, organizational procedures links, control thresholds, rules of performance measurement, reporting formats and process descriptions used to plan, manage and control project costs.

Why the other options are wrong:

  • B. Work performance information is analyzed performance data, not a place where measurement rules are established.
  • C. The quality management plan describes how the organization's quality policies will be implemented.
  • D. The work breakdown structure is a hierarchical decomposition of the total scope of work.

Question 109

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

  • A. External
  • B. Internal
  • C. Mandatory
  • D. Discretionary
Show answer and explanation ▾

Correct answer: D

Discretionary dependencies, also called preferred logic, preferential logic or soft logic, are established from knowledge of best practices in an application area or some unusual aspect of the project where a specific sequence is desired, even though other sequences would be acceptable.

Why the other options are wrong:

  • A. External dependencies involve a relationship between project activities and non-project activities outside the team's control.
  • B. Internal dependencies involve a precedence relationship between project activities that is within the team's control.
  • C. Mandatory dependencies are legally or contractually required or inherent in the nature of the work.

Question 110

Sensitivity analysis is typically displayed as a/an:

  • A. Decision tree diagram.
  • B. Tornado diagram.
  • C. Pareto diagram.
  • D. Ishikawa diagram.
Show answer and explanation ▾

Correct answer: B

A tornado diagram is the typical display of sensitivity analysis. It is a bar chart that compares the relative importance and impact of variables with a high degree of uncertainty against those that are more stable, with the widest bars at the top.

Why the other options are wrong:

  • A. A decision tree diagram is used for expected monetary value analysis of alternative choices.
  • C. A Pareto diagram ranks the sources of a problem by frequency.
  • D. An Ishikawa diagram traces a problem back to its root causes.

Question 111

The Monitoring and Controlling Process Group includes processes that:

  • A. Establish the scope, objectives, and course of action of a project,
  • B. Define a new project or a new phase of an existing project.
  • C. Track, review, and regulate the progress and performance of a project.
  • D. Complete the work defined in the project management plan.
Show answer and explanation ▾

Correct answer: C

The Monitoring and Controlling Process Group consists of the processes required to track, review and regulate the progress and performance of the project, identify any areas in which changes to the plan are required, and initiate the corresponding changes.

Why the other options are wrong:

  • A. Establishing the scope, objectives and course of action describes the Planning Process Group.
  • B. Defining a new project or a new phase describes the Initiating Process Group.
  • D. Completing the work defined in the project management plan describes the Executing Process Group.

Question 112

Which Control Quality tool is also known as an arrow diagram?

  • A. Matrix diagram
  • B. Affinity diagram
  • C. Tree diagram
  • D. Activity network diagram
Show answer and explanation ▾

Correct answer: D

Activity network diagrams were previously known as arrow diagrams. They include both the activity-on-arrow and activity-on-node formats and are used with scheduling methods such as the program evaluation and review technique and the critical path method.

Why the other options are wrong:

  • A. A matrix diagram shows the strength of relationships between factors, causes and objectives in rows and columns.
  • B. An affinity diagram groups ideas into related sets.
  • C. A tree diagram shows a decomposition hierarchy such as the WBS or an organizational breakdown structure.

Question 113

A project manager builds consensus and overcomes obstacles by employing which communication technique?

  • A. Listening
  • B. Facilitation
  • C. Meeting management
  • D. Presentation
Show answer and explanation ▾

Correct answer: B

Facilitation techniques are used to build consensus and overcome obstacles. They are among the techniques applied in Manage Communications, alongside listening, meeting management and presentation techniques.

Why the other options are wrong:

  • A. Listening techniques involve acknowledging, clarifying and confirming understanding and removing barriers to comprehension.
  • C. Meeting management covers preparing an agenda and dealing with conflicts during the meeting.
  • D. Presentation techniques concern awareness of body language and the design of visual aids.

Question 114

When does the project team determine which dependencies are discretionary?

  • A. Before the Define Activities process
  • B. During the Define Activities process
  • C. Before the Sequence Activities process
  • D. During the Sequence Activities process
Show answer and explanation ▾

Correct answer: D

Dependency determination is a tool and technique of Sequence Activities. The project team decides which dependencies are discretionary while it is sequencing the activities, and it documents them because they can create arbitrary total float values and limit later scheduling options.

Why the other options are wrong:

  • A. Before Define Activities the activities do not yet exist, so their dependencies cannot be determined.
  • B. Define Activities identifies the activities themselves and does not determine the relationships between them.
  • C. Dependencies are determined as part of sequencing the activities, not ahead of that process.

Question 115

Typical outcomes of a project include:

  • A. Products, services, and improvements.
  • B. Products, programs, and services.
  • C. Improvements, portfolios, and services.
  • D. Improvements, processes, and products.
Show answer and explanation ▾

Correct answer: A

A project can create a product, a service or a capability to perform a service, an improvement in existing product or service lines, or a result such as a document. Products, services and improvements are therefore typical project outcomes.

Why the other options are wrong:

  • B. A program is a group of related projects managed in a coordinated way, not an outcome of a project.
  • C. A portfolio is a collection of projects, programs and operations managed to meet strategic objectives, not an outcome of a project.
  • D. This combination is not the set of outcomes that the project definition lists.

Question 116

Which grid shows which resources are tied to work packages?

  • A. Work breakdown structure (WBS)
  • B. Responsibility assignment matrix (RAM)
  • C. Project assignment chart
  • D. Personnel assignment matrix
Show answer and explanation ▾

Correct answer: B

A responsibility assignment matrix is a grid that shows the project resources assigned to each work package. It illustrates the connections between work packages or activities and project team members, and a RACI chart is one common form.

Why the other options are wrong:

  • A. The WBS is a hierarchical decomposition of the project scope and does not show resource assignments.
  • C. A project assignment chart is not the grid used to tie resources to work packages.
  • D. A personnel assignment matrix is not the grid used to tie resources to work packages.

Question 117

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

  • A. Continuous improvement.
  • B. Predictive planning.
  • C. Progressive elaboration.
  • D. Quality assurance.
Show answer and explanation ▾

Correct answer: C

Progressive elaboration is the iterative process of increasing the level of detail in the project management plan as greater amounts of information and more accurate estimates become available. It allows the team to define and manage work in more detail as the project evolves.

Why the other options are wrong:

  • A. Continuous improvement is the ongoing effort to improve the quality of processes and products.
  • B. A predictive approach fixes scope, time and cost as early as possible rather than describing how detail is added over time.
  • D. Quality assurance audits quality requirements and the results of quality control measurements.

Question 118

An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:

  • A. smooth/accommodate.
  • B. force/direct,
  • C. collaborate/problem solve,
  • D. compromise/reconcile.
Show answer and explanation ▾

Correct answer: C

Collaborate/problem solve incorporates multiple viewpoints and insights from differing perspectives. It requires a cooperative attitude and open dialogue and typically leads to consensus and commitment, which makes it a win-win approach.

Why the other options are wrong:

  • A. Smooth/accommodate emphasizes areas of agreement and concedes one's position to maintain harmony.
  • B. Force/direct pushes one viewpoint at the expense of others and offers only win-lose solutions.
  • D. Compromise/reconcile seeks some degree of satisfaction for all parties and resolves the conflict only temporarily or partially.

Question 119

A temporary endeavor that creates a unique product or service is called a:

  • A. Project
  • B. Plan
  • C. Program
  • D. Portfolio
Show answer and explanation ▾

Correct answer: A

A project is a temporary endeavor undertaken to create a unique product, service or result. Temporary means it has a definite beginning and end, and unique means its output differs in some way from other products or services.

Why the other options are wrong:

  • B. A plan describes how work will be carried out and is not the endeavor itself.
  • C. A program is a group of related projects managed in a coordinated way to obtain benefits.
  • D. A portfolio is a collection of projects, programs and operations managed as a group to achieve strategic objectives.

Question 120

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

  • A. Earned value management.
  • B. Enterprise environmental factors.
  • C. Organizational process assets.
  • D. Work performance information.
Show answer and explanation ▾

Correct answer: D

Work performance information is the performance data collected from the controlling processes, analyzed in context and integrated across areas. Examples are the status of deliverables, the implementation status for change requests and forecasted estimates to complete.

Why the other options are wrong:

  • A. Earned value management is a method for measuring performance, not the resulting information items listed.
  • B. Enterprise environmental factors are conditions outside the project team's control.
  • C. Organizational process assets are the organization's processes, policies, procedures and knowledge bases.

Question 121

Which item is an output of Plan Quality Management and an input to

Perform Quality Assurance?

  • A. Organizational process updates
  • B. Quality metrics
  • C. Change requests
  • D. Quality control measurements
Show answer and explanation ▾

Correct answer: B

Quality metrics are an output of Plan Quality Management and an input to Perform Quality Assurance and Control Quality. A quality metric describes a project or product attribute and how the Control Quality process will measure it.

Why the other options are wrong:

  • A. Organizational process updates are not an output of Plan Quality Management.
  • C. Change requests are an output of Perform Quality Assurance.
  • D. Quality control measurements are produced by Control Quality, not by Plan Quality Management.

Question 122

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

  • A. Urgent information need
  • B. Sensitivity of information
  • C. Project environment
  • D. Ease of use
Show answer and explanation ▾

Correct answer: C

Project environment is the communication technology factor that asks whether the team will meet face to face or work virtually, whether members are spread over one or several time zones, whether they use multiple languages, and whether other factors such as culture may affect communications.

Why the other options are wrong:

  • A. Urgency of the need for information concerns how quickly and how often information must be delivered.
  • B. Sensitivity and confidentiality of information concerns whether extra security measures are needed.
  • D. Ease of use concerns whether the chosen technologies suit the participants and whether training is planned.

Question 123

The number of potential communication channels for a project with 5 stakeholders is:

  • A. 10.
  • B. 12.
  • C. 20.
  • D. 24.
Show answer and explanation ▾

Correct answer: A

The number of potential communication channels is n(n - 1) / 2, where n is the number of stakeholders. With 5 stakeholders the result is 5 x 4 / 2 = 10 channels.

Why the other options are wrong:

  • B. 12 does not result from the formula n(n - 1) / 2 with n = 5.
  • C. 20 is n(n - 1) without dividing by 2, which counts every channel twice.
  • D. 24 does not result from the formula n(n - 1) / 2 with n = 5.

Question 124

The process of prioritizing risks for further analysis or action is known as:

  • A. Plan Risk Management.
  • B. Plan Risk Responses.
  • C. Perform Qualitative Risk Analysis.
  • D. Perform Quantitative Risk Analysis.
Show answer and explanation ▾

Correct answer: C

Perform Qualitative Risk Analysis is the process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact. It lets project managers reduce uncertainty and focus on high-priority risks.

Why the other options are wrong:

  • A. Plan Risk Management defines how risk management activities will be conducted.
  • B. Plan Risk Responses develops options and actions for risks that have already been prioritized.
  • D. Perform Quantitative Risk Analysis numerically analyzes the effect of identified risks on overall project objectives.

Question 125

Which tool or technique is used in validating the scope of a project?

  • A. Facilitated workshops
  • B. Interviews
  • C. Inspection
  • D. Meetings
Show answer and explanation ▾

Correct answer: C

The tools and techniques of Validate Scope are inspection and group decision-making techniques. Inspection includes measuring, examining and validating to determine whether work and deliverables meet requirements and product acceptance criteria, and may be called a review, audit or walkthrough.

Why the other options are wrong:

  • A. Facilitated workshops are used to define requirements in Collect Requirements.
  • B. Interviews are used to elicit information from stakeholders in Collect Requirements.
  • D. Meetings are not a tool or technique of Validate Scope.

Question 126

An input to Close Project or Phase is:

  • A. Accepted deliverables,
  • B. Final products or services,
  • C. Document updates,
  • D. Work performance information.
Show answer and explanation ▾

Correct answer: A

Close Project or Phase takes the project management plan, accepted deliverables and organizational process assets as inputs. Accepted deliverables are those the customer or sponsor has formally approved in Validate Scope, so they can be handed over when the project or phase closes.

Why the other options are wrong:

  • B. The final product, service or result transition is an output of Close Project or Phase.
  • C. Document updates are an output of many processes, not an input to closing.
  • D. Work performance information is an output of monitoring and controlling processes and is not an input to closing.

Question 127

An output of the Direct and Manage Project Work process is:

  • A. Deliverables.
  • B. Activity lists.
  • C. A work breakdown structure.
  • D. A scope statement.
Show answer and explanation ▾

Correct answer: A

Direct and Manage Project Work is where the planned work is performed, so its main output is deliverables: the unique, verifiable products, results or capabilities the project must produce. It also produces work performance data and change requests.

Why the other options are wrong:

  • B. The activity list is an output of Define Activities.
  • C. The work breakdown structure is created in the Create WBS process.
  • D. The project scope statement is an output of Define Scope.

Question 128

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

  • A. Customers.
  • B. Business partners.
  • C. Sellers.
  • D. Functional managers.
Show answer and explanation ▾

Correct answer: B

Business partners are external organizations that have a special relationship with the enterprise, sometimes gained through a certification process, and that provide specialized expertise or fill a specified role such as installation, customization, training or support.

Why the other options are wrong:

  • A. Customers are the people or organizations that approve and manage the project's product, service or result.
  • C. Sellers are external companies that supply components or services under a contract.
  • D. Functional managers are internal managers of an administrative or functional area of the business.

Question 129

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

  • A. Develop Schedule
  • B. Create VVBS
  • C. Estimate Activity Resources
  • D. Define Scope
Show answer and explanation ▾

Correct answer: B

Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable components. Its benefit is a structured view of everything that has to be delivered.

Why the other options are wrong:

  • A. Develop Schedule analyzes activity sequences, durations and resources to build the schedule model.
  • C. Estimate Activity Resources estimates the type and quantity of resources each activity needs.
  • D. Define Scope develops the detailed description of the project and product.

Question 130

In a project, total float measures the:

  • A. Ability to shuffle schedule activities to lessen the duration of the project.
  • B. Amount of time an activity can be extended or delayed without altering the project finish date.
  • C. Cost expended to restore order to the project schedule after crashing the schedule.
  • D. Estimate of the total resources needed for the project after performing a forward pass.
Show answer and explanation ▾

Correct answer: B

Total float is the amount of time a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint. Activities on the critical path normally have zero total float.

Why the other options are wrong:

  • A. Rearranging activities to shorten the project describes schedule compression, not float.
  • C. Float is measured in time, not in cost spent after crashing.
  • D. Float does not estimate resources, and a forward pass calculates early dates only.

Question 131

Which Knowledge Areas include processes from the Closing Process Group?

  • A. Project Quality Management and Project Time Management
  • B. Project Scope Management and Project Risk Management
  • C. Project Stakeholder Management and Project Cost Management
  • D. Project Integration Management and Project Procurement Management
Show answer and explanation ▾

Correct answer: D

The Closing Process Group contains two processes: Close Project or Phase, which belongs to Project Integration Management, and Close Procurements, which belongs to Project Procurement Management.

Why the other options are wrong:

  • A. Quality and Time Management have no processes in the Closing Process Group.
  • B. Scope and Risk Management have no processes in the Closing Process Group.
  • C. Stakeholder and Cost Management have no processes in the Closing Process Group.

Question 132

Stakeholder satisfaction should be managed as a key project:

  • A. Benefit
  • B. Initiative
  • C. Objective
  • D. Process
Show answer and explanation ▾

Correct answer: C

Project Stakeholder Management focuses on continuous communication with stakeholders to understand their needs and expectations. Stakeholder satisfaction should be managed as a project objective in its own right, alongside the scope, time and cost targets.

Why the other options are wrong:

  • A. A benefit is an outcome the project delivers, not how stakeholder satisfaction is managed.
  • B. An initiative is a piece of work the organization undertakes, not a measure the project manages toward.
  • D. A process is a set of activities, whereas satisfaction is a target to be achieved.

Question 133

Which cost is associated with nonconformance?

  • A. Liabilities
  • B. Inspections
  • C. Training
  • D. Equipment
Show answer and explanation ▾

Correct answer: A

The cost of nonconformance is money spent because of failures. Liabilities, along with warranty work and lost business, are external failure costs that arise when the customer finds the defect.

Why the other options are wrong:

  • B. Inspections are an appraisal cost, which is a cost of conformance.
  • C. Training is a prevention cost, which is a cost of conformance.
  • D. Equipment is a prevention cost, which is a cost of conformance.

Question 134

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

  • A. Historical relationships
  • B. Dependency determination
  • C. Bottom-up estimating
  • D. Rolling wave planning
Show answer and explanation ▾

Correct answer: D

Rolling wave planning is an iterative technique in which near-term work is planned in detail and future work is planned at a higher level. Work can therefore exist at different levels of detail depending on where it sits in the project life cycle.

Why the other options are wrong:

  • A. Historical relationships are used in parametric and analogous estimating, not in Define Activities.
  • B. Dependency determination is a technique of Sequence Activities.
  • C. Bottom-up estimating aggregates estimates of lower-level components and is not a Define Activities technique.

Question 135

An output of the Create WBS process is:

  • A. Scope baseline.
  • B. Change requests.
  • C. Accepted deliverables.
  • D. Variance analysis.
Show answer and explanation ▾

Correct answer: A

Create WBS produces the scope baseline, which is the approved version of the project scope statement, the WBS and the WBS dictionary. Its other output is project documents updates.

Why the other options are wrong:

  • B. Change requests are not an output of Create WBS.
  • C. Accepted deliverables are an output of Validate Scope.
  • D. Variance analysis is a technique used in controlling processes, not an output.

Question 136

A tool or technique used in the Control Procurements process is:

  • A. Expert judgment.
  • B. Performance reporting.
  • C. Bidder conferences.
  • D. Reserve analysis.
Show answer and explanation ▾

Correct answer: B

Performance reporting is a Control Procurements technique. Work performance data and reports supplied by sellers are evaluated against the agreement, giving management information on how effectively the seller is meeting the contractual objectives.

Why the other options are wrong:

  • A. Expert judgment is not among the tools and techniques listed for Control Procurements.
  • C. Bidder conferences are a technique of Conduct Procurements.
  • D. Reserve analysis is used in estimating, budgeting and risk control, not in Control Procurements.

Question 137

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

  • A. Perform Quality Assurance
  • B. Direct and Manage Project Work
  • C. Monitor and Control Project Work
  • D. Perform Integrated Change Control
Show answer and explanation ▾

Correct answer: D

Configuration identification, configuration status accounting, and configuration verification and audit are the configuration management activities included in Perform Integrated Change Control, the process that reviews, approves and manages changes to deliverables, documents and the project management plan.

Why the other options are wrong:

  • A. Perform Quality Assurance audits quality requirements and quality control results.
  • B. Direct and Manage Project Work performs the planned work and implements approved changes.
  • C. Monitor and Control Project Work tracks and reports progress against the plan.

Question 138

Which tool or technique is used in the Estimate Costs process?

  • A. Acquisition
  • B. Earned value management
  • C. Vendor bid analysis
  • D. Forecasting
Show answer and explanation ▾

Correct answer: C

Vendor bid analysis is an Estimate Costs technique. It examines what the project should cost based on the responsive bids received from qualified vendors.

Why the other options are wrong:

  • A. Acquisition is a technique of Acquire Project Team.
  • B. Earned value management is a technique of Control Costs.
  • D. Forecasting is a technique of Control Costs.

Question 139

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

  • A. Supportive
  • B. Directive
  • C. Controlling
  • D. Instructive
Show answer and explanation ▾

Correct answer: A

A supportive PMO plays a consultative role, supplying templates, best practices, training, access to information and lessons learned from other projects. It acts as a project repository and has a low degree of control.

Why the other options are wrong:

  • B. A directive PMO takes control by managing the projects directly.
  • C. A controlling PMO provides support and also requires compliance with its frameworks, tools and governance.
  • D. Instructive is not one of the PMO types.

Question 140

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

  • A. Project document updates
  • B. Activity list
  • C. Activity attributes
  • D. Project calendars
Show answer and explanation ▾

Correct answer: C

Activity attributes extend the description of each activity by identifying the multiple components associated with it, such as the activity identifier, predecessors, successors, leads and lags, resource requirements, constraints and assumptions.

Why the other options are wrong:

  • A. Project document updates are not an output of Define Activities.
  • B. The activity list names the activities and gives a scope of work description, without the detailed components.
  • D. Project calendars identify working days and shifts and are an output of Develop Schedule.

Question 141

An input to the

Identify Stakeholders process is:

  • A. The project management plan.
  • B. The stakeholder register.
  • C. Procurement documents.
  • D. Stakeholder analysis.
Show answer and explanation ▾

Correct answer: C

The inputs to Identify Stakeholders are the project charter, procurement documents, enterprise environmental factors and organizational process assets. When a project results from a procurement or an established contract, the parties to that contract are important stakeholders.

Why the other options are wrong:

  • A. The project management plan does not exist yet when stakeholders are first identified during initiation.
  • B. The stakeholder register is the output of Identify Stakeholders.
  • D. Stakeholder analysis is a technique of Identify Stakeholders.

Question 142

Identify Risks is part of which Process Group?

  • A. Planning
  • B. Executing
  • C. Closing
  • D. Initiating
Show answer and explanation ▾

Correct answer: A

Identify Risks belongs to the Planning Process Group, together with Plan Risk Management, the two risk analysis processes and Plan Risk Responses. Control Risks is the only risk process outside planning.

Why the other options are wrong:

  • B. No Project Risk Management process belongs to the Executing Process Group.
  • C. No Project Risk Management process belongs to the Closing Process Group.
  • D. The Initiating Process Group contains only Develop Project Charter and Identify Stakeholders.

Question 143

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

  • A. Force/direct
  • B. Withdraw/avoid
  • C. Compromise/reconcile
  • D. Collaborate/problem solve
Show answer and explanation ▾

Correct answer: C

Compromise/reconcile searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict. Each side gives something up.

Why the other options are wrong:

  • A. Force/direct pushes one viewpoint at the expense of others.
  • B. Withdraw/avoid retreats from the conflict or postpones the issue.
  • D. Collaborate/problem solve combines multiple viewpoints to reach consensus and a lasting commitment.

Question 144

Which tool or technique is used in the

Perform Integrated Change Control process?

  • A. Decomposition
  • B. Modeling techniques
  • C. Resource optimization
  • D. Meetings
Show answer and explanation ▾

Correct answer: D

The tools and techniques of Perform Integrated Change Control are expert judgment, meetings and change control tools. The meetings are usually change control meetings, where the change control board reviews change requests and approves or rejects them.

Why the other options are wrong:

  • A. Decomposition is used in Create WBS and Define Activities.
  • B. Modeling techniques are used in Develop Schedule and Control Schedule.
  • C. Resource optimization techniques are used in Develop Schedule and Control Schedule.

Question 145

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

  • A. Start-to-start (SS).
  • B. Start-to-finish (SF).
  • C. Finish-to-start (FS).
  • D. Finish-to-finish (FF).
Show answer and explanation ▾

Correct answer: C

Finish-to-start (FS) is the logical relationship in which a successor activity cannot start until a predecessor activity has finished. It is the most commonly used relationship in the precedence diagramming method.

Why the other options are wrong:

  • A. Start-to-start means the successor cannot start until the predecessor has started.
  • B. Start-to-finish means the successor cannot finish until the predecessor has started.
  • D. Finish-to-finish means the successor cannot finish until the predecessor has finished.

Question 146

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

  • A. Cost Plus Incentive Fee (CPIF)
  • B. Fixed Price Incentive Fee (FPIF)
  • C. Cost Pius Award Re (CPAF)
  • D. Time and Material (T&M)
Show answer and explanation ▾

Correct answer: B

A Fixed Price Incentive Fee contract gives the buyer and seller some flexibility in that it allows for deviation from performance, with financial incentives tied to achieving agreed metrics such as cost, schedule or technical performance. A price ceiling is set.

Why the other options are wrong:

  • A. Under Cost Plus Incentive Fee the seller is reimbursed for allowable costs and earns a fee based on performance objectives.
  • C. Under Cost Plus Award Fee the fee is earned on the buyer's subjective judgment of performance.
  • D. Time and Material contracts pay agreed rates for labor and materials and carry no performance incentive.

Question 147

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

  • A. $50
  • B. $100
  • C. $125
  • D. $175
Show answer and explanation ▾

Correct answer: C

When the remaining work is expected to be done at the budgeted rate, EAC = AC + (BAC - EV). Here that is $50 + ($100 - $25) = $125.

Why the other options are wrong:

  • A. $50 is only the actual cost spent so far.
  • B. $100 is the budget at completion, which ignores the overspend to date.
  • D. $175 does not result from applying the EAC formula to these figures.

Question 148

The business needs, assumptions, and constraints and the understanding of the customers’ needs and high-level requirements are documented in the:

  • A. Project management plan.
  • B. Project charter.
  • C. Work breakdown structure.
  • D. Stakeholder register.
Show answer and explanation ▾

Correct answer: B

The project charter documents the business needs, assumptions, constraints, the understanding of the customer's needs and high-level requirements, and the new product, service or result the project is intended to satisfy. It also formally authorizes the project.

Why the other options are wrong:

  • A. The project management plan describes how the project will be executed, monitored and controlled.
  • C. The work breakdown structure decomposes the total scope of work into deliverables.
  • D. The stakeholder register records identification, assessment and classification details of stakeholders.

Question 149

Which Process Group and Knowledge Area include the Sequence Activities process?

  • A. Executing Process Group and Project Time Management
  • B. Executing Process Group and Project Cost Management
  • C. Planning Process Group and Project Time Management
  • D. Planning Process Group and Project Cost Management
Show answer and explanation ▾

Correct answer: C

Sequence Activities identifies and documents the relationships among project activities. It is a Project Time Management process and, like all schedule development work before control, it sits in the Planning Process Group.

Why the other options are wrong:

  • A. Project Time Management has no processes in the Executing Process Group.
  • B. Sequence Activities is not an executing process and is not part of Project Cost Management.
  • D. Sequence Activities is a planning process, but it belongs to Project Time Management.

Question 150

In the Plan Stakeholder Management process, expert judgment is used to:

  • A. Provide information needed to plan appropriate ways to engage project stakeholders.
  • B. Ensure comprehensive identification and listing of new stakeholders.
  • C. Analyze the information needed to develop the project scope statement.
  • D. Decide the level of engagement of the stakeholders at each required stage.
Show answer and explanation ▾

Correct answer: D

In Plan Stakeholder Management, the project manager applies expert judgment to decide the level of engagement required from each stakeholder at each stage of the project. Engagement needs change as the project moves through its life cycle.

Why the other options are wrong:

  • A. Providing the information needed to plan engagement is the role of the stakeholder register, an input.
  • B. Identifying and listing stakeholders is the use of expert judgment in Identify Stakeholders.
  • C. Developing the project scope statement belongs to Define Scope.

Question 151

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

  • A. Analysis
  • B. Appetite
  • C. Tolerance
  • D. Response
Show answer and explanation ▾

Correct answer: C

Risk tolerance is the degree, amount or volume of risk that an organization or individual will withstand. It is one of the three elements of risk attitude, with risk appetite and risk threshold.

Why the other options are wrong:

  • A. Risk analysis is the assessment of identified risks, not a measure of how much risk is withstood.
  • B. Risk appetite is the degree of uncertainty an entity is willing to take on in anticipation of a reward.
  • D. A risk response is an action taken to address a risk.

Question 152

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

  • A. Verified deliverables.
  • B. Validated deliverables.
  • C. Acceptance criteria.
  • D. Activity resource requirements.
Show answer and explanation ▾

Correct answer: A

Verified deliverables are project deliverables that have been completed and checked for correctness through the Control Quality process. They are then an input to Validate Scope, where the customer formally accepts them.

Why the other options are wrong:

  • B. Validated deliverables is not the term for the Control Quality output; customer acceptance produces accepted deliverables.
  • C. Acceptance criteria are the conditions a deliverable must meet before it is accepted.
  • D. Activity resource requirements identify the resources needed for each activity.

Question 153

An output of the

Perform Integrated Change Control process is:

  • A. Deliverables.
  • B. Validated changes.
  • C. The change log.
  • D. The requirements traceability matrix.
Show answer and explanation ▾

Correct answer: C

Perform Integrated Change Control produces approved change requests, the change log, project management plan updates and project documents updates. The change log records every change raised during the project, including those that were rejected.

Why the other options are wrong:

  • A. Deliverables are an output of Direct and Manage Project Work.
  • B. Validated changes are an output of Control Quality.
  • D. The requirements traceability matrix is an output of Collect Requirements.

Question 154

During which process does the project team receive bids and proposals?

  • A. Conduct Procurements
  • B. Plan Procurements
  • C. Estimate Costs
  • D. Control Budget
Show answer and explanation ▾

Correct answer: A

Conduct Procurements is the process of obtaining seller responses, selecting a seller and awarding a contract. During this process the team receives bids or proposals and applies the selection criteria to choose qualified sellers.

Why the other options are wrong:

  • B. Planning procurements documents purchasing decisions and identifies potential sellers before any bids arrive.
  • C. Estimate Costs develops an approximation of the money needed for project activities.
  • D. Control Budget is not a project management process.

Question 155

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

  • A. Validate Scope.
  • B. Plan Scope Management.
  • C. Control Scope.
  • D. Define Scope.
Show answer and explanation ▾

Correct answer: C

Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline. It keeps the scope baseline maintained throughout the project.

Why the other options are wrong:

  • A. Validate Scope formalizes acceptance of the completed project deliverables.
  • B. Plan Scope Management creates the plan for how scope will be defined, validated and controlled.
  • D. Define Scope develops the detailed description of the project and product.

Question 156

Which output is the approved version of the time-phased project budget?

  • A. Resource calendar
  • B. Scope baseline
  • C. Trend analysis
  • D. Cost baseline
Show answer and explanation ▾

Correct answer: D

The cost baseline is the approved version of the time-phased project budget, excluding management reserves. It can be changed only through formal change control and is the basis for comparison with actual results.

Why the other options are wrong:

  • A. A resource calendar shows when specific resources are available.
  • B. The scope baseline is the approved scope statement, WBS and WBS dictionary.
  • C. Trend analysis is a technique for examining performance over time, not an output.

Question 157

The purpose of the Project Communications Management Knowledge Area is to:

  • A. Monitor and control communications throughout the entire project life cycle.
  • B. Maintain an optimal flow of information among all project participants.
  • C. Develop an appropriate approach for project communications.
  • D. Ensure timely and appropriate collection of project information.
Show answer and explanation ▾

Correct answer: D

Project Communications Management includes the processes required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring and ultimate disposition of project information.

Why the other options are wrong:

  • A. Monitoring and controlling communications is the purpose of the single process Control Communications.
  • B. Keeping an optimal information flow among participants is the benefit of Control Communications, not the purpose of the Knowledge Area.
  • C. Developing an approach for project communications is the purpose of Plan Communications Management.

Question 158

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:

  • A. Level of control.
  • B. Communication channels.
  • C. Scope.
  • D. Strategic alignment.
Show answer and explanation ▾

Correct answer: A

Initiating processes may be performed at the organizational, program or portfolio level and would then be outside of the project's level of control. For example, a business need may be documented in portfolio management before the project begins.

Why the other options are wrong:

  • B. Communication channels describe the paths between stakeholders, not where initiating work is carried out.
  • C. Scope describes the work of the project, not the level at which initiating processes are controlled.
  • D. Initiating processes are meant to align the project with the organization's strategy.

Question 159

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project.

Which item did this project create?

  • A. Result
  • B. Product
  • C. Service
  • D. Improvement
Show answer and explanation ▾

Correct answer: A

A project can create a result, such as an outcome or document. A research project that develops knowledge used to determine whether a trend exists produces a result.

Why the other options are wrong:

  • B. A product is a component, enhancement or end item, not a research finding.
  • C. A service is a capability to perform a function, such as a business function that supports production.
  • D. An improvement changes an existing product or service line, for example by reducing defects.

Question 160

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

  • A. Salience
  • B. Influence/impact
  • C. Power/interest
  • D. Power/influence
Show answer and explanation ▾

Correct answer: A

The salience model describes classes of stakeholders based on their power (ability to impose their will), urgency (need for immediate attention) and legitimacy (their involvement is appropriate).

Why the other options are wrong:

  • B. The influence/impact grid groups stakeholders by active involvement and ability to effect changes to the project.
  • C. The power/interest grid groups stakeholders by level of authority and level of concern about project outcomes.
  • D. The power/influence grid groups stakeholders by level of authority and active involvement.

Question 161

Through whom do project managers accomplish work?

  • A. Consultants and stakeholders
  • B. Stakeholders and functional managers
  • C. Project team members and consultants
  • D. Project team members and stakeholders
Show answer and explanation ▾

Correct answer: D

Project managers accomplish work through the project team and other stakeholders. That is why interpersonal skills such as leadership, communication and influencing matter as much as technical skills.

Why the other options are wrong:

  • A. Consultants may contribute, but this pair leaves out the project team that performs the work.
  • B. Functional managers supply resources, but this pair leaves out the project team.
  • C. This pair leaves out the wider stakeholders, and consultants are not a required part of a project.

Question 162

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

  • A. Checksheets
  • B. Histograms
  • C. Flowcharts
  • D. Control charts
Show answer and explanation ▾

Correct answer: C

Flowcharts may prove useful in understanding and estimating the cost of quality in a process. Using the workflow branching logic and its relative frequencies, the expected monetary value of conformance and nonconformance work can be estimated.

Why the other options are wrong:

  • A. Checksheets are used to organize facts while gathering data on a potential quality problem.
  • B. Histograms show the central tendency, dispersion and shape of a distribution.
  • D. Control charts determine whether a process is stable or has predictable performance.

Question 163

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

  • A. Smooth/accommodate
  • B. Withdraw/avoid
  • C. Compromise/reconcile
  • D. Force/direct
Show answer and explanation ▾

Correct answer: B

Withdraw/avoid means retreating from an actual or potential conflict situation, or postponing the issue to be better prepared or to be resolved by others.

Why the other options are wrong:

  • A. Smooth/accommodate emphasizes areas of agreement and concedes one's position to maintain harmony.
  • C. Compromise/reconcile looks for solutions that bring some degree of satisfaction to all parties.
  • D. Force/direct pushes one viewpoint at the expense of others.

Question 164

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

  • A. Activity cost estimates
  • B. Earned value management
  • C. Cost management plan
  • D. Cost baseline
Show answer and explanation ▾

Correct answer: A

Activity cost estimates are quantitative assessments of the probable costs required to complete project work. They are the main output of Estimate Costs and cover all resources applied to the estimate, such as labor, materials, equipment and contingency.

Why the other options are wrong:

  • B. Earned value management is a technique for measuring performance, not an output.
  • C. The cost management plan describes how costs will be planned, structured and controlled.
  • D. The cost baseline is the approved time-phased budget, built from the estimates.

Question 165

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

  • A. ends.
  • B. begins.
  • C. delays.
  • D. deviates.
Show answer and explanation ▾

Correct answer: A

Planning cannot continue indefinitely. While the team gathers feedback and refines the project documents, procedures set by the organization dictate when the initial planning effort ends.

Why the other options are wrong:

  • B. The start of planning follows from the approval of the project charter, not from these procedures.
  • C. Organizational procedures do not exist to dictate delays in planning.
  • D. Deviations are handled through change control, not dictated by planning procedures.

Question 166

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

  • A. Plan Stakeholder Management
  • B. Identify Stakeholders
  • C. Manage Stakeholder Engagement
  • D. Control Stakeholder Engagement
Show answer and explanation ▾

Correct answer: A

Plan Stakeholder Management develops engagement strategies based on an analysis of stakeholder needs, interests and potential impact on the project. A need that surfaces unexpectedly points to a gap in that analysis.

Why the other options are wrong:

  • B. Identify Stakeholders names the people affected by the project, and this stakeholder was already known.
  • C. Manage Stakeholder Engagement works with stakeholders to meet needs that have already been planned for.
  • D. Control Stakeholder Engagement monitors relationships and adjusts strategies after they are in place.

Question 167

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

  • A. organizational skills
  • B. technical skills
  • C. communication skills
  • D. hard skills
Show answer and explanation ▾

Correct answer: C

Listening actively, persuading a person, team or organization to act, motivating to provide encouragement, and summarizing, recapping and identifying next steps are all communication skills that general management and project management share.

Why the other options are wrong:

  • A. Organizational skills concern arranging work and resources, not listening, persuading and summarizing.
  • B. Technical skills relate to the specialized work of the project.
  • D. The skills listed are interpersonal soft skills, not hard skills.

Question 168

Which tools or techniques are used during the Close Project or Phase process?

  • A. Reserve analysis and expert judgment
  • B. Facilitation techniques and meetings
  • C. Expert judgment and analytical techniques
  • D. Performance reviews and meetings
Show answer and explanation ▾

Correct answer: C

The tools and techniques of Close Project or Phase are expert judgment, analytical techniques and meetings. Analytical techniques such as regression analysis and trend analysis support the closure review.

Why the other options are wrong:

  • A. Reserve analysis is not a technique of Close Project or Phase.
  • B. Facilitation techniques are not a technique of Close Project or Phase.
  • D. Performance reviews are not a technique of Close Project or Phase.

Question 169

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

  • A. improvement
  • B. program
  • C. result
  • D. portfolio
Show answer and explanation ▾

Correct answer: A

A project can create an improvement in existing product or service lines. A Six Sigma project undertaken to reduce defects is the standard example.

Why the other options are wrong:

  • B. A program is a group of related projects managed in a coordinated way, not something one project creates.
  • C. A result is an outcome or document, such as research findings.
  • D. A portfolio is a collection of projects and programs managed to meet strategic objectives.

Question 170

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

  • A. management
  • B. response
  • C. tolerance
  • D. appetite
Show answer and explanation ▾

Correct answer: D

Risk appetite is the degree of uncertainty an entity is willing to take on in anticipation of a reward. It is one of the three elements of risk attitude, with risk tolerance and risk threshold.

Why the other options are wrong:

  • A. Risk management is the set of processes for planning, identifying, analyzing and responding to risk.
  • B. A risk response is an action taken to address a risk.
  • C. Risk tolerance is the degree, amount or volume of risk that will be withstood.

Question 171

The zero duration of milestones in project planning occurs because milestones:

  • A. Are unpredictable and challenge the Plan Schedule Management process.
  • B. Occur at random times in the project plans.
  • C. Represent a moment in time such as a significant project point or event.
  • D. Represent both significant and insignificant points in the project and are difficult to anticipate.
Show answer and explanation ▾

Correct answer: C

A milestone is a significant point or event in a project. Milestones are similar to schedule activities but have zero duration because they represent a moment in time.

Why the other options are wrong:

  • A. Milestones are planned points in the schedule and are not unpredictable.
  • B. Milestones are placed deliberately, not at random times.
  • D. Milestones mark only significant points and are defined in advance.

Question 172

An example of a group decision-making technique is:

  • A. nominal group technique
  • B. majority
  • C. affinity diagram
  • D. multi-criteria decision analysis
Show answer and explanation ▾

Correct answer: B

Group decision-making techniques are the methods a group uses to reach a decision: unanimity, majority, plurality and dictatorship. A majority decision is reached with support from more than 50 percent of the members.

Why the other options are wrong:

  • A. Nominal group technique is a group creativity technique.
  • C. An affinity diagram is a group creativity technique for sorting ideas into groups.
  • D. Multi-criteria decision analysis is a group creativity technique that uses a decision matrix.

Question 173

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

  • A. Procurement documents
  • B. Inspection and audits
  • C. Estimate budget
  • D. Risk register
Show answer and explanation ▾

Correct answer: B

Inspections and audits are required by the buyer and supported by the seller as specified in the procurement contract. They can be conducted during execution of the project to verify compliance in the seller's work processes or deliverables.

Why the other options are wrong:

  • A. Procurement documents are an input to Control Procurements, not a technique.
  • C. Estimate budget is not a tool or technique of Control Procurements.
  • D. The risk register is a project document, not a technique for verifying compliance.

Question 174

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

  • A. Influencing
  • B. Motivation
  • C. Negotiation
  • D. Trust building
Show answer and explanation ▾

Correct answer: B

Motivating a team means creating an environment that meets project objectives while providing maximum satisfaction for what people value most. Those values include job satisfaction, challenging work, a sense of accomplishment and sufficient financial compensation.

Why the other options are wrong:

  • A. Influencing is about sharing power and persuading others to cooperate toward common goals.
  • C. Negotiation is conferring with parties of shared or opposed interests to reach an agreement.
  • D. Trust building concerns the confidence team members and stakeholders have in one another.

Question 175

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

  • A. recognition and rewards
  • B. compliance
  • C. staff acquisition
  • D. training needs
Show answer and explanation ▾

Correct answer: D

Training needs is the part of the staffing management plan that covers developing team members who lack required competencies. It can include ways to help team members obtain certifications that support their ability to benefit the project.

Why the other options are wrong:

  • A. Recognition and rewards sets the criteria and system for rewarding desired behavior.
  • B. Compliance covers strategies for meeting regulations, union contracts and human resource policies.
  • C. Staff acquisition covers how and from where team members will be obtained.

Question 176

Stakeholders can be identified in later stages of the project because the

Identify Stakeholders process should be:

  • A. Continuous
  • B. Discrete
  • C. Regulated
  • D. Arbitrary
Show answer and explanation ▾

Correct answer: A

Stakeholder identification is a continuous process throughout the project life cycle. New stakeholders can appear as the project progresses, so the stakeholder register is reviewed and updated regularly.

Why the other options are wrong:

  • B. A discrete, one-time exercise would miss stakeholders who appear later.
  • C. Regulated describes external rules, not how often stakeholders are identified.
  • D. Stakeholder identification is systematic, not arbitrary.

Question 177

A graphic display of project team members and their reporting relationships is known as a:

  • A. Resource calendar.
  • B. Project organization chart.
  • C. Resource breakdown structure (RBS).
  • D. Responsibility assignment matrix (RAM).
Show answer and explanation ▾

Correct answer: B

A project organization chart is a graphic display of project team members and their reporting relationships. It is part of the human resource management plan and can be formal or informal, detailed or broadly framed.

Why the other options are wrong:

  • A. A resource calendar shows the time periods when resources are available.
  • C. A resource breakdown structure is a hierarchical list of resources by category and type.
  • D. A responsibility assignment matrix maps work packages or activities to the people responsible for them.

Question 178

Which item is a cost of conformance?

  • A. Training
  • B. Liabilities
  • C. Lost business
  • D. Scrap
Show answer and explanation ▾

Correct answer: A

The cost of conformance is money spent during the project to avoid failures. Training is a prevention cost, alongside documenting processes, equipment and time to do the work right.

Why the other options are wrong:

  • B. Liabilities are an external failure cost, which is a cost of nonconformance.
  • C. Lost business is an external failure cost, which is a cost of nonconformance.
  • D. Scrap is an internal failure cost, which is a cost of nonconformance.

Question 179

Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

  • A. Collaboration
  • B. Negotiation
  • C. Decision making
  • D. Influencing
Show answer and explanation ▾

Correct answer: D

Influencing is a strategy of sharing power and relying on interpersonal skills to get others to cooperate toward common goals. It matters most where the project manager has little direct authority over team members.

Why the other options are wrong:

  • A. Collaboration is a way of working together or resolving conflict, not the skill defined by sharing power to gain cooperation.
  • B. Negotiation is a strategy of conferring with parties of shared or opposed interests to reach an agreement.
  • C. Decision making is the selection of a course of action from the alternatives.

Question 180

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

  • A. Estimate Costs
  • B. Control Costs
  • C. Plan Cost Management
  • D. Determine Budget
Show answer and explanation ▾

Correct answer: D

Determine Budget aggregates the estimated costs of individual activities or work packages to establish an authorized cost baseline. To do that it takes the activity cost estimates and the project schedule as inputs, so costs can be assigned to the periods in which they are incurred.

Why the other options are wrong:

  • A. Estimate Costs produces the activity cost estimates as an output, it does not take them as an input.
  • B. Control Costs works from the cost baseline and funding requirements, not from the activity cost estimates.
  • C. Plan Cost Management creates the cost management plan before any activity cost estimates exist.

Question 181

In project management, a temporary project can be:

  • A. Completed without planning
  • B. A routine business process
  • C. Long in duration
  • D. Ongoing to produce goods
Show answer and explanation ▾

Correct answer: C

Temporary means a project has a definite beginning and end. It does not mean the project is short, so a temporary project can still run for a long time.

Why the other options are wrong:

  • A. Every project needs planning, however temporary it is.
  • B. A routine business process is ongoing operations work, not a project.
  • D. Ongoing production of goods is operations, which has no defined end.

Question 182

Which document in the project management plan can be updated in the Plan Procurement Management process?

  • A. Budget estimates
  • B. Risk matrix
  • C. Requirements documentation
  • D. Procurement documents
Show answer and explanation ▾

Correct answer: C

Plan Procurement Management can lead to updates of the requirements documentation, along with the requirements traceability matrix and the risk register, because procurement decisions can add or change contractual and legal requirements.

Why the other options are wrong:

  • A. Budget estimates are not listed as a document updated by Plan Procurement Management.
  • B. A risk matrix is not the document this process updates.
  • D. Procurement documents are a separate output created by the process, not an existing document that it updates.

Question 183

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

  • A. Uniform
  • B. Continuous
  • C. Discrete
  • D. Linear
Show answer and explanation ▾

Correct answer: C

A discrete distribution represents uncertain events that have a limited number of separate outcomes, such as a test passing or failing, or the possible scenarios on the branches of a decision tree.

Why the other options are wrong:

  • A. A uniform distribution is used when no value in a range is more likely than another.
  • B. A continuous distribution represents values such as durations and costs that can fall anywhere in a range.
  • D. Linear is not the distribution type used for test outcomes or decision tree scenarios.

Question 184

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

  • A. Update
  • B. Preventive action
  • C. Defect repair
  • D. Corrective action
Show answer and explanation ▾

Correct answer: D

A corrective action is an intentional activity that realigns the performance of the project work with the project management plan. It responds to a variance that has already happened.

Why the other options are wrong:

  • A. An update changes a formally controlled document or plan, it does not realign performance.
  • B. A preventive action makes sure future performance stays aligned with the plan.
  • C. A defect repair modifies a nonconforming product or product component.

Question 185

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

  • A. 100
  • B. 120
  • C. 1,000
  • D. 1,200
Show answer and explanation ▾

Correct answer: A

Parametric estimating multiplies or divides the quantity of work by a known rate. Here 12,000 units divided by 120 units per hour gives 100 hours.

Why the other options are wrong:

  • B. 120 is the hourly production rate, not the number of hours needed.
  • C. 1,000 hours would produce 120,000 units at this rate.
  • D. 1,200 hours would produce 144,000 units at this rate.

Question 186

Which stakeholder approves a project's result?

  • A. Customer
  • B. Sponsor
  • C. Seller
  • D. Functional manager
Show answer and explanation ▾

Correct answer: A

The customer is the person or organization that will approve and manage the project's product, service, or result, so acceptance of the result comes from the customer.

Why the other options are wrong:

  • B. The sponsor provides resources and support for the project and is not the stakeholder named as approving the result here.
  • C. The seller provides components or services to the project under a contract.
  • D. The functional manager manages a business department and its resources.

Question 187

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

  • A. Collect Requirements
  • B. Plan Scope Management
  • C. Define Scope
  • D. Define Activities
Show answer and explanation ▾

Correct answer: A

Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. It provides the basis for defining and managing the project scope.

Why the other options are wrong:

  • B. Plan Scope Management creates the plan for how scope will be defined, validated, and controlled.
  • C. Define Scope develops a detailed description of the project and product.
  • D. Define Activities identifies the specific actions needed to produce the deliverables.

Question 188

Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

  • A. Available organizational assets
  • B. Project staff assignments
  • C. Interpersonal skills
  • D. Enterprise environmental factors
Show answer and explanation ▾

Correct answer: A

Plan Communications Management develops an appropriate approach and plan for project communications based on stakeholders' information needs and requirements, and the available organizational assets.

Why the other options are wrong:

  • B. Project staff assignments are an output of acquiring the team, not the basis of the communications approach.
  • C. Interpersonal skills are a technique for managing people, not part of this definition.
  • D. Enterprise environmental factors are not what the definition of this process names as the basis for the communications approach.

Question 189

Perform Integrated Change Control is the process of:

  • A. Reviewing, approving, and managing all change requests
  • B. Facilitating change management, manuals, or automation tools
  • C. Comparing actual results with planned results in order to expand or change a project
  • D. Documenting changes according to the change control system by the change control board
Show answer and explanation ▾

Correct answer: A

Perform Integrated Change Control reviews all change requests, approves or rejects them, and manages the changes to deliverables, organizational process assets, project documents, and the project management plan, then communicates the decisions.

Why the other options are wrong:

  • B. Manuals and automation tools support change management, they do not define the process.
  • C. Comparing actual results with planned results is monitoring work, not the review and approval of change requests.
  • D. Documenting changes through the change control board does not define the process.

Question 190

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

  • A. lead
  • B. lag
  • C. mandatory dependency
  • D. internal dependency
Show answer and explanation ▾

Correct answer: A

A lead lets a successor activity start before its predecessor has finished. Preparing the walls while the paint is still being chosen moves the later work forward in time, which is what a lead does.

Why the other options are wrong:

  • B. A lag delays the successor activity, and nothing is delayed here.
  • C. A mandatory dependency is one required by contract or by the nature of the work, which does not describe overlapping these two activities.
  • D. An internal dependency describes a relationship under the team's control, not the overlap in timing.

Question 191

Which action is included in the Control Costs process?

  • A. Identify how the project costs will be planned, structured, and controlled
  • B. Determine policies, objectives, and responsibilities to satisfy stakeholder needs
  • C. Develop an approximation of the monetary resources needed to complete project activities
  • D. Monitor cost performance to isolate and understand variances from the approved cost baseline
Show answer and explanation ▾

Correct answer: D

Control Costs monitors the status of the project to update project costs and manage changes to the cost baseline. That includes monitoring cost performance to isolate and understand variances from the approved cost baseline.

Why the other options are wrong:

  • A. Identifying how costs will be planned, structured, and controlled is Plan Cost Management.
  • B. Determining quality policies, objectives, and responsibilities belongs to Project Quality Management.
  • C. Developing an approximation of the monetary resources needed is Estimate Costs.

Question 192

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

  • A. 0.03
  • B. 0.06
  • C. 0.10
  • D. 0.50
Show answer and explanation ▾

Correct answer: B

The risk rating is the probability multiplied by the impact. 0.30 multiplied by 0.20 equals 0.06.

Why the other options are wrong:

  • A. 0.03 would need a probability of 0.15 with this impact.
  • C. 0.10 is the difference between the two values, not their product.
  • D. 0.50 is the sum of the two values, not their product.

Question 193

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

  • A. a Knowledge Area
  • B. a Process Group
  • C. program management
  • D. portfolio management
Show answer and explanation ▾

Correct answer: A

A Knowledge Area represents a complete set of concepts, terms, and activities that make up a professional field, project management field, or area of specialization.

Why the other options are wrong:

  • B. A Process Group is a logical grouping of project management processes, such as Planning or Executing.
  • C. Program management coordinates related projects to obtain benefits.
  • D. Portfolio management selects and manages projects and programs to meet strategic objectives.

Question 194

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

  • A. exploit
  • B. avoid
  • C. mitigate
  • D. share
Show answer and explanation ▾

Correct answer: C

Mitigate is the risk response strategy in which the project team acts to reduce the probability of occurrence or the impact of a risk to within acceptable limits.

Why the other options are wrong:

  • A. Exploit is a strategy for opportunities that makes sure the opportunity happens.
  • B. Avoid eliminates the threat or protects the project from it completely.
  • D. Share allocates ownership of an opportunity to a third party.

Question 195

Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

  • A. Control Quality
  • B. Monitor and Control Project Work
  • C. Control Scope
  • D. Perform Integrated Change Control
Show answer and explanation ▾

Correct answer: D

Perform Integrated Change Control is conducted from project inception through completion and is the ultimate responsibility of the project manager. Change requests can arrive at any point in the project.

Why the other options are wrong:

  • A. Control Quality monitors and records the results of quality activities.
  • B. Monitor and Control Project Work tracks and reports progress and is not the process this description refers to.
  • C. Control Scope manages changes to the scope baseline only.

Question 196

Project management processes ensure the:

  • A. alignment with organizational strategy
  • B. efficient means to achieve the project objectives
  • C. performance of the project team
  • D. effective flow of the project throughout its life cycle
Show answer and explanation ▾

Correct answer: D

Project management processes ensure the effective flow of the project throughout its life cycle. They cover the tools and techniques used to apply the skills and capabilities of the Knowledge Areas.

Why the other options are wrong:

  • A. Alignment with organizational strategy is the concern of portfolio management and governance.
  • B. An efficient means to achieve objectives is not how the purpose of the processes is described.
  • C. Team performance is managed through the human resource processes, not ensured by the processes as a whole.

Question 197

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

  • A. Forecasting,
  • B. Brainstorming.
  • C. Historical databases.
  • D. Cost of quality.
Show answer and explanation ▾

Correct answer: D

Modern quality management approaches aim to be compatible with ISO standards and recognize the importance of customer satisfaction, prevention over inspection, continuous improvement, management responsibility, and cost of quality.

Why the other options are wrong:

  • A. Forecasting predicts future project performance and is not an element of the quality management approach.
  • B. Brainstorming is an idea-gathering technique.
  • C. Historical databases are organizational process assets.

Question 198

Which items are components of a project management plan?

  • A. Change management plan, process improvement plan, and scope management plan
  • B. Agreements, procurement management plan, and work performance information
  • C. Schedule management plan, project schedule, and resource calendars
  • D. Scope baseline, project statement of work, and requirements traceability matrix
Show answer and explanation ▾

Correct answer: A

The project management plan is made up of the baselines and the subsidiary plans. The change management plan, process improvement plan, and scope management plan are all subsidiary plans.

Why the other options are wrong:

  • B. Agreements and work performance information are not components of the project management plan.
  • C. The project schedule and resource calendars are project documents.
  • D. The project statement of work and the requirements traceability matrix are not components of the project management plan.

Question 199

Which project document is updated in the Control Stakeholder Engagement process?

  • A. Project reports
  • B. Issue log
  • C. Lessons learned documentation
  • D. Work performance information
Show answer and explanation ▾

Correct answer: B

Control Stakeholder Engagement updates two project documents: the stakeholder register and the issue log. The issue log is updated as new issues are identified and current ones are resolved.

Why the other options are wrong:

  • A. Project reports are organizational process assets, not project documents updated here.
  • C. Lessons learned documentation is an organizational process asset update.
  • D. Work performance information is a separate output of the process, not a project document update.

Question 200

A project manager should communicate to stakeholders about resolved project issues by updating the:

  • A. project records
  • B. project reports
  • C. stakeholder notifications
  • D. stakeholder register
Show answer and explanation ▾

Correct answer: C

Stakeholder notifications give stakeholders information about resolved issues, approved changes, and general project status. They are one of the organizational process assets updated when communications are managed.

Why the other options are wrong:

  • A. Project records hold correspondence, memos, and meeting minutes.
  • B. Project reports describe project status rather than notifying stakeholders of resolved issues.
  • D. The stakeholder register lists stakeholders and their details, it is not a communication to them.

Question 201

Which Project Time Management process includes bottom-up estimating as a tool or technique?

  • A. Estimate Activity Resources
  • B. Sequence Activities
  • C. Estimate Activity Durations
  • D. Develop Schedule
Show answer and explanation ▾

Correct answer: A

Estimate Activity Resources uses bottom-up estimating. When an activity cannot be estimated with confidence, its work is broken down in more detail, the resource needs of each piece are estimated, and the results are added up.

Why the other options are wrong:

  • B. Sequence Activities uses the precedence diagramming method, dependency determination, and leads and lags.
  • C. Estimate Activity Durations uses analogous, parametric, and three-point estimating.
  • D. Develop Schedule uses schedule network analysis techniques such as the critical path method.

Question 202

Progressively elaborating high-level information into detailed plans is performed by the:

  • A. project management office
  • B. portfolio manager
  • C. program manager
  • D. project manager
Show answer and explanation ▾

Correct answer: D

Project managers progressively elaborate high-level information into detailed plans throughout the project life cycle. Program managers plan at the program level and portfolio managers maintain processes for the whole portfolio.

Why the other options are wrong:

  • A. The project management office supports and standardizes project work, it does not elaborate the plans of a project.
  • B. The portfolio manager maintains processes and communication for the aggregate portfolio.
  • C. The program manager develops the overall program plan and high-level plans for its components.

Question 203

An input to the Control Quality process is:

  • A. Activity attributes
  • B. Quality control measurements
  • C. Enterprise environmental factors
  • D. Deliverables
Show answer and explanation ▾

Correct answer: D

Deliverables are an input to Control Quality. The process inspects them against the quality requirements, and the result is verified deliverables.

Why the other options are wrong:

  • A. Activity attributes are an input to the scheduling processes.
  • B. Quality control measurements are an output of Control Quality.
  • C. Enterprise environmental factors are not listed as an input to Control Quality.

Question 204

Which

Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

  • A. Inspection
  • B. Quality audits
  • C. Design of experiments
  • D. Root cause analysis
Show answer and explanation ▾

Correct answer: D

Root cause analysis is the technique used to identify a problem, discover the underlying causes that lead to it, and develop preventive actions.

Why the other options are wrong:

  • A. Inspection examines a work product to see whether it conforms to documented standards.
  • B. A quality audit checks whether project activities comply with policies, processes, and procedures.
  • C. Design of experiments identifies which factors influence specific variables of a product or process.

Question 205

A disadvantage associated with virtual teams is that they:

  • A. Require communication technology that is not readily available.
  • B. Create difficulties when including people with disabilities.
  • C. Often cannot accommodate teams that work different hours or shifts.
  • D. Create the possibility for misunderstandings to arise.
Show answer and explanation ▾

Correct answer: D

Virtual teams have little or no face-to-face time, which creates the possibility of misunderstandings, a feeling of isolation, and difficulty sharing knowledge and experience between team members.

Why the other options are wrong:

  • A. Virtual teams exist because communication technology such as email and video conferencing is readily available.
  • B. Virtual teams make it easier to include people with mobility limitations or disabilities.
  • C. Virtual teams can be formed from people who work different shifts, hours, or days.

Question 206

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

  • A. Performing
  • B. Storming
  • C. Norming
  • D. Forming
Show answer and explanation ▾

Correct answer: C

In the norming phase, team members begin to work together and adjust their work habits and behaviors to support the team, and they learn to trust each other.

Why the other options are wrong:

  • A. In performing, the team already works as a well-organized unit.
  • B. In storming, the team starts to address the work and conflict can arise.
  • D. In forming, team members meet and learn about the project and their roles.

Question 207

Which is an enterprise environmental factor?

  • A. Marketplace conditions
  • B. Policies and procedures
  • C. Project files from previous projects
  • D. Lessons learned from previous projects
Show answer and explanation ▾

Correct answer: A

Enterprise environmental factors are conditions outside the control of the project team that influence, constrain, or direct the project. Marketplace conditions are one of them.

Why the other options are wrong:

  • B. Policies and procedures are organizational process assets.
  • C. Project files from previous projects are organizational process assets.
  • D. Lessons learned from previous projects are organizational process assets.

Question 208

Project Stakeholder Management focuses on:

  • A. project staff assignments
  • B. project tea m acquisition
  • C. managing conflicting interests
  • D. communication methods
Show answer and explanation ▾

Correct answer: C

Project Stakeholder Management focuses on continuous communication with stakeholders to understand their needs and expectations, addressing issues as they occur, and managing conflicting interests.

Why the other options are wrong:

  • A. Project staff assignments belong to Project Human Resource Management.
  • B. Acquiring the project team belongs to Project Human Resource Management.
  • D. Communication methods are a tool of Project Communications Management.

Question 209

A risk that arises as a direct result of implementing a risk response is called a:

  • A. contingent risk
  • B. residual risk
  • C. potential risk
  • D. secondary risk
Show answer and explanation ▾

Correct answer: D

A secondary risk is a risk that arises as a direct result of implementing a risk response.

Why the other options are wrong:

  • A. Contingent risk is not the term for a risk created by a response.
  • B. A residual risk is the risk that remains after the planned responses have been taken.
  • C. Potential risk is not the term for a risk created by a response.

Question 210

The purpose of developing a project scope management plan is to:

  • A. Manage the timely completion of the project.
  • B. Ensure that the project includes all of the work required.
  • C. Make sure the project will satisfy the needs for which it was begun.
  • D. Reduce the risk of negative events in the project.
Show answer and explanation ▾

Correct answer: B

Project Scope Management ensures that the project includes all the work required, and only the work required, to complete the project successfully. The scope management plan describes how that scope will be defined, validated, and controlled.

Why the other options are wrong:

  • A. Timely completion of the project is the purpose of time management planning.
  • C. Satisfying the needs for which the project was undertaken is the purpose of quality management.
  • D. Reducing the likelihood and impact of negative events is the purpose of risk management.

Question 211

A tool and technique used in the Develop Project Charter process is:

  • A. change control tools
  • B. expert judgment
  • C. meetings
  • D. analytical techniques
Show answer and explanation ▾

Correct answer: B

Develop Project Charter uses two tools and techniques: expert judgment and facilitation techniques. Expert judgment is used to assess the inputs that go into the charter.

Why the other options are wrong:

  • A. Change control tools are used in Perform Integrated Change Control.
  • C. Meetings are a tool of later integration processes, not of Develop Project Charter.
  • D. Analytical techniques are not a tool or technique of Develop Project Charter.

Question 212

One of the key benefits of the Plan Human Resource Management process is that it:

  • A. outlines team selection guidelines and team member responsibilities.
  • B. establishes project roles and responsibilities.
  • C. improves teamwork, interpersonal skills, and competencies.
  • D. provides an accurate appraisal of team member performance.
Show answer and explanation ▾

Correct answer: B

Plan Human Resource Management establishes project roles and responsibilities, project organization charts, and the staffing management plan, including the timetable for staff acquisition and release.

Why the other options are wrong:

  • A. Team selection guidelines are not the stated benefit of this planning process.
  • C. Improved teamwork, interpersonal skills, and competencies are the benefit of Develop Project Team.
  • D. Appraising team member performance is part of Manage Project Team.

Question 213

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

  • A. Decomposition
  • B. Inspection
  • C. Project analysis
  • D. Document analysis
Show answer and explanation ▾

Correct answer: A

Decomposition divides and subdivides the project scope and project deliverables into smaller, more manageable parts. In Define Activities, it breaks the work packages down into the activities needed to produce them.

Why the other options are wrong:

  • B. Inspection examines work to verify that it meets requirements.
  • C. Project analysis is not a Define Activities technique.
  • D. Document analysis elicits requirements by reviewing existing documentation.

Question 214

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

  • A. Schedule network analysis
  • B. Reserve analysis
  • C. Alternative analysis
  • D. Variance analysis
Show answer and explanation ▾

Correct answer: D

Variance analysis determines the cause and degree of difference between the baseline and actual performance, so the team can decide whether corrective or preventive action is needed.

Why the other options are wrong:

  • A. Schedule network analysis generates the project schedule model.
  • B. Reserve analysis checks whether the remaining contingency and management reserves are adequate.
  • C. Alternative analysis compares different ways of carrying out the work.

Question 215

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

  • A. Work breakdown structure
  • B. Requirements document
  • C. Project charter
  • D. Project management plan
Show answer and explanation ▾

Correct answer: C

The project charter documents the project purpose or justification, measurable objectives and related success criteria, high-level requirements, a summary milestone schedule, and a summary budget. It formally authorizes the project.

Why the other options are wrong:

  • A. The work breakdown structure decomposes the project scope into deliverables and work packages.
  • B. A requirements document describes how individual requirements meet the business need.
  • D. The project management plan describes how the project will be executed, monitored, and controlled.

Question 216

In the Define Activities process, the schedule management plan is used to:

  • A. Capture the lessons learned from other projects for comparison.
  • B. Contain the standard activity list.
  • C. Document and support the project change requests.
  • D. Prescribe the level of detail needed to manage the work.
Show answer and explanation ▾

Correct answer: D

The schedule management plan is an input to Define Activities because it prescribes the level of detail necessary to manage the work.

Why the other options are wrong:

  • A. Lessons learned from other projects come from organizational process assets.
  • B. Standard activity lists come from organizational process assets, such as templates.
  • C. Documenting and supporting change requests is not the role of the schedule management plan in this process.

Question 217

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

  • A. risk management plan
  • B. human resource management plan
  • C. scope management plan
  • D. procurement management plan
Show answer and explanation ▾

Correct answer: D

Procurement planning includes the make-or-buy analysis, which shows when a deliverable is better obtained from outside the team. A procurement management plan would have identified the lack of expertise and time early and arranged for a seller to provide the deliverable.

Why the other options are wrong:

  • A. A risk management plan describes how risk activities are structured and performed, not how outside expertise is obtained.
  • B. A human resource management plan covers the roles and staffing of the team, not acquiring the deliverable from outside.
  • C. A scope management plan describes how scope is defined and controlled, not how work is sourced.

Question 218

A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

  • A. cultural differences of team members
  • B. possibility of communication misunderstandings
  • C. costs associated with travel
  • D. costs associated with technology
Show answer and explanation ▾

Correct answer: C

Virtual teams work with little or no time spent meeting face to face, so projects that would otherwise be ruled out by travel expenses can go ahead. The benefit is the reduction of travel costs.

Why the other options are wrong:

  • A. Cultural differences remain, and can be greater, when the team is spread across locations.
  • B. The possibility of misunderstandings increases with virtual teams.
  • D. Technology costs go up, because virtual teams depend on communication technology.

Question 219

Those who enter into a contractual agreement to provide services necessary for a project are:

  • A. buyers
  • B. sellers
  • C. business partners
  • D. product users
Show answer and explanation ▾

Correct answer: B

Sellers, also called vendors, suppliers, or contractors, are external companies that enter into a contractual agreement to provide components or services necessary for the project.

Why the other options are wrong:

  • A. Buyers acquire the products or services, they do not provide them.
  • C. Business partners have a special relationship with the enterprise, for example through certification, and provide specialized expertise.
  • D. Product users are the people who will use the project's product.

Question 220

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

  • A. influencing
  • B. leadership
  • C. motivation
  • D. coaching
Show answer and explanation ▾

Correct answer: A

Influencing is a strategy of sharing power and relying on interpersonal skills to get others to cooperate toward common goals. One of its guidelines is to lead by example and follow through with commitments.

Why the other options are wrong:

  • B. Leadership is focusing the efforts of a group toward a common goal, which is not the skill this guideline is listed under.
  • C. Motivation is about creating an environment that meets project objectives while giving people satisfaction in their work.
  • D. Coaching develops the team to higher levels of competency and performance.

Question 221

Which items are an output of the

Perform Integrated Change Control process?

  • A. Work performance reports
  • B. Accepted deliverables
  • C. Project management plan updates
  • D. Organizational process assets
Show answer and explanation ▾

Correct answer: C

The outputs of Perform Integrated Change Control are approved change requests, the change log, project management plan updates, and project documents updates.

Why the other options are wrong:

  • A. Work performance reports are an input to this process.
  • B. Accepted deliverables are an output of Validate Scope.
  • D. Organizational process assets are an input to this process.

Question 222

Which term describes an assessment of correctness?

  • A. Accuracy
  • B. Precision
  • C. Grade
  • D. Quality
Show answer and explanation ▾

Correct answer: A

Accuracy is an assessment of correctness: how close a measured value is to the true value. Precision is a measure of exactness.

Why the other options are wrong:

  • B. Precision is a measure of exactness, meaning how closely repeated measurements cluster.
  • C. Grade is a category assigned to deliverables that have the same functional use but different technical characteristics.
  • D. Quality is the degree to which a set of inherent characteristics fulfills requirements.

Question 223

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

  • A. Estimate Costs
  • B. Control Costs
  • C. Plan Cost Management
  • D. Determine Budget
Show answer and explanation ▾

Correct answer: D

Determine Budget produces the cost baseline and the project funding requirements, along with project documents updates. The cost baseline is the approved, time-phased project budget.

Why the other options are wrong:

  • A. Estimate Costs produces activity cost estimates and the basis of estimates.
  • B. Control Costs produces work performance information, cost forecasts, and change requests.
  • C. Plan Cost Management produces the cost management plan.

Question 224

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

  • A. Acquire Project Team.
  • B. Plan Human Resource Management.
  • C. Manage Project Team.
  • D. Develop Project Team.
Show answer and explanation ▾

Correct answer: A

Acquire Project Team is the process of confirming human resource availability and obtaining the team necessary to complete project activities.

Why the other options are wrong:

  • B. Plan Human Resource Management identifies and documents roles, responsibilities, and the staffing management plan.
  • C. Manage Project Team tracks team member performance, gives feedback, and resolves issues.
  • D. Develop Project Team improves competencies, team interaction, and the team environment.

Question 225

Success is measured by benefits realization for a:

  • A. strategic plan
  • B. project
  • C. portfolio
  • D. program
Show answer and explanation ▾

Correct answer: D

Program success is measured by the degree to which the program satisfies the needs and benefits for which it was undertaken. Programs exist to deliver benefits that the projects could not deliver if managed separately.

Why the other options are wrong:

  • A. A strategic plan sets direction, it is not measured by benefits realization.
  • B. Project success is measured by product and project quality, timeliness, budget compliance, and customer satisfaction.
  • C. Portfolio success is measured by the aggregate investment performance of the portfolio.

Question 226

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

  • A. Plan Cost Management
  • B. Plan Scope Management
  • C. Plan Stakeholder Management
  • D. Plan Schedule Management
Show answer and explanation ▾

Correct answer: C

Plan Stakeholder Management uses all organizational process assets as inputs, and the lessons learned database and historical information are of particular importance because they show how earlier stakeholder management plans worked.

Why the other options are wrong:

  • A. Plan Cost Management relies on financial control procedures and cost estimating policies.
  • B. Plan Scope Management is not the process described with this set of inputs.
  • D. Plan Schedule Management relies on schedule control tools, templates, and scheduling procedures.

Question 227

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

  • A. Quality assurance.
  • B. A stakeholder management plan.
  • C. Project team building.
  • D. Integrated change control.
Show answer and explanation ▾

Correct answer: D

Integrated change control requires every change request to be reviewed for its effect on the whole project before it is approved. That review would have exposed the adverse effect on the other deliverable before the change was made.

Why the other options are wrong:

  • A. Quality assurance audits processes and quality requirements, it does not review change requests.
  • B. A stakeholder management plan sets out how stakeholders are engaged, it does not assess the impact of a change.
  • C. Team building improves working relationships, it does not control changes to deliverables.

Question 228

The process of defining how the project scope will be validated and controlled is known as:

  • A. Define Scope.
  • B. Develop Project Management Plan.
  • C. Plan Scope Management.
  • D. Plan Quality Management.
Show answer and explanation ▾

Correct answer: C

Plan Scope Management creates a scope management plan that documents how the project scope will be defined, validated, and controlled.

Why the other options are wrong:

  • A. Define Scope develops a detailed description of the project and product.
  • B. Develop Project Management Plan integrates all the subsidiary plans into one plan.
  • D. Plan Quality Management identifies the quality requirements and standards for the project.

Question 229

Technical capability, past performance, and intellectual property rights are examples of:

  • A. performance measurement criteria
  • B. source selection criteria
  • C. product acceptance criteria
  • D. phase exit criteria
Show answer and explanation ▾

Correct answer: B

Source selection criteria are used to rate or score seller proposals. Examples include technical capability, past performance of sellers, and intellectual property rights.

Why the other options are wrong:

  • A. Performance measurement criteria assess how the project work is progressing, not which seller to choose.
  • C. Product acceptance criteria are the conditions a deliverable must meet before it is accepted.
  • D. Phase exit criteria are the conditions for closing one project phase and moving to the next.

Question 230

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

  • A. Earned value management.
  • B. Forecasting.
  • C. Critical chain methodology.
  • D. Critical path methodology.
Show answer and explanation ▾

Correct answer: A

Earned value management combines scope, schedule, and resource measurements to assess project performance and progress. It compares planned value, earned value, and actual cost.

Why the other options are wrong:

  • B. Forecasting predicts future performance from the information available at the time.
  • C. Critical chain methodology is a scheduling method that places buffers on the schedule path to allow for limited resources.
  • D. Critical path methodology calculates the longest path through the schedule network.

Question 231

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

  • A. Identify Risks
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis
Show answer and explanation ▾

Correct answer: C

Perform Qualitative Risk Analysis prioritizes risks by assessing their probability of occurrence and impact. It is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses.

Why the other options are wrong:

  • A. Identify Risks determines which risks may affect the project and documents them.
  • B. Plan Risk Management defines how risk management activities will be conducted.
  • D. Perform Quantitative Risk Analysis numerically analyzes the effect of risks and takes more time and effort.

Question 232

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

  • A. triangular distribution
  • B. tornado diagram
  • C. beta distribution
  • D. fishbone diagram
Show answer and explanation ▾

Correct answer: B

A tornado diagram is a special type of bar chart used in sensitivity analysis to compare the relative importance of the variables. The variables with the greatest effect appear as the longest bars at the top.

Why the other options are wrong:

  • A. A triangular distribution is a probability distribution built from three estimates.
  • C. A beta distribution is a probability distribution used in modeling and simulation.
  • D. A fishbone diagram traces a problem back to its possible causes.

Question 233

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

  • A. Strong
  • B. Weak
  • C. Managed
  • D. Balanced
Show answer and explanation ▾

Correct answer: D

In a balanced matrix the project manager works full time on the project but has only low to moderate authority, and the administrative staff supporting the project is part time. Power is shared between the project manager and the functional manager.

Why the other options are wrong:

  • A. A strong matrix gives the project manager moderate to high authority and full-time administrative staff.
  • B. A weak matrix has a part-time project manager with low authority, acting more as a coordinator or expediter.
  • C. Managed is not one of the matrix organization types.

Question 234

Project Scope Management is primarily concerned with:

  • A. Developing a detailed description of the project and product.
  • B. Determining how requirements will be analyzed, documented, and managed.
  • C. Defining and controlling what is and is not included in the project.
  • D. Formalizing acceptance of the completed project deliverables.
Show answer and explanation ▾

Correct answer: C

Project Scope Management includes the processes that ensure the project contains all the work required, and only the work required. Its main concern is defining and controlling what is and is not included in the project.

Why the other options are wrong:

  • A. Developing a detailed description of the project and product is the Define Scope process, one part of the knowledge area.
  • B. Determining how requirements are analyzed, documented and managed belongs to the requirements management plan.
  • D. Formalizing acceptance of completed deliverables is the Validate Scope process, one part of the knowledge area.

Question 235

For a stakeholder with low interest and high power, the project manager should:

  • A. Monitor the stakeholder.
  • B. Manage the stakeholder closely.
  • C. Keep the stakeholder satisfied.
  • D. Keep the stakeholder informed.
Show answer and explanation ▾

Correct answer: C

On the power/interest grid, a stakeholder with high power but low interest is kept satisfied. Their authority can affect the project, so their needs are met without loading them with detail they do not want.

Why the other options are wrong:

  • A. Monitoring with minimum effort applies to stakeholders with low power and low interest.
  • B. Managing closely applies to stakeholders with high power and high interest.
  • D. Keeping informed applies to stakeholders with low power and high interest.

Question 236

In a typical project, project managers spend most of their time:

  • A. Estimating
  • B. Scheduling
  • C. Controlling
  • D. Communicating
Show answer and explanation ▾

Correct answer: D

Project managers spend most of their time communicating with team members and other project stakeholders, both inside and outside the organization. Effective communication connects stakeholders with different backgrounds, expertise and interests.

Why the other options are wrong:

  • A. Estimating is done at specific points in planning and is not where most of the project manager's time goes.
  • B. Scheduling is one planning activity and does not take up most of the project manager's time.
  • C. Controlling is an important part of the role but takes less time than communicating.

Question 237

When closing a project or phase, part of the process may require the use of which type of analysis?

  • A. Reserve analysis
  • B. Regression analysis
  • C. Document analysis
  • D. Product analysis
Show answer and explanation ▾

Correct answer: B

Close Project or Phase uses analytical techniques, and regression analysis is one of them, together with trend analysis. They help the team examine project results and the relationships between variables as the work is closed out.

Why the other options are wrong:

  • A. Reserve analysis is used to size and monitor contingency and management reserves for cost and schedule.
  • C. Document analysis is used to draw requirements out of existing documentation.
  • D. Product analysis is used in Define Scope to turn a product description into tangible deliverables.

Question 238

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

  • A. Critical path method
  • B. Critical chain method
  • C. Resource leveling
  • D. Schedule network analysis
Show answer and explanation ▾

Correct answer: B

The critical chain method lets the project team place buffers on any project schedule path to account for limited resources and project uncertainties. It manages the buffers rather than the total float of individual activities.

Why the other options are wrong:

  • A. The critical path method calculates early and late dates without regard for resource limitations and adds no buffers.
  • C. Resource leveling adjusts start and finish dates to balance resource demand with supply.
  • D. Schedule network analysis is the general technique that generates the schedule model, not a buffer method.

Question 239

The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

  • A. work package
  • B. deliverable
  • C. milestone
  • D. activity
Show answer and explanation ▾

Correct answer: A

The work package is the lowest level of the work breakdown structure. It is the level at which cost and duration can be estimated and managed.

Why the other options are wrong:

  • B. A deliverable can sit at any level of the WBS and is decomposed further into work packages.
  • C. A milestone is a significant point or event in the schedule, not a WBS level.
  • D. Activities come from decomposing work packages in Define Activities and belong to the schedule, not the WBS.

Question 240

The scope management plan and scope baseline are contained in:

  • A. organizational process assets
  • B. a requirements traceability matrix
  • C. the project charter
  • D. the project management plan
Show answer and explanation ▾

Correct answer: D

The project management plan integrates all subsidiary plans and baselines. The scope management plan is one of its subsidiary plans and the scope baseline is one of its baselines.

Why the other options are wrong:

  • A. Organizational process assets hold policies, templates and historical information, not this project's plans and baselines.
  • B. A requirements traceability matrix links requirements to their origin and to the deliverables that satisfy them.
  • C. The project charter authorizes the project at a high level and is written before these plans exist.

Question 241

Which Manage Communications tool or technique focuses on identifying and managing barriers?

  • A. Communication methods
  • B. Information technology
  • C. Communication models
  • D. Information management systems
Show answer and explanation ▾

Correct answer: C

Communication models describe how a message travels from sender to receiver, including the noise that can distort it. Choosing a suitable model in Manage Communications includes identifying and managing those barriers.

Why the other options are wrong:

  • A. Communication methods concern how information is shared, such as interactive, push or pull communication.
  • B. Information technology is not the Manage Communications technique that deals with barriers.
  • D. Information management systems are the tools used to store and distribute project information.

Question 242

Outputs of the Control Communications process include:

  • A. expert judgment and change requests.
  • B. work performance information and change requests.
  • C. organizational process asset updates and an issue log.
  • D. project management plan updates and an issue log.
Show answer and explanation ▾

Correct answer: B

Control Communications produces work performance information and change requests, along with updates to the project management plan, project documents and organizational process assets.

Why the other options are wrong:

  • A. Expert judgment is a tool and technique of the process, not an output.
  • C. The issue log is an input to Control Communications, not an output.
  • D. The issue log is an input to Control Communications, not an output.

Question 243

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

  • A. Technical approach
  • B. Technical capability
  • C. Business size and type
  • D. Production capacity and interest
Show answer and explanation ▾

Correct answer: A

Technical approach is the source selection criterion that asks whether the seller's proposed technical methodologies, techniques, solutions and services meet the requirements in the procurement documents.

Why the other options are wrong:

  • B. Technical capability asks whether the seller has, or can acquire, the technical skills and knowledge needed.
  • C. Business size and type asks whether the seller's enterprise meets a required category, such as small or disadvantaged business.
  • D. Production capacity and interest asks whether the seller has the capacity and interest to meet potential future requirements.

Question 244

Stakeholder communication requirements should be included as a component of:

  • A. enterprise environmental factors
  • B. organizational process assets
  • C. the project management plan
  • D. the stakeholder register
Show answer and explanation ▾

Correct answer: C

Stakeholder communication requirements are recorded in the communications management plan, which is a component of the project management plan.

Why the other options are wrong:

  • A. Enterprise environmental factors are conditions outside the team's control that influence the project, not a place to record requirements.
  • B. Organizational process assets are the organization's templates, policies and lessons learned from past work.
  • D. The stakeholder register identifies stakeholders and their assessment and classification, and feeds communications planning.

Question 245

Which element does a project charter contain?

  • A. Management reserves
  • B. Work breakdown structure
  • C. Stakeholder list
  • D. Stakeholder register
Show answer and explanation ▾

Correct answer: C

The project charter documents high-level information about the project, including the project purpose, measurable objectives, high-level requirements and risks, a summary milestone schedule and budget, and a stakeholder list.

Why the other options are wrong:

  • A. Management reserves are part of the project budget and are set in cost planning, not in the charter.
  • B. The work breakdown structure is created later in Create WBS and forms part of the scope baseline.
  • D. The stakeholder register is produced by Identify Stakeholders, which uses the charter as an input.

Question 246

Every project creates a unique product, service, or result that may be:

  • A. tangible
  • B. targeted
  • C. organized
  • D. variable
Show answer and explanation ▾

Correct answer: A

A project is a temporary endeavor undertaken to create a unique product, service or result, and that outcome may be tangible or intangible.

Why the other options are wrong:

  • B. Targeted is not the term used to describe a project's product, service or result.
  • C. Organized is not the term used to describe a project's product, service or result.
  • D. Variable is not the term used to describe a project's product, service or result.

Question 247

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

  • A. project documents updates.
  • B. project management plan updates.
  • C. change requests.
  • D. work performance information.
Show answer and explanation ▾

Correct answer: D

Work performance information from Control Scope is correlated and contextualized information on how the project scope is performing against the scope baseline. It can include the categories of changes received, the scope variances identified and their causes.

Why the other options are wrong:

  • A. Project documents updates revise items such as requirements documentation and the traceability matrix.
  • B. Project management plan updates revise the baselines and subsidiary plans themselves.
  • C. Change requests ask for corrective action, preventive action, defect repair or enhancements.

Question 248

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

  • A. adaptive
  • B. reflexive
  • C. predictive
  • D. iterative
Show answer and explanation ▾

Correct answer: A

Adaptive life cycles, also called change-driven or agile, are intended to respond to high levels of change and ongoing stakeholder involvement. Work is done in short, fixed iterations and the scope is reprioritized as the project goes on.

Why the other options are wrong:

  • B. Reflexive is not a recognized project life cycle model.
  • C. Predictive life cycles fix scope, time and cost as early as possible and suit stable, well understood work.
  • D. Iterative life cycles repeat phases to refine the product but are not the model built for high change with continuous stakeholder involvement.

Question 249

Whose approval may be required for change requests after change control board (CCB) approval?

  • A. Functional managers
  • B. Business partners
  • C. Customers or sponsors
  • D. Subject matter experts
Show answer and explanation ▾

Correct answer: C

After the change control board approves a change request, customer or sponsor approval may still be required for certain changes, unless the customer or sponsor is already part of the board.

Why the other options are wrong:

  • A. Functional managers supply resources but do not give the further approval that follows a CCB decision.
  • B. Business partners have a relationship with the organization but do not approve change requests after the CCB.
  • D. Subject matter experts give advice that informs the decision but do not approve change requests.

Question 250

The primary benefit of the Plan Schedule Management process is that it:

  • A. provides guidance to identify time or schedule challenges within the project.
  • B. tightly links processes to create a seamless project schedule.
  • C. guides how the project schedule will be managed throughout the project.
  • D. creates an overview of all activities broken down into manageable subsections.
Show answer and explanation ▾

Correct answer: C

Plan Schedule Management sets the policies, procedures and documentation for planning, developing, managing, executing and controlling the schedule. Its benefit is guidance and direction on how the project schedule will be managed throughout the project.

Why the other options are wrong:

  • A. Identifying schedule challenges is not the stated benefit of this process.
  • B. Linking processes into a seamless schedule is not the stated benefit of this process.
  • D. Breaking the work down into manageable pieces describes decomposition, as in Create WBS and Define Activities.

Question 251

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

  • A. Influence/impact grid
  • B. Power/influence grid
  • C. Power/interest grid
  • D. Salience model
Show answer and explanation ▾

Correct answer: C

The power/interest grid groups stakeholders by their level of authority (power) and their level of concern (interest) about the project outcomes.

Why the other options are wrong:

  • A. The influence/impact grid groups stakeholders by their active involvement and their ability to effect changes to planning or execution.
  • B. The power/influence grid groups stakeholders by their level of authority and their active involvement in the project.
  • D. The salience model classifies stakeholders by power, urgency and legitimacy.

Question 252

Variance and trend analysis is a tool and technique used in which process?

  • A. Perform Qualitative Risk Analysis
  • B. Perform Quantitative Risk Analysis
  • C. Control Risks
  • D. Plan Risk Responses
Show answer and explanation ▾

Correct answer: C

Variance and trend analysis is a tool and technique of Control Risks. It compares planned results with actual results and reviews trends in performance, which can show the potential impact of threats or opportunities.

Why the other options are wrong:

  • A. Perform Qualitative Risk Analysis uses techniques such as probability and impact assessment and the probability and impact matrix.
  • B. Perform Quantitative Risk Analysis uses techniques such as sensitivity analysis, expected monetary value analysis and simulation.
  • D. Plan Risk Responses uses strategies for threats, strategies for opportunities and contingent response strategies.

Question 253

An intentional activity to modify a nonconforming product or product component is called:

  • A. defect repair
  • B. work repair
  • C. corrective action
  • D. preventive action
Show answer and explanation ▾

Correct answer: A

Defect repair is an intentional activity to modify a nonconforming product or product component so that it meets requirements.

Why the other options are wrong:

  • B. Work repair is not one of the defined types of change request.
  • C. Corrective action realigns the performance of the project work with the project management plan.
  • D. Preventive action ensures the future performance of the project work stays aligned with the project management plan.

Question 254

Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

  • A. Control chart
  • B. Flowchart
  • C. Checksheet
  • D. Pareto diagram
Show answer and explanation ▾

Correct answer: A

A control chart shows whether a process is stable and performing predictably. Its upper and lower specification limits are based on the requirements of the agreement and show the maximum and minimum values allowed.

Why the other options are wrong:

  • B. A flowchart maps the sequence of steps and branches in a process and has no limits on it.
  • C. A checksheet is a tally sheet used to collect data on attributes or defects.
  • D. A Pareto diagram ranks causes by frequency to show the vital few that produce most problems.

Question 255

Analytical techniques are a tool and technique of which process in Project Procurement Management?

  • A. Plan Procurement Management
  • B. Control Procurements
  • C. Conduct Procurements
  • D. Close Procurements
Show answer and explanation ▾

Correct answer: C

Conduct Procurements lists analytical techniques among its tools and techniques. They help the organization judge whether a seller is ready and able to provide the end state, and they look at past performance to find areas of higher risk.

Why the other options are wrong:

  • A. Plan Procurement Management relies on make-or-buy analysis, market research, expert judgment and meetings.
  • B. Control Procurements relies on tools such as the contract change control system, performance reviews, inspections and audits.
  • D. Close Procurements relies on procurement audits, procurement negotiations and the records management system.

Question 256

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

  • A. Close Procurements.
  • B. Control Procurements.
  • C. Plan Procurements.
  • D. Conduct Procurements.
Show answer and explanation ▾

Correct answer: D

Conduct Procurements is the process of obtaining seller responses, selecting a seller and awarding a contract. It aligns internal and external stakeholder expectations through established agreements.

Why the other options are wrong:

  • A. Close Procurements completes each procurement and documents agreements for future reference.
  • B. Control Procurements manages procurement relationships, monitors contract performance and makes changes as needed.
  • C. Planning procurements documents purchasing decisions, specifies the approach and identifies potential sellers.

Question 257

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

  • A. Business case
  • B. Work breakdown structure
  • C. Requirements documentation
  • D. Risk register
Show answer and explanation ▾

Correct answer: C

Requirements documentation describes how individual requirements meet the business need for the project. Its typical components include levels of service, acceptance criteria and impacts to other organizational areas.

Why the other options are wrong:

  • A. A business case gives the justification for the investment, such as the business need and cost-benefit analysis.
  • B. A work breakdown structure is a hierarchical decomposition of the total scope of work.
  • D. A risk register records identified risks, their analysis and the planned responses.

Question 258

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

  • A. Estimate Costs
  • B. Control Costs
  • C. Plan Cost Management
  • D. Determine Budget
Show answer and explanation ▾

Correct answer: D

Funding limit reconciliation is a tool and technique of Determine Budget. It compares the planned expenditure of funds with any limits on the commitment of funds, and a variance may require work to be rescheduled to level out the rate of spending.

Why the other options are wrong:

  • A. Estimate Costs uses estimating techniques such as analogous, parametric, bottom-up and three-point estimating.
  • B. Control Costs uses techniques such as earned value management, forecasting and the to-complete performance index.
  • C. Plan Cost Management uses expert judgment, analytical techniques and meetings.

Question 259

In complex projects/ initiating processes should be completed:

  • A. Within a work package.
  • B. In each phase of the project.
  • C. To estimate schedule constraints.
  • D. To estimate resource allocations.
Show answer and explanation ▾

Correct answer: B

Large and complex projects are divided into phases, and the initiating processes are carried out in each phase. Repeating them keeps the project focused on the business need it was undertaken to address.

Why the other options are wrong:

  • A. A work package is the lowest level of the WBS and is not where initiating processes are performed.
  • C. Estimating schedule constraints is planning work, not the purpose of the initiating processes.
  • D. Estimating resource allocations is planning work, not the purpose of the initiating processes.

Question 260

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

  • A. Communication models.
  • B. Stakeholder participation.
  • C. Expert judgment
  • D. Enterprise environmental factors.
Show answer and explanation ▾

Correct answer: C

Expert judgment is expertise provided by any group or person with specialized knowledge or training. Consultants and professional and industry groups are named sources of it, so asking them for recommendations is relying on expert judgment.

Why the other options are wrong:

  • A. Communication models describe how information passes between a sender and a receiver.
  • B. Stakeholder participation concerns the involvement of people affected by the project, not advice sought from outside specialists.
  • D. Enterprise environmental factors are conditions outside the team's control that influence the project.

Question 261

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

  • A. appetite
  • B. tolerance
  • C. threshold
  • D. management
Show answer and explanation ▾

Correct answer: B

Risk tolerance is the degree, amount or volume of risk that an organization or individual will withstand.

Why the other options are wrong:

  • A. Risk appetite is the degree of uncertainty an entity is willing to take on in anticipation of a reward.
  • C. Risk threshold is the level of uncertainty or impact at which a stakeholder has a specific interest: below it the risk is accepted, above it the risk is not tolerated.
  • D. Risk management is the set of processes for planning, identifying, analyzing, responding to and controlling risk.

That was 261 of 704.

The full GAQM APM-001 pack has all 704 questions, each with the answer, the explanation and why the other options are wrong, plus a questions-only copy for timed runs. $39.00 USD, paid once, with free monthly updates and a pass-or-your-money-back guarantee.

Get the full pack

Not ready yet? Get the first 277 free as one PDF by email. Get the Half Pack →

About the APM-001 exam

These 261 GAQM APM-001 questions are free here. The free PDF has 277, free by email.

They are drawn from the same bank as the full APM-001 pack, which has 704 questions in total.