EXIN Agile Scrum Master Practice Questions with Explanations

Free EXIN Agile Scrum Master practice questions. 12 of them, each with the correct answer, a full explanation, and the reason every other option is wrong.

Agile Scrum Master practice questions

Question 1

Your team uses Story Points to estimate User stories.

Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other Stories.

How should you address this?

  • A. Complete incomplete Stories
  • B. Increase or re-estimate Velocity
  • C. Re-estimate all small Stories
  • D. Switch to using Ideal days
Show answer and explanation ▾

Correct answer: A

Story points are relative estimates, and Velocity evens out individual estimating errors over time. In the middle of a Sprint the team should keep its focus on finishing the Stories that are not yet complete, and leave any re-estimation for later planning.

Why the other options are wrong:

  • B. Velocity is measured from the work the team completes; it is not something to raise or re-estimate during a Sprint.
  • C. Re-estimating all small Stories in the middle of a Sprint takes time away from the work and does not help finish it.
  • D. Changing the estimating unit to Ideal days does not fix Stories that are sized inconsistently against each other.

Question 2

Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?

  • A. This conflicts with the principle of Self-Management of the Development Team.
  • B. The Product Owner does not know the velocity of the Development Team.
  • C. The Scrum Master is responsible for the velocity of the Development Team.
  • D. The Scrum Master and the Product Owner must agree on the workload of the Development Team.
Show answer and explanation ▾

Correct answer: A

A Scrum Development Team decides how much work it can take on in a Sprint. If the Product Owner set the workload, it would break the team's self-management.

Why the other options are wrong:

  • B. The issue is the team's autonomy, not what the Product Owner knows about velocity.
  • C. The Scrum Master is not responsible for the team's velocity.
  • D. The workload is not negotiated between the Scrum Master and Product Owner.

Question 3

What is one of the most difficult challenges you face when transitioning your software development team to Scrum?

  • A. Introducing certain technical practices
  • B. Team members may already have their hands full
  • C. Too rapid improvements are possible
Show answer and explanation ▾

Correct answer: B

People who are asked to change how they work are usually already fully occupied with their current tasks. Finding the time and energy to learn and apply Scrum on top of a full workload is one of the hardest parts of a transition.

Why the other options are wrong:

  • A. Introducing technical practices is part of the transition but is not the challenge singled out as most difficult.
  • C. Improving too quickly is not a difficulty teams face when they move to Scrum.

Question 4

Your organization found that the Product Owner is consistently under more pressure than the developments and other participants in the project.

What is common solution for that?

  • A. Compiling a list with Product Owner tasks
  • B. Rotating the Scrum Master role
  • C. Using a Product Owner team
Show answer and explanation ▾

Correct answer: A

Writing down everything the Product Owner is expected to do makes the workload visible. With that list, the team and the organization can see which tasks really need the Product Owner and which can be shared or handed to others.

Why the other options are wrong:

  • B. Rotating the Scrum Master role does nothing to reduce the Product Owner's workload.
  • C. A Product Owner team is not the common remedy described for a single Product Owner who is under pressure.

Question 5

A Scrum Team suggests to have a project with 3 Sprints of 2 weeks, while the customer suggests 1 Sprint of 6 weeks.

What is the greatest advantage of having 3 Sprints of 2 weeks?

  • A. The customer has to invest fewer time.
  • B. The team can inspect and adapt 2 times.
  • C. The team delivers more Story Points.
Show answer and explanation ▾

Correct answer: C

Short Sprints give the team a clear goal and a finish line every two weeks, which keeps the pace steady and the work focused. Over the same six weeks, the team completes more work than it would in one long Sprint.

Why the other options are wrong:

  • A. Three Sprints mean three Sprint Reviews, so the customer invests more time, not less.
  • B. The number of inspection points is not the greatest advantage of the shorter Sprints in this comparison.

Question 6

Kevin is a Product Owner for a retail organization. The Product Backlog for his immense marketing tool project has 200 Product Backlog Items.

Into what should he group the smaller Stories together?

  • A. Epics
  • B. Themes
  • C. User Stories
  • D. Views
Show answer and explanation ▾

Correct answer: B

A theme is a group of related user stories. Grouping the smaller Stories into themes keeps a Product Backlog of 200 items manageable, because related Stories can be handled and prioritized together.

Why the other options are wrong:

  • A. An Epic is a single large story that is later split, not a group of smaller Stories.
  • C. User Stories are the items being grouped, not the grouping.
  • D. Views are not a Product Backlog grouping concept in Scrum.

Question 7

Company X-AppGo is very interested in getting the benefits of both the ITIL® Framework and the Agile principles. They want to establish a disciplined service based approach, while reducing lead team in releasing application enhancements and improvements to their customer base.

Based on the above scenario, which would be the best processes to start integrating Agile into the ITIL® Framework?

  • A. Service Design and Service Transition
  • B. Service Strategy and Service Design
  • C. Service Strategy and Service Operation
  • D. Service Transition and Service Operation
Show answer and explanation ▾

Correct answer: D

The company wants to shorten the lead time for releasing enhancements to customers. Releases are built, tested and deployed in Service Transition and then run and supported in Service Operation, so these are the processes where Agile practices have the most direct effect.

Why the other options are wrong:

  • A. Service Design shapes new services but does not cover running and supporting released enhancements.
  • B. Service Strategy and Service Design are furthest from the release and deployment work the company wants to speed up.
  • C. Service Strategy sets direction and does not deal with releasing application enhancements.

Question 8

You are a project manager for a midsize software company, which still uses the Waterfall model. Your customer wants a new software project.

When should you consider the use of Agile?

  • A. The product definition is stable and will not change.
  • B. The scope lacks specificity and is unlikely to remain stable.
  • C. The user technology to be developed is understood.
  • D. There are almost no ambiguous requirements.
Show answer and explanation ▾

Correct answer: B

Agile works best when requirements are unclear and expected to change. Short iterations and frequent feedback let the scope be refined as the project goes on, which a Waterfall plan handles poorly.

Why the other options are wrong:

  • A. A stable product definition that will not change suits a plan-driven approach such as Waterfall.
  • C. Well understood technology removes much of the uncertainty that Agile is meant to handle.
  • D. A project with almost no ambiguous requirements can be planned up front.

Question 9

Which information Radiator can the team use best during the Sprint to track the work?

  • A. Gantt chart
  • B. Product Backlog
  • C. Release Burn Up
  • D. Task board
Show answer and explanation ▾

Correct answer: D

A task board shows every task in the Sprint and its current state, such as to do, in progress and done. It is visible to the whole team and is updated daily, so it is the best way to track work during the Sprint.

Why the other options are wrong:

  • A. A Gantt chart is a traditional planning tool and is not used to track Sprint work in Scrum.
  • B. The Product Backlog lists everything still to be built, not the progress of work in the current Sprint.
  • C. A Release Burn Up shows progress toward a release across Sprints, not the work inside one Sprint.

Question 10

The Product Owner informs the team that the release will be date-driven.

What kind of buffer for uncertainty is most important to use in this type of release?

  • A. Budget buffer
  • B. Feature buffer
  • C. Padding buffer
  • D. Schedule buffer
Show answer and explanation ▾

Correct answer: D

In a date-driven release the delivery date is what must be protected. A schedule buffer sets aside time for the uncertainty in the estimates, so the team can still meet the date when work takes longer than expected.

Why the other options are wrong:

  • A. A budget buffer protects cost, not the delivery date.
  • B. A feature buffer works by leaving lower priority features out, which is a different measure from reserving time before the date.
  • C. Padding individual estimates hides uncertainty instead of managing it in one visible buffer.

Question 11

Your company wants to be highly responsive to bug reports or feature requests from your customers. For your customers it is more important to have confidence in the date by which you promise to have a fix than an occasional quick fix.

What part of Scrum allows you to have this predictability?

  • A. Agile planning
  • B. The Velocity of the Team
  • C. Working in strict timeboxes
Show answer and explanation ▾

Correct answer: C

Sprints have a fixed length and always end on time. Because every Sprint finishes on a known date, the company can promise customers when a fix will be delivered and be confident of meeting that date.

Why the other options are wrong:

  • A. Agile planning sets what goes into a Sprint, but the dependable end date comes from the fixed timebox.
  • B. Velocity shows how much work fits in a Sprint, not the date on which work is delivered.

Question 12

As items are developed and removed from the top of the Product Backlog, the Product Backlog iceberg develops a flat spot at the top and loses its shape.

What would be a necessary measure to counter this effect?

  • A. Creating a chart of the number of Product Backlog Items
  • B. Grooming the Product Backlog
  • C. Prioritizing the Product Backlog
  • D. Using an improvement Backlog
Show answer and explanation ▾

Correct answer: B

Items at the top of the Product Backlog are small and detailed, while lower items are larger and vaguer. As top items are completed, grooming breaks the next large items into small, detailed ones so the top of the Backlog is ready for the coming Sprints.

Why the other options are wrong:

  • A. Charting the number of Product Backlog Items does not split large items into smaller ones.
  • C. Prioritizing changes the order of items but does not add the detail needed at the top.
  • D. An improvement Backlog holds process improvements, not Product Backlog Items.

That was 12 of 39.

The full EXIN Agile Scrum Master pack has all 39 questions, each with the answer, the explanation and why the other options are wrong, plus a questions-only copy for timed runs. $39.00 USD, paid once, with free monthly updates and a pass-or-your-money-back guarantee.

Get the full pack

Not ready yet? Get the first 12 free as one PDF by email. Get the Half Pack →

About the Agile Scrum Master exam

These 12 EXIN Agile Scrum Master questions are free here, and as a free PDF by email.

They are drawn from the same bank as the full Agile Scrum Master pack, which has 39 questions in total.