Question 1
How many Start Stages can a sub-page in a Process have?
- A. 0
- B. 1
- C. 2
- D. Any Number
Show answer and explanation ▾
Correct answer: B
Every page in a Blue Prism process, including each sub-page, has exactly one Start stage. It is the single entry point where the page begins and where its input parameters are defined.
Why the other options are wrong:
- A. A sub-page cannot run without a Start stage, so it cannot have none.
- C. Two Start stages would give the page two entry points; Blue Prism allows only one per page.
- D. The number of Start stages is fixed at one per page, unlike End stages, of which a page can have several.
Question 2
You identify an element in Application Modeller but when you highlight or use that element Blue Prism gives you an error message saying that duplicate elements were found.
Which of the following statements is true?
- A. It is common for duplicate elements to be found based upon the attributes that are ticked by default using the Blue Prism product. Time needs to be spent experimenting with the attribute ticks until a unique, reliable, and consistent selection of attributes are found.
- B. It will not be possible to interface with the element in a unique way. You will need to use Surface Automation techniques for this element.
- C. A code stage interface will need to be created and used for this application, this will give you more flexibility to interact with the application elements.
- D. You will need to make the attributes you have selected dynamic. This will allow your flow to loop around, incrementing the attribute value until the correct element is found and used. D
Show answer and explanation ▾
Correct answer: A
The attributes ticked by default after spying often match more than one element. The fix is to adjust which attributes are ticked until the set identifies the element uniquely and stays reliable each time the application is used.
Why the other options are wrong:
- B. A duplicate match is normally solved by refining attributes, so Surface Automation is not required.
- C. A code stage is not needed to resolve a duplicate match in Application Modeller.
- D. Looping through dynamic attribute values is not how a duplicate match is resolved.
Question 3
Which of the following statements about Business Objects is true?
- A. It is Blue Prism best practice to include business rules within Business Objects
- B. A Business Object is configured in the Studio area of Blue Prism
- C. A Business Object can be exposed to Control Room
- D. Logging of individual stages is not configurable in Business Objects
Show answer and explanation ▾
Correct answer: B
Business Objects are created and edited in Object Studio, which is opened from the Studio area of Blue Prism alongside processes.
Why the other options are wrong:
- A. Best practice keeps business rules in the process, with objects limited to application interaction.
- C. Processes are published to Control Room; Business Objects are not run from there.
- D. Stage logging can be set on individual stages in a Business Object.
Question 4
A Blue Prism solution works fine when developing and testing it in Process and Object studio but when it is running in Control Room exceptions occur because of screen elements not being found.
What is the most likely cause?
- A. The most likely cause for the errors is that your application has changed.
- B. The most likely cause for the errors seen in Control Room is that best practice use of wait stages has not been followed.
- C. The most likely cause for the errors is that the Object Studio action has not been published and therefore cannot be used by the Process in control room.
- D. The most likely cause for the exceptions is that best practice exception handling has not been incorporated into the Process.
Show answer and explanation ▾
Correct answer: B
A session in Control Room runs much faster than stepping through in Studio. Without conditional wait stages the flow tries to use elements before the application has finished loading them, which produces element not found exceptions only at full speed.
Why the other options are wrong:
- A. A changed application would also fail in Studio, not only in Control Room.
- C. An unpublished action could not be called at all, which is a different failure from elements not being found.
- D. Exception handling deals with errors after they occur and does not explain why elements are missing at run time.
Question 5
You identify an element in Application Modeller and it highlights uniquely and can be used in your object flow diagram. The next day you find that Blue Prism cannot no longer identify the same element, your object flow is giving you "˜Element not found' exceptions.
Which of the following statements is true?
- A. This must be an environment issue. The Blue Prism environment must be consistent and persistent, and an element that worked one day and does not work the next day suggests the environment is changeable. The IT team supporting the environment needs to be contacted to fix the problem.
- B. The Blue Prism product support team should be contacted to report the issue. This signifies an inconsistency in how the Blue Prism product is working which needs to be fixed.
- C. This suggests that Best Practice exception handling has not been implemented in the object. A retry loop around the object stages that are using the element will probably fix the problem.
- D. It is common for consistency issues to be found during configuration/development testing. The most likely cause is that an attribute has been selected for the element that is changeable, such as a window title with a date, or a URL. The developer needs to ensure that any changeable attributes are unticked. D
Show answer and explanation ▾
Correct answer: D
An element that matched yesterday and fails today usually has a ticked attribute whose value changes, such as a window title containing a date or a URL. Unticking the changeable attributes leaves a set that matches consistently.
Why the other options are wrong:
- A. A changing attribute value is the usual cause, not an unstable environment.
- B. This is normal development behavior, not a product fault to report to support.
- C. A retry loop would repeat the same failed match because the attribute value is still different.
Question 6
When automating a Windows application what type of stage is configured to perform a Global Send Key Events?
- A. Notes Stage
- B. Read Stage
- C. Write Stage
- D. Navigate Stage
Show answer and explanation ▾
Correct answer: D
Sending global keystrokes is one of the actions offered by a Navigate stage. It is selected against the application's root element so the input goes to the active window.
Why the other options are wrong:
- A. A Note stage only holds descriptive text on the diagram.
- B. A Read stage retrieves data from elements and does not send input.
- C. A Write stage puts a value directly into an element and is not where this action is configured.
Question 7
What is the syntax for using a collection field in an expression?
- A. Like this MyCollection(MyField)
- B. Like this MyCollection[MyField]
- C. Like this [MyCollection[MyField]]
- D. Like this MyCollection.MyField
- E. Like this [MyCollection.MyField]
Show answer and explanation ▾
Correct answer: E
A collection field is referenced with the collection name, a dot and the field name, all inside one pair of square brackets, for example [MyCollection.MyField].
Why the other options are wrong:
- A. Round brackets are used for function arguments, not for collection fields.
- B. The whole reference must sit inside square brackets, with a dot before the field name.
- C. Nested square brackets are not valid; a dot separates the collection and the field.
- D. Without square brackets the reference is not recognized as a data item.
Question 8
When considering an element's attributes in Application Modeller which of the following statements are true?
- A. The attributes are provided to Blue Prism by the Target System
- B. The initial selection of attributes made by Blue Prism will always be the optimum attribute set for the element
- C. The list of attributes may vary from application type to application type
- D. Selected attributes are shown as ticks in the Match column of Application Modeller
Show answer and explanation ▾
Correct answer: D
In Application Modeller each attribute has a checkbox in the Match column. The ticked attributes are the ones Blue Prism uses to find the element at run time.
Why the other options are wrong:
- A. This concerns where attribute values originate, not how the chosen set is indicated in Application Modeller.
- B. The default selection is only a starting point and often needs adjusting.
- C. This concerns differences between application types, not how selected attributes are indicated.
Question 9
How can a session variable value be updated when a process is running? (Select all that apply.)
- A. By using the Internal "" Session Variables business object.
- B. By pausing the Session Variables work queue.
- C. By updating the value in Credential Manager.
- D. By updating the value in Control Room.
Show answer and explanation ▾
Correct answer: D
A data item exposed as a session variable appears against the running session in Control Room, where a controller can view it and change its value while the process is running.
Why the other options are wrong:
- A. This is not the route used to change a session variable during a run.
- B. Session variables are not held in a work queue.
- C. Credential Manager stores credentials, not session variables.
Question 10
If you change a session variable when will the new value be available to the process?
- A. Immediately
- B. Next time a new case is taken from a WQ
- C. Next time resource PC starts
- D. Next time the process starts
Show answer and explanation ▾
Correct answer: A
A session variable is read live from the running session. When its value is changed in Control Room, the process sees the new value the next time it reads the data item, without any restart.
Why the other options are wrong:
- B. The new value does not wait for the next queue item.
- C. No restart of the resource PC is needed.
- D. The change applies to the session that is already running, not only to the next one.
Question 11
When a process is running in Control Room which of the following functions within the process can be accessed from Control Room to request the process to stop?
- A. Stop ()
- B. IsStopRequested?
- C. IsStopRequested ()
- D. StopNow ()
- E. Stop?
- F. StopNow?
Show answer and explanation ▾
Correct answer: C
IsStopRequested() is the function a process calls, usually in a decision stage, to check whether a controller has chosen Request Stop for the session in Control Room. It returns True once a stop has been requested, letting the process finish cleanly.
Why the other options are wrong:
- A. Stop() is not a Blue Prism function.
- B. The function is written with brackets, not a question mark.
- D. StopNow() is not a Blue Prism function.
- E. Stop? is not a Blue Prism function.
- F. StopNow? is not a Blue Prism function.
Question 12
What is the Blue Prism Application Navigator?
- A. It is the spy tool that you drag around the application to identify attributes.
- B. It is part of the zoom tool in Process and Object Studio that allows you to instantly jump to different parts of the process map.
- C. It is the Studio list side-bar of Process and Objects.
- D. It is Application Modeller functionality to create an application's entire element tree that when selected will highlight individual elements in the application. B
Show answer and explanation ▾
Correct answer: D
Application Navigator is part of Application Modeller. It builds a tree of all the elements in the connected application, and selecting an entry in the tree highlights that element in the application so it can be added to the model.
Why the other options are wrong:
- A. The spy tool is a separate identification feature.
- B. It is not a zoom or diagram navigation feature of the Studio.
- C. It is not the list of processes and objects shown in the Studio.
Question 13
A Blue Prism solution interfaces with an internet application called HappyWeb. There is a test website available for development, and a training site available for user acceptance testing, and there is the production site available for processing live cases in HappyWeb.
Which of the following is true?
- A. All development and testing MUST be done using the production site. This is because the test and training websites might not mirror production exactly.
- B. A local text file should be used to easily configure the details of the HappyWeb website to be used in each Blue Prism environment.
- C. An Environment variable should be used to store the HappyWeb URL.
- D. Three different versions of object that launches the HappyWeb website will need to be created and maintained, one for each environment.
Show answer and explanation ▾
Correct answer: A
Test and training sites can differ from the live site, so elements spied and flows proven against them are not guaranteed to behave the same way in production.
Why the other options are wrong:
- B. A local text file is not the recommended way to hold configuration.
- C. This is not the statement that applies to this scenario.
- D. Maintaining three copies of the same object is not good practice.
Question 14
A process has been created but it is not listed in Control Room. The following reasons have been suggested.
1. The process uses objects with different run modes
2. The process has not been published
3. Process validation shows more than 99 errors
4. The user does not have privileges to run processes in Control Room
Which of the above could cause the process not to be visible in Control Room?
- A. 1 and 2
- B. 2 only
- C. 2 and 3
- D. 1 and 4
Show answer and explanation ▾
Correct answer: B
Only published processes are listed in Control Room. A process that has been saved but not published stays out of the list, whatever its objects, validation results or the user's run permissions.
Why the other options are wrong:
- A. Mixed run modes affect what can run together, not whether the process is listed.
- C. Validation errors do not remove a process from the Control Room list.
- D. Run mode and run privileges do not decide whether a published process is listed.
Question 15
When building a solution to use Tags within a Work Queue, which of the following statements is correct true?
- A. Adding a tag requires an item to be locked
- B. Adding a tag requires an item to be locked if there are multiple resources working the same queue
- C. Adding a tag does not require an item to be locked
Show answer and explanation ▾
Correct answer: C
The Tag Item action only needs the item ID. A tag can be added to an item whether or not the item is currently locked by a session.
Why the other options are wrong:
- A. An item does not have to be locked for a tag to be added.
- B. The number of resources working the queue does not create a need for a lock when tagging.
Question 16
According to Blue Prism best practice which of the following information would be appropriate to store in a Work Queue tag? (select 3 responses)
- A. Something that identifies the type of work that was performed. Example tags might be: Funds Transferred, SIM Card Requested, Account Closed, Account Suspended, Account Noted
- B. Something that identifies exact datetime of a step in the process. Example of tags might include: Account Closed 20/03/2017 12:12:16, Work Completed 20/03/2017 12:12:16, Request Loaded 20/03/2017 12:12:16
- C. Something that identifies the source of work. Example of tags might include: Email, Web Form, Excel, Adhoc, Database
- D. Something that identifies the client record to make work queue items easier to search. Example tags might be a phone number, customer reference number or ID, customer full name. For example: +4407994446767, 00023231A, Mr John A Smith.
- E. Something that identifies the type of process scenario. Example of tags might include: Invalid Product, Unrecognized customer, Goneaway Marker, Invalid Status
- F. Details of an exception that has occurred. For example: The Login Screen was not found.
Show answer and explanation ▾
Correct answer: A, C, E
Tags are for grouping items into a small number of categories that can be counted and filtered. The type of work done, the source of the work and the process scenario all give a short list of repeatable values, which is what makes them useful as tags.
Why the other options are wrong:
- B. An exact date and time makes almost every tag unique, which defeats grouping.
- D. A customer reference is unique to each item and belongs in the item's identifying field or data, not in a tag.
- F. Exception detail belongs in the exception reason of the item, not in a tag.
Question 17
The Work Queue "Customer Onboarding" has a number of Pending Items which may be tagged as "Domestic", "Retail" or "Business". There is also a tag for the 8 digit product code formatted as "Product Code: {product code}" e.g. Product Code: CA123456.
What is the correct configuration to get the next item from the queue that:
- Isn't applying for a loan product i.e. Product Code doesn't begin with "LN" And
- Is a domestic customer
- A. Configure "Domestic; -Product Code: LN*" in the Tag Filter parameter
- B. Configure "Domestic; -Product Code: LN?" in the Tag Filter parameter
- C. Configure "Domestic and Product Code: <> LN?" in the Tag Filter parameter
- D. Configure "Domestic + [Product Code] <> LN*" in the Tag Filter parameter
Show answer and explanation ▾
Correct answer: A
Terms in a tag filter are separated by semicolons and all of them must match. A leading minus excludes items with a matching tag, and the asterisk matches any run of characters, so the filter returns Domestic items without a product code starting LN.
Why the other options are wrong:
- B. A question mark matches a single character, so it would not match the six characters that follow LN.
- C. The words and, and the <> operator, are not part of tag filter syntax.
- D. Square brackets, + as a joiner and <> are not part of tag filter syntax.
Question 18
Which of the following statements regarding the use of Work Queues are correct? (select 2 responses)
- A. Control Room allows filtering of the displayed queue items using exact tags and by using wildcards
- B. Wildcards are not allowed in the Tag Filter property of the Work Queues business object Get Next Item action
- C. Work Queue item Status can only be set to Completed or Exception
- D. Tags can be used allow flexibility in the order items are worked within a single Work Queue
Show answer and explanation ▾
Correct answer: A, D
Queue Management in Control Room can filter the item list by an exact tag or by a tag pattern with wildcards. In a process, the Tag Filter on Get Next Item lets one queue be worked in a chosen order, for example one category of item before another.
Why the other options are wrong:
- B. The Tag Filter on Get Next Item accepts wildcards.
- C. Status is a free text value that a process can set to anything useful.
Question 19
The Work Queue "˜Account Closure has a number of Pending Items which may be tagged as "Current", "Saving" or "Loan".
What is the correct configuration to get the next item from the queue that is tagged either "Current" or "Loan"?
- A. Configure "Current or Loan" in the Tag Filer parameter
- B. Configure "-Saving" in the Tag Filter parameter
- C. Configure "Current; Loan" in the Tag Filter parameter
- D. Configure "Current + Loan" in the Tag Filter parameter
Show answer and explanation ▾
Correct answer: B
Terms in a tag filter are separated by semicolons and are all applied together, so listing two tags finds only items that carry both. Every item here is tagged Current, Saving or Loan, so excluding Saving with a leading minus returns the Current and Loan items.
Why the other options are wrong:
- A. The filter has no or operator, so this is read as one literal tag.
- C. Terms separated by a semicolon must all match, so this needs both tags on the same item.
- D. A plus sign is only a prefix on a single term and does not join two tags as alternatives.
Question 20
Which of the following can you perform in Control Room?
- A. Refresh a Work Queue
- B. Create a Work Queue
- C. Encrypt a Work Queue
- D. Rename a Work Queue
Show answer and explanation ▾
Correct answer: A
Control Room is where queues and their items are monitored, so refreshing the view of a queue is done there. Creating, renaming and encrypting a queue are configuration tasks carried out in System Manager under Workflow.
Why the other options are wrong:
- B. Work queues are created in System Manager, not in Control Room.
- C. Queue encryption is set in System Manager, not in Control Room.
- D. A queue is renamed in System Manager by editing its Name field, not in Control Room.
Question 21
In which of these scenarios is it ok not to use a Blue Prism work queue as part of your Blue Prism solution?
- A. A Blue Prism work queue is not required for simple linear processes that do not work multiple cases.
- B. A Blue Prism work queue should always be used. It eliminates the risk of contention and allows you to gracefully pause the queue at any time.
- C. A Blue Prism work queue is not required if the business process interfaces with a Work List system with-in-built capability to ensure multiple users cannot work the same case at the same time.
- D. A Blue Prism Work Queue decreases the scalability of the solution and therefore should only be used for complex scenarios such as multiday processing.
Show answer and explanation ▾
Correct answer: C
A work queue stops two sessions from working the same case by locking each item. When the business system already has a work list that prevents two users from taking the same case, that protection exists outside Blue Prism and a work queue is not essential.
Why the other options are wrong:
- A. This is not the scenario in which Blue Prism guidance allows a work queue to be left out.
- B. A work queue is recommended in most solutions but is not mandatory in every one.
- D. Work queues increase scalability by letting several resources share the same work.
Question 22
How many End Stages can a sub-page in a Process have?
- A. 0
- B. 1
- C. 2
- D. Any Number
Show answer and explanation ▾
Correct answer: B
A sub-page runs from its Start stage to its End stage, where control and any output parameters pass back to the calling page.
Why the other options are wrong:
- A. A sub-page needs an End stage to return to the calling page.
- C. This is not the number that applies to a sub-page.
- D. This is not the number that applies to a sub-page.
Question 23
The Work Queue "Customer Onboarding" has a number of Pending Items which may be tagged as "Domestic", "Retail" or "Business".
What is the correct configuration to get the next item from the queue that is tagged either "Retail" or "Business"?
- A. Configure "-Domestic" in the Tag Filter parameter
- B. Configure "Retail or Business" in the Tag Filter parameter
- C. Configure "Retail;Business" in the Tag Filter parameter
- D. Configure "Retail+Business' in the Tag Filter parameter
Show answer and explanation ▾
Correct answer: A
Terms in a tag filter are separated by semicolons and are all applied together, so listing two tags finds only items that carry both. Every item here is tagged Domestic, Retail or Business, so excluding Domestic with a leading minus returns the Retail and Business items.
Why the other options are wrong:
- B. The filter has no or operator, so this is read as one literal tag.
- C. Terms separated by a semicolon must all match, so this needs both tags on the same item.
- D. A plus sign is only a prefix on a single term and does not join two tags as alternatives.
Question 24
Which of the following can you perform in the System->Workflow area of Blue Prism? (Choose two.)
- A. View the contents of a Work Queue.
- B. Refresh a Work Queue.
- C. Encrypt a Work Queue.
- D. Create a Work Queue.
Show answer and explanation ▾
Correct answer: C, D
The Workflow section of System Manager is where work queues are created and configured. The same screen holds the queue's encryption setting, so a queue can be set there to encrypt its item data.
Why the other options are wrong:
- A. Queue contents are viewed in Control Room.
- B. The item list is refreshed in Control Room, not in System Manager.
Question 25
How would you run a Blue Prism Process on a virtual Digital Worker?
- A. Through Control Room
- B. Through the Digital Worker Management Console
- C. Through System Manager
- D. Through Process Studio
- E. Through Object Studio
Show answer and explanation ▾
Correct answer: A
A process is run on a resource from Control Room. A session is created by dragging the process onto the required resource, and the pending session is then started from the session list.
Why the other options are wrong:
- B. This is not where a process is run.
- C. System Manager is for configuration, not for running processes.
- D. Process Studio is for building a process and simulating its execution during development, not for running it on a Digital Worker.
- E. Object Studio is for building and testing objects, not for running processes.
That was 25 of 190.
The full Blue Prism AD01 pack has all 190 questions, each with the answer, the explanation and why the other options are wrong, plus a questions-only copy for timed runs. $39.00 USD, paid once, with free monthly updates and a pass-or-your-money-back guarantee.
Get the full packNot ready yet? Get the first 61 free as one PDF by email. Get the Half Pack →
About the AD01 exam
These 25 Blue Prism AD01 questions are free here. The free PDF has 61, free by email.
They are drawn from the same bank as the full AD01 pack, which has 190 questions in total.